Decision The Council agreed that – 1. Ardchattan Primary School discontinue as a school on a temporary basis and that the building be retained for two years on a care and maintenance basis. 2. If there are no registered pupils by the close of the registration period for session 2016/17, the Council consult formally on the future of school provision at Ardchattan . 3. The community will have prearranged access to the building to support community functions. (Reference: Report by Executive Director – Community Services dated April 2014, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1As from June 2014 there will be no pupils in Ardchattan Primary School. At the time of writing there are no preschool age children in the catchment area for the school who have registered to attend the school.
1.2Considerable uncertainty exists as to what will happen to staff and the school building and it is proposed that this paper will clarify the Education Service plan.
1.3It is proposed that the Ardchattan Primary School building be retained on a care and maintenance basis for a period of two years.
1.4If there are no registered pupils by the close of the registration period for session 2016/17, that the Council should consult formally on the future of school provision at Ardchattan.
Recommendations
2.1The Council is asked to agree to the proposal that: 1) Ardchattan Primary School discontinue as a school on a temporary basis and that the building be retained for two years on a care and maintenance basis 2) If there are no registered pupils by the close of the registration period for session 2016/17, the Council consult formally on the future of school provision at Ardchattan 3) The community will have prearranged access to the building to support community functions.
3.0DETAIL
3.1The roll in Ardchattan primary has declined over the last few years and as from June 2014 there will be no pupils in the school. At the time of writing there are no preschool age children in the catchment area for the school who have registered to attend the school.
3.2All Members of staff from Ardchattan Primary School will be redeployed in other posts within the authority. A meeting has been held with staff involved to provide information on the process and ongoing dialogue will take place during the period of redeployment. 3.3 In the event of a school age pupil moving to live within the catchment area for Ardchattan Primary School and seeking to attend this school the present situation is that the school would require to re-open at the next appropriate session.
3.4It is recognised that the school is the only local community facility available and supports a few key community events during the course of the year. There are considerable travel distances to access similar facilities elsewhere and it would be proposed that the school remain available during this period for those events. Council staff will seek further discussions with local community organisations regarding the arrangements for that access.
4.0CONCLUSION
4.1Ardchattan Primary School will discontinue as a school on a temporary basis at the end of June 2014 and the property will be managed on a care and maintenance basis.
5.0IMPLICATIONS 5.1 Policy - None 5.2 Financial - The school property will be managed on a care and maintenance basis however there is likely to be a saving in overall property costs. The council will seek to redeploy staff in line with the staffing standard linked to pupil roll. 5.3 Legal There is a requirement to comply with the Schools (Consultation) (Scotland) Act 2010 when considering any proposal in relation to a school. 5.4 HR - All efforts will be made to redeploy staff in line with the council’s redeployment procedures. 5.5 Equalities - None
5.6Risk - There are identified risks to the property which requires to be managed on a care and maintenance basis
5.7Customer Service – Consideration has been given to supporting customers seeking community lets of the property
Cleland Sneddon Executive Director of Community Services 13 March 2014
For further information contact: Carol Evans, Head of Service (Education), Dalintart Drive, Oban, PA34
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.