Resolved
Decision The Council noted the content of the report. (Reference: Report by Executive Director – Customer Services dated April 2017, submitted)
Argyll and Bute Council noted this item on Thursday 20 April 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Council noted the content of the report. (Reference: Report by Executive Director – Customer Services dated April 2017, submitted)
1.1This report summarises progress in relation to the Council’s NPDO project to end of March 2017 and, in particular, provides an update on the current financial position of the Project.
1.3The Council is asked to note the contents of this report. ARGYLL AND BUTE COUNCIL COUNCIL
CUSTOMER SERVICES 20 APRIL 2017
NPDO SCHOOLS AFFORDABILITY REPORT
2. INTRODUCTION
2.1This report summarises progress in relation to the Council’s NPDO project to end of March 2017 and, in particular, provides an update on the current financial position of the Project.
3.1The Council is asked to note the contents of this report.
4. DETAIL
3.1All five School sites within the NPDO Project, at Lochgilphead, Oban, Dunoon, Rothesay and Helensburgh, are operational.
3.2The Special Projects Team (SPT) operates a monitoring framework and continues to utilise the system of liaison meetings and inspections along with assistance from Facility Services to assist in identifying issues in relation to service provision and building fabric within the facilities. Within that the SPT continues to attend the regular Board meetings of ABC Schools Ltd and meets regularly with the Schools and representatives from the Council’s partners, ABC Schools Ltd and MITIE PFI, to monitor progress.
5 BUDGET POSITION
5.1At the Executive meeting in August 2008, the SPT was requested to provide, the Council with an annual report on the ongoing financial status of the NPDO project based on the assumptions prevalent at the time of reporting.
5.2In April 2013 it was reported that, based on assumptions prevalent at the time, the project was affordable in each contract year.
5.3As part of the 2012/13 budget setting process the Council agreed to remove the NPDO smoothing fund and apply the sums earmarked therein for other purposes. The Council also agreed to fully fund the NPDO budget on an ongoing basis. It is anticipated that, based on current assumptions, the NPDO will be able to operate within the budget allocation set by the Council and will be sustainable going forward. The budgetary position of the NPDO will continue to be reviewed and reported as part of the Council’s budget monitoring process.
Future Pressures
5.4Notwithstanding the above, there continue to be potential cost pressures on the NPDO which will continue for the life of the project and affect its long term budgetary position. These will include fluctuations in the general Retail Price Index (RPI), utility tariff rates and Non Domestic Rates (NDR) where the Council takes the risk on changes to these. The current forecast assumes that these factors will increase in line with overall Council estimates but the actual annual impact of these pressures will be considered, with Strategic Finance, as part of the annual budget setting process.
6 EFFICIENCIES IDENTIFIED
6.1The SPT are continuing to monitor ongoing availability and performance deductions. Since April 2016, ABC Schools have required to make payment to the Council of approximately £52k by way of deductions. The SPT are currently withholding a further sum of £230k by way of disputed deductions accrued and are in discussion with ABC Schools to resolve that matter. In relation to this sum, the SPT continue to dispute unitary charge invoices, as appropriate, following the contractual provisions, to enable discussions to settle the deductions considered due to the Authority. The SPT have also been able to release the sum of £16k accrued in respect of unbilled utilities for periods prior to the end of 2012. These sums now fall outwith the 5 year negative prescription period and are no longer lawfully recoverable.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
NPDO SCHOOLS AFFORDABILITY REPORTReport | 76 KB | DownloadRead as text |
Follow Argyll and Bute Council at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro... | Decided | Open |
| 23 Sep 2026 | Nhs highland director of public health annual report 2025Decision The Council – 1. noted the Director of Public Health Annual Report 2025; and 2. supported the recommendation... | Noted | Open |
| 23 Sep 2026 | Leader's reportDecision The Council – 1. noted the contents of the submitted report; and 2. noted that any reports, briefings or cop... | Noted | Open |
| 23 Sep 2026 | Policy leads reportDecision The Council noted the content of the submitted report. (Reference: Report by Policy Lead Councillors dated 1... | Noted | Open |
| 23 Sep 2026 | Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.