EXECUTIVE SUMMARY AND INTRODUCTORY REPORT - FINANCIAL REPORT MONITORING PACK - DECEMBER 2014

Noted Committee 1 paper

Policy and Resources Committee noted this item on Thursday 5 February 2015. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

Decision The Committee noted:- 1. the revenue budget monitoring report as at 31 December 2014; 2. the progress towards the 1% savings target for 2014-15 and 2015-16; 3. the updates to the 2015-16 budget as at 31 December 2014; 4. the current assessment of the Council’s financial risks; 5. the overall level of reserves and balances and monitoring of earmarked reserves; 6. the change in profile as detailed in paragraphs 3.3.6 to 3.3.9 in the reserves and balances report; 7. the capital plan monitoring report as at 31 December 2014; and 8. the treasury monitoring report as at 31 December 2014. (Reference: Report by Head of Strategic Finance dated 27 January 2015, submitted) *
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy and Resources Committee

ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE

STRATEGIC FINANCE 5 FEBRUARY 2015

EXECUTIVE SUMMARY AND INTRODUCTORY REPORT - FINANCIAL REPORT MONITORING PACK – DECEMBER 2014

1. INTRODUCTION

1.1This report introduces the full package of papers included in the financial reports monitoring pack. There are seven reports included within the financial report monitoring pack as follows:

 Revenue Budget Monitoring Report as at 31 December 2014  Monitoring of 1% Savings for 2014-15 and 2015-16  Update to 2015-16 Budget as at 31 December 2014  Monitoring of Financial Risks  Reserves and Balances  Capital Plan Monitoring Report as at 31 December 2014  Treasury Monitoring Report as at 31 December 2014

1.2Revenue Budget Monitoring Report – this report provides a summary of the current revenue budget monitoring position to ensure net expenditure is contained within budget. It provides corporate and departmental information with comparisons on a forecast outturn and a year to date basis. The projected year end outturn at 31 December 2014 is an overall underspend of £0.202m. There are overspends in respect of adult care, leisure central repairs, refuse collection and coastal protection works, shortfall in car parking income, unrecoverable costs for dangerous buildings and additional holiday pay costs. These overspends are offset by savings within school and public transport, a significant saving in respect of utility costs, an underspend within early years and over recovery of vacancy savings.

1.3Monitoring of 1% Savings for 2014-15 and 2015-16 – this report provides a summary of the progress towards the savings target for 2014-15 and 2015- 16. The budget savings required for 2014-15 based on 1% savings are £1.822m and savings of £1.802m (98.9%) have already been secured and £0.020m (1.1%) are being implemented all with no policy implications.

1.4Update to 2015-16 Budget – this report provides an update on any of the changes to the budget assumptions used when preparing the 2015-16 budget and an assessment of the impact. The main change to the budget update is the reduction in grant funding of £2.557m due to updating the finance settlement indicators rather than the flat cash approach. There are further funding adjustments of £1.244m relating to Children and Young Persons (Scotland) Act, transfer of the A83, Council Tax Reduction Scheme Administration, Self-Directed Support as well as a number of small funding changes. There are adjustments to the base budget of £1.209m, employee cost changes which give a net increase of £0.902m, reduction of £0.857m within inflation an additional £1.445m cost and demand pressures and a reduction to fees and charges income of £0.055m. The overall impact is a projected surplus for 2015-16 of £0.154m.

1.5Monitoring of Financial Risks - this report outlines the process and approach developed in carrying out a financial risks analysis and provides an update on the current assessment of financial risks. Whilst a total of 59 financial risk areas have been identified only 11 are classed as likely with a potential impact of £2.761m. These will continue to be monitored throughout the year and action taken to mitigate or manage these risks.

1.6Reserves and Balances – this report summarises the overall level of reserves and balances and monitors the spending of the earmarked reserves. The Council has usable reserves of £48.526m. Most of these are earmarked for specific purposes. The General Fund contingency level remains at 1.5% of net expenditure. There is currently an estimated surplus over contingency of £9.811m and this is being directed towards the delivery of the Single Outcome Agreement.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EXECUTIVE SUMMARY AND INTRODUCTORY REPORT: FINANCIAL REPORT MONITORING PACK: DECEMBER 2014Report 3.5 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 17 attended
DW
Councillor Dick WalshChair, present
RC
Councillor Robin CurrieMember, present
VD
Councillor Vivien DanceMember, present
DK
Councillor Donald KellyMember, present
AM
Councillor Alistair MacDougallMember, present
DM
Councillor Duncan MacIntyreMember, apologies
RM
Councillor Roderick McCuishMember, present
AM
Councillor Aileen MortonMember, present
EM
Councillor Ellen MortonMember, present
GM
Councillor Gary MulvaneyMember, apologies
DP
Councillor Douglas PhilandMember, present
JR
Councillor James RobbMember, present

All 17 on the meeting page

On this subject at Argyll and Bute

Search all
  1. EXECUTIVE SUMMARY AND INTRODUCTORY REPORT - FINANCIAL REPORT MONITORING PACK - DECEMBER 2014This decision
  2. Helensburgh eia executive summaryNoted
  3. Executive summaryNoted

More from Argyll and Bute Policy and Resources Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... Agreed Open
20 Aug 2026 Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... Noted Open
20 Aug 2026 Potential impact of iran conflict - updateDecision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section ... Noted Open
20 Aug 2026 Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... Agreed Open
20 Aug 2026 Scottish languages act 2025 - areas of linguistic significanceDecision The Policy and Resources Committee – 1. noted the progress being made to ensure that the Council meets its s... Noted Open