Resolved
Decision Following a show of hands vote the Motion was carried by 19 votes to 8 and the Council resolved accordingly. (Reference: Report by Executive Director – Community Services dated April 2014, submitted)
Argyll and Bute Council decided this item on Thursday 24 April 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Following a show of hands vote the Motion was carried by 19 votes to 8 and the Council resolved accordingly. (Reference: Report by Executive Director – Community Services dated April 2014, submitted)
2.1It is recommended that Council:
a) Note the potential impact of the economic development and population demographics on the secondary school design capacity requirements in Oban and Campbeltown;
b) Note the assessment of affordability for the proposed new Oban High School at Appendix 1 and Campbeltown Grammar at Appendix 2 hereof which highlight, in respect of each school, the likely budget requirement to include the capital contribution, over the duration of the 25 year project;
c) Approve the design capacity for Oban High School and Campbeltown Grammar School as 1300 and 500 respectively, in terms of the Education base case;
d) Note capital contribution required for Oban High School of £11.27M and the additional capital requirement for Campbeltown Grammar School of £1.66M and agree an additional provision in Capital Budget for 2017/18 of £12.93M;
e) Note revenue contribution required for Oban High School of £1.05M and the additional revenue requirement for Campbeltown Grammar School of £0.24M and agree an additional provision in Revenue Budget for 2017/18 onwards of £1.29M per annum;
f) Authorise the Executive Director of Community Services to issue the NPR on the basis of the agreed design capacities; and
g) Delegate all matters in respect of the provision of the new school facilities to the Council’s Policy and Resources Committee.
1 3. BACKGROUND 3.1 In early 2013, the Scottish Government announced a 3rd tranche of funding under Scotland’s Schools for the Future (SSF) programme and encouraged bids from local authorities. Argyll and Bute Council submitted an outline proposal for the replacement of Oban High School which was identified as requiring a significant level of maintenance investment to extend its operational life and which was assessed as offering limited suitability due to the constraints of the original design and range of successive extensions. The proposal received in principle support from the Scottish Futures Trust (SFT) subject to the development of a robust business case based on a grant contribution for two thirds of the eligible costs of the project.
3.2In April 2013, the Council approved general governance arrangements for the project in respect of the proposed new school facilities in Campbeltown, Dunoon and Oban and agreed that the sums previously earmarked for development of the project could now be called upon.
3.3The Council has previously agreed a capital provision of £6.5M for Dunoon, £6M for Campbeltown and £0.5M per annum from 2015/16 for funding the on-going affordability gap for those proposed school facilities. The affordability gap shown within this report for each of the proposed new secondary schools in Oban and Campbeltown is the difference between the total estimated cost of the project and the current revenue budget available. Currently there is no agreed capital provision for the replacement of Oban High School.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
NEW SCHOOLS: OBAN AND CAMPBELTOWN: AFFORDABILITY POSITION AND ISSUE OF NEW PROJECT REQUEST TO HUBNORTH SCOTLANDReport | 110 KB | DownloadRead as text |
Follow Argyll and Bute Council at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro... | Decided | Open |
| 23 Sep 2026 | Nhs highland director of public health annual report 2025Decision The Council – 1. noted the Director of Public Health Annual Report 2025; and 2. supported the recommendation... | Noted | Open |
| 23 Sep 2026 | Leader's reportDecision The Council – 1. noted the contents of the submitted report; and 2. noted that any reports, briefings or cop... | Noted | Open |
| 23 Sep 2026 | Policy leads reportDecision The Council noted the content of the submitted report. (Reference: Report by Policy Lead Councillors dated 1... | Noted | Open |
| 23 Sep 2026 | Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.