Resolved
Decision The Council noted the content of the report. (Reference: Report by Executive Director – Customer Services dated 21 April 2016, tabled)
Argyll and Bute Council noted this item on Thursday 21 April 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Council noted the content of the report. (Reference: Report by Executive Director – Customer Services dated 21 April 2016, tabled)
1.1This report advises Members on remedial repairs at Rothesay Joint Campus and Oban Primary Campus carried out following issues identified during ABC Schools / MITIE’s annual fabric condition surveys and the further surveys being carried out this week across the NPDO school estate.
The Council has a contract with ABC Schools for the design, build, financing and maintenance of the NPDO schools. As such ABC Schools are responsible for the provision of the schools and their maintenance and repair.
MITIE PFI is the facilities maintenance company employed by ABC Schools to maintain the schools and provide janitorial services.
RECOMMENDATIONS Members are asked to note the report.
1 ARGYLL AND BUTE COUNCIL COUNCIL
COMMUNITY SERVICES 21 April 2016 CUSTOMER SERVICES
NPDO SCHOOLS REMEDIAL REPAIRS
2.0INTRODUCTION
2.1This report advises Members on remedial repairs at Rothesay Joint Campus (RJC) and Oban Primary Campus (OPC) carried out following issues identified during ABC Schools / MITIE’s annual fabric condition surveys the further surveys being carried out this week across the NPDO school estate.
The Council has a contract with ABC Schools for the design, build, financing and maintenance of the NPDO schools. As such ABC Schools are responsible for the provision of the schools and their maintenance and repair.
MITIE PFI is the facilities maintenance company employed by ABC Schools to maintain the schools and provide janitorial services.
3.0RECOMMENDATIONS 3.1 Members are asked to note the report.
4.0REMEDIAL ISSUES
4.1ABC Schools and MITIE carry out annual fabric condition surveys across the NPDO schools estate. Cracking to blockwork in the gym and sports hall was identified in RJC.
As a result of this ABC Schools and MITIE instructed a structural surveyor to attend. An intrusive survey was undertaken. This identified that remedial works were required to the blockwork walls. Both RJC and OPC were constructed by the same builder, Barr Construction. Having regard to that and as a precautionary measure a survey was also instructed at OPC to ascertain whether there were similar issues.
Initial findings - Rothesay Joint Campus The findings of the structural survey to the gym and games hall were: Lack of wall ties to the heads of walls Poor workmanship and the use of deficient materials Installation of blockwork not in line with original specification
Initial Findings - Oban Primary Campus The findings of the structural survey to the gym and games hall were: 2 Lack of wall ties to the heads of walls Poor workmanship and the use of deficient materials
Following the identification of these issues, the structural engineer’s survey was extended to the remainder of the buildings in each of Rothesay and Oban; further construction issues were found but, in the opinion of the structural engineer, all areas could continue to be occupied safely.
Remedial Works The structural engineer provided a scope of works to be carried out to remediate the defects found in the gym and sports hall areas of both schools and to allow the areas identified above to be occupied.
The remedial works were carried out during the Easter break. On 17 April 2016 ABC Schools confirmed that the structural engineer had attended both Rothesay Joint Campus and Oban Primary Campus and certified the prescribed remedial works. The structural engineer confirmed that he was now satisfied that the affected areas were safe to occupy.
The engineer also advised that he remained satisfied that all other areas of both buildings were safe for occupation and that as such, ABC Schools advised that they had confirmation that all areas of both buildings were safe for occupation.
ABC Schools have advised that they are developing a programme of works to permanently address all issues identified in the survey report.
4.2Further Surveys Across The NPDO Estate.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
NPDO SCHOOLS REMEDIAL REPAIRSReport | 81 KB | DownloadRead as text |
Follow Argyll and Bute Council at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro... | Decided | Open |
| 23 Sep 2026 | Nhs highland director of public health annual report 2025Decision The Council – 1. noted the Director of Public Health Annual Report 2025; and 2. supported the recommendation... | Noted | Open |
| 23 Sep 2026 | Leader's reportDecision The Council – 1. noted the contents of the submitted report; and 2. noted that any reports, briefings or cop... | Noted | Open |
| 23 Sep 2026 | Policy leads reportDecision The Council noted the content of the submitted report. (Reference: Report by Policy Lead Councillors dated 1... | Noted | Open |
| 23 Sep 2026 | Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.