Decision The Committee:- 1. noted the content of the report; and 2. agreed that Officers write to the Scottish Government and COSLA to request that sufficient extension funding is allocated to ensure that coverage levels within Argyll and Bute match the Scotland wide action plan to “put in place infrastructure that will have the capacity to deliver next generation broadband to 95% of premises by 2017, and a significant uplift in speeds for the remaining areas”. (Reference: Report by Executive Director – Development and Infrastructure Services, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The main aim of this report is to provide an update in relation to the digital infrastructure projects which are ongoing across Argyll and Bute. The report includes updates in relation to broadband and mobile communication improvements.
1.2Next Generation Broadband • BT commercial programme – Live in Helensburgh and Oban, Dunoon expected to follow in 2015. • Highlands and Islands Programme – subsea cable work was undertaken during the summer, the first live premises are in Oban. • Rest of Scotland Programme – Properties in the Cardross exchange area received the service in October 2014 (initial build date was 2016); other areas are expected to follow in 2015. • Community Broadband Scotland (CBS) - CBS continue to support communities across Argyll and Bute, including the Argyll Isles project known as Giga Plus Argyll. • New Technology – remodelling work to include Fibre to the Remote Node (FTTRN) is being undertaken and is expected to be available during 2015. • Extension Funding - £21 million has been identified by Broadband Delivery UK (BDUK) for an extension project in Scotland subject to match funding being identified. • Exchange Activate – Highlands and Islands Enterprise (HIE) are in discussions with BT in relation to upgrading the nine Exchange Activate exchanges in Argyll and Bute and they understand that BT are investigating what could be achieved.
1.3Mobile Communications • Mobile Infrastructure Plan - Site searches have commenced in relation to four locations contained within the revised National Implementation Plan, transmission issues are expected to be a significant factor in relation to deliverability. • Scottish Government Pilot on Coll - Work on the installation of the mast commenced during the summer and the service – which is planned to include 4G – is expected to go live once connections to Mull have been completed. • Vodafone Rural – The Isle of Luing and the Isles of Seil and Easdale were announced within the first 30 successful communities planned to receive the equipment. Crossapol (Isle of Tiree) was announced in the second 30 communities. • 4G Coverage – we understand 4G deployment is planned but we have no confirmation as to coverage levels within Argyll.
It is recommended that Policy and Resources Committee 1. Note the content of this report; and 2. Agree that officers write to the Scottish Government and COSLA to request that sufficient extension funding is allocated to ensure that coverage levels within Argyll and Bute match the Scotland wide action to “put in place infrastructure that will have the capacity to deliver next generation broadband to 95% of premises by 2017, and a significant uplift in speeds for the remaining areas”. ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
Development and Infrastructure 5 FEBRUARY 2014
Digital Infrastructure Update
2.0INTRODUCTION
2.1Work has commenced on a number of programmes which aim to improve the digital infrastructure across Argyll. This report provides an update on the various projects.
Recommendations
3.1It is recommended that Policy and Resources Committee 1. Note the content of this report; and 2. Agree that officers write to the Scottish Government and COSLA to request that sufficient extension funding is allocated to ensure that coverage levels within Argyll and Bute match the Scotland wide action to “put in place infrastructure that will have the capacity to deliver next generation broadband to 95% of premises by 2017, and a significant uplift in speeds for the remaining areas”.
4.0DETAIL The work being undertaken in relation to digital infrastructure relates to broadband or mobile communications.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.