Resolved
Decision Members agreed to note the report. (Reference: Report by Executive Director – Development and Infrastructure Services, dated 29 April 2016, submitted).
Helensburgh & Lomond Area Committee agreed this item on Friday 29 April 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Members agreed to note the report. (Reference: Report by Executive Director – Development and Infrastructure Services, dated 29 April 2016, submitted).
1.1This report provides an update on the various digital infrastructure projects including:
Next Generation Broadband o BT commercial programme o Rest of Scotland Programme o Community Broadband Scotland o Extension of Funding o Upgrade to Helensburgh Exchange
Mobile Communications o Mobile Infrastructure Project o Commercial upgrades
Public Wi-Fi
It is recommended that Helensburgh and Lomond Area Committee
1. Note the content of this report. ARGYLL AND BUTE COUNCIL HELENSBURGH AND LOMOND AREA COMMITTEE
Development and Infrastructure 29 APRIL 2016
Digital Infrastructure Update
2.0INTRODUCTION
2.1Work has commenced on a number of programmes which aim to improve the digital infrastructure across Argyll and Bute. This report provides an update on the various projects within the Helensburgh and Lomond area.
3.1It is recommended that Helensburgh and Lomond Area Committee
1. Note the content of this report.
4.0DETAIL
The work being undertaken in relation to digital infrastructure relates to broadband or mobile communications.
4.1Next Generation Broadband
Next generation broadband within Helensburgh and Lomond is being delivered through one of three programmes – the commercial programme by BT (parts of Helensburgh), the Rest of Scotland project and Community Broadband Scotland supported community projects.
4.2Work continues on building the new infrastructure network to support next generation broadband. Land based backhaul and local access fibre cables are required to connect communities. Whilst telephone exchanges will continue to provide a service in relation to telephone calls only a handful of exchanges will handle next generation broadband services, new access cables running from these “headend” exchanges directly to new communication cabinets within communities will ensure that the superfast speeds reach the local cabinets.
4.3Unfortunately during 2015 and early 2016, we saw few new connections within the Helensburgh and Lomond area although work continues across the area to extend the fibre services to as many premises as possible within the budget of the project. A summary of all exchanges across Helensburgh and Lomond is contained at Appendix 1. We have sought clarification regarding these timescales and have been advised that these are the best indications currently. Members should however be aware that slippage can occur during deployment for reasons such as underground duct routes are congested; there are utility cables or underground structures where BT want to lay fibre; BT have been unable to agree a suitable location for the cabinet or the costs of providing electrical power have become excessive. BT Openreach are testing an online search which details the progress of individual cabinets, this can be found at http://homeandwork.openreach.co.uk/when-can-i-get-fibre.aspx.
4.4Once the new fibre cabinets are live, customers who want access to superfast broadband must order the upgraded fibre service from their internet service provider. Members of the public can check whether they are able to order a next generation service at www.scotlandsuperfast.com/where-when. If they are not able to order a next generation broadband service they will be given an indication of whether the service is likely to be available within their exchange area and if so when the first premises are expected to be connected.
4.5BT commercial programme The commercial rollout by BT has continued in Helensburgh with some additional connections expected during 2016.
4.6Rest of Scotland Programme The Rest of Scotland (RoS) Programme in Argyll expects connections to around 92% of premises when the commercial coverage is included.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Digital Infrastructure: updateReport | 2 MB | DownloadRead as text |
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Police scotland updateDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Report by Police Scotl... | Noted | Open |
| 8 Sep 2026 | Clyde transformation programme & clyde land acquisition overviewDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Verbal update from Cly... | Noted | Open |
| 8 Sep 2026 | Charts (argyll and the isles)Decision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Presentation by Chair,... | Noted | Open |
| 8 Sep 2026 | Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref... | Noted | Open |
| 8 Sep 2026 | Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.