Resolved
Decision Members agreed to note the report and the progress update for each action. (Reference: Report by Executive Director – Development and Infrastructure Services, dated 29 April 2016, submitted).
Helensburgh & Lomond Area Committee agreed this item on Friday 29 April 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Members agreed to note the report and the progress update for each action. (Reference: Report by Executive Director – Development and Infrastructure Services, dated 29 April 2016, submitted).
1.1The purpose of this paper is to provide members of the Helensburgh and Lomond (H&L) Area Committee with an update with regard to the progress of the actions and success measures in the H&L Economic Development Action Plan (EDAP), 2015/16.
1.2The content of the H&L EDAP aligns with the Single Outcome Agreement (SOA) Delivery Plans developed by the Community Planning Partnership.
1.3It is important to note that the H&L EDAP is a working document so that economic opportunities can be captured and addressed as they arise during 2015/16.
1.4A detailed financial year-end presentation will be delivered by representatives from the Economic Development and Strategic Transportation Service at this H&L Area Committee meeting.
1.5The following recommendations are for consideration:
The H&L Area Committee members note the H&L EDAP provided in this paper and the progress update for each action.
Helensburgh and Lomond Economic Development Action Plan, 2015/16 Page 1 ARGYLL AND BUTE COUNCIL HELENSBURGH AND LOMOND AREA COMMITTEE
DEVELOPMENT AND INFRASTRUCTURE SERVICES 29h April 2016
HELENSBURGH AND LOMOND ECONOMIC DEVELOPMENT ACTION PLAN 2015/16 – UPDATE
2. INTRODUCTION
2.1The purpose of this paper is to provide members of the H&L Area Committee with an update with regard to the progress of the actions and success measures in the H&L Economic Development Action Plan (EDAP), 2015/16.
3.1The H&L Area Committee members note the H&L EDAP provided in this paper and the progress update for each action.
4. H&L EDAP UPDATE
4.1Following approval by the Area Committee in August 2015 of the H&L EDAP, officers continue to work to implement the key actions. As members will be aware many of the actions are reliant upon partnership working with our Community Planning Partners. Many of the actions will be taken forward over a 12 month timeframe and beyond as appropriate.
4.2The update outlined in Appendix 1 provides a tabular presentation to include comments on progress for each of the actions and success measures under the four headings of competitive, collaborative, compelling and connected H&L.
5. CONCLUSION
5.1The H&L EDAP is a working document for 2015/16 and officers continue to work and focus on the delivery of the actions with key partners.
Helensburgh and Lomond Economic Development Action Plan, 2015/16 Page 2 6 IMPLICATIONS
6.1The implications for the H&L Area Committee are as outlined in Table 7.1 below.
Table 6.1: Implications for the H&L Area Committee The H&L EDAP 2015/16 (and subsequent in-year plans) must align and adhere, as appropriate, to the overarching EDAP, Policy 2013-2018, Local Development Plan and the SOA Local/SOA Delivery Plans. The H&L EDAP will ensure that the area’s resources are allocated efficiently and effectively with regard to the economic Financial development priorities and ambitions for H&L. There will need to be annual consideration of best alignment between resources and priorities. All legal implications at project level will be taken into Legal consideration. The H&L EDAP priorities will be resourced in terms of staff time in the context of the Council’s annual service planning process HR and through shared staff resource discussions with Community Planning Partners. The H&L EDAP will comply with all Equal Opportunities policies Equalities and obligations. Without a H&L EDAP for 2015/16 there would be no clear focus on or understanding of the economic development activities, Risk and the associated resources, that will have the greatest beneficial economic impact for the area. The H&L EDAP will provide internal and external customers Customer with a clear articulation of the key priorities for developing the Service H&L economy, thereby facilitating focus, effective resource planning and partnership working at the local level.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HELENSBURGH AND LOMOND ECONOMIC DEVELOPMENT ACTION PLAN 2015/16: UPDATEReport | 191 KB | DownloadRead as text |
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Police scotland updateDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Report by Police Scotl... | Noted | Open |
| 8 Sep 2026 | Clyde transformation programme & clyde land acquisition overviewDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Verbal update from Cly... | Noted | Open |
| 8 Sep 2026 | Charts (argyll and the isles)Decision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Presentation by Chair,... | Noted | Open |
| 8 Sep 2026 | Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref... | Noted | Open |
| 8 Sep 2026 | Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.