Decision The Council – 1. Noted the results of the public consultation process; and 2. Agreed a new build of Kirn Primary school on its current site to an A rating in terms of condition and suitability as set out in paragraph 3.15. Councillor Robb having moved an amendment which failed to find a seconder required his dissent from the foregoing decision to be recorded. (Reference: Report by Executive Director – Community Services dated 31 March 2014, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report updates the Council on the outcome of the agreed public consultation on the two shortlisted options for primary and Pre-5 provision in the Dunoon area.
1.2It outlines points for consideration in progressing improvements in the school estate. Scottish Government funding is available for a limited time and on particular criteria only; the local community preference overall, expressed through consultation, is against a shared campus and for retaining three separate schools; the cost of refurbishing or rebuilding all three schools is beyond the resources of the Council and would not qualify for the same level of Scottish Government funding.
1.3The way forward recommended will secure Scottish Government funding for school improvement in Dunoon, takes account of the community’s preference regarding a shared campus, and through a combination of Scottish Government and Council funding, will allow significant investment in the school estate.
Recommendation
2.1It is recommended that the Council:
2.1.1 Note the results of the public consultation process; and
2.1.2 Agree a new build of Kirn Primary school on its current site to an A rating in terms of condition and suitability as set out in paragraph 3.15.
Background
3.1In 2009, the Council was granted funding under Scotland’s Schools for the Future (SSF) programme for a new shared primary and Pre-5 school campus in Dunoon. The Council’s original proposal was approved on the basis that 3 schools came together to form one campus, subject only to the positive outcome of statutory consultation.
The proposal was based on construction of a new shared primary campus school with pre-school and wrap around care nursery facility. It
1 was proposed that the new campus would include Dunoon, Kirn and St Mun’s Primary schools with associated Pre-5 provision, and that the new campus would be built on the existing site of Kirn Primary school and adjacent playing fields west of the Kirn school site.
A strategic brief for the new primary school campus was developed to the stage where an application for Planning consent in Principle could be lodged.
3.2Prior to the lodging of that application, the Council, at its meeting on 28 June 2012, instructed a review to be carried out to establish whether there were other options that may be preferred in regard to the new build, refurbishment, amalgamation or otherwise of the current Dunoon, Kirn and St Mun’s Primary schools and Clyde Cottage Nursery.
3.3Following the Council’s decision to review this process, GMA/Ryder were commissioned to carry out a review of primary school buildings in Dunoon and to explore options for the future provision of primary and Pre-5 education.
3.4GMA/Ryder arrived at 8 options. These were narrowed down to 7 to ensure that each option addressed the improvement of all three of the schools. At its meeting on 23 May 2013, the Council agreed that the methodology for detailed appraisal of options for delivering improved facilities in Dunoon should be implemented in order to determine the feasibility of the respective options. From the list of 7 options the Council agreed that two options were to be subject of a detailed appraisal. These were:
Option 6 – Formation of a new Kirn Primary school and nursery on the existing Kirn site by retaining the existing 1881 building and its extension with minimal refurbishment, demolishing the 1950’s extension; formation of a new Dunoon Primary school at the existing Dunoon Primary site by retaining the existing facade and constructing a new build school behind; St Mun’s Primary school and Clyde Cottage Nursery to be refurbished. All schools to meet Grade A condition.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.