Decision The Committee – 1. Noted that £9,268,259 of funding has been awarded to current existing programmes, projects and initiatives match funded by £1,367,100 of Council investment. This has resulted in £1 of Argyll and Bute Council funding levering in £6.78 of external funding. 2. Noted that the Economic Development and Strategic Transportation service is seeking £9,636,058 of funding with £712,500 of Council match funding. If all sought funding is secured, for every £1 of Argyll and Bute Council funding a total of £13.52 will be levered in of external funding. 3. Endorsed the continued efforts of the Economic Development and Strategic Transportation service to maximise the level of external funding being secured for Argyll and Bute to augment existing and potential projects. 4. Congratulated the Economic Development and Strategic Transportation Team on their outstanding achievement across Argyll and Bute in attracting funding and stimulating development and regeneration. (Reference: Report by Executive Director – Development and Infrastructure Services dated 9 January 2017, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1The purpose of this paper is to provide the Environment, Development and Infrastructure (EDI) Committee with an update on the funding awarded for existing programmes, projects and initiatives and that in progress for proposed programmes, projects and initiatives to be delivered by the Council’s Economic Development and Strategic Transportation (EDST) service.
1.2£9,268,259 of funding has awarded to current existing programmes, projects and initiatives from an initial ask of £9,369,259. The £101,000 funding shortfall relates only to two projects. As the focus is always to maximise the leverage of external funding into Argyll and Bute initial asks, subject to strong competition, can be capped.
1.3At present the EDST service is seeking £9,636,058 of funding. To date some elements of total project funding have been approved and one project has been approved in principle; this currently totals £1,083,448.
1.4Details of the programmes, projects and initiatives awarded and in progress by team within the EDST service are outlined in Table 1 and Table 2 in the main report.
1.5It is recommended that Members:
Note that £9,268,259 of funding has been awarded to current existing programmes, projects and initiatives match funded by £1,367,100 of Council investment. This has resulted in £1 of Argyll and Bute Council funding levering in £6.78 of external funding.
Note that the EDST service is seeking £9,636,058 of funding with £712,500 of Council match funding. If all sought funding is secured, for every £1 of Argyll and Bute Council funding a total of £13.52 will be levered in of external funding.
Endorse the continued efforts of the EDST service to maximise the level of external funding being secured for Argyll and Bute to augment existing and potential projects. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
DEVELOPMENT AND INFRASTRUCTURE 19th JANUARY 2017 SERVICES
FUNDING UPDATE: AWARDED AND IN PROGRESS
2. INTRODUCTION
2.1The purpose of this paper is to provide the Environment, Development and Infrastructure (EDI) Committee with an update on the funding awarded for existing programmes, projects and initiatives and that in progress for proposed programmes, projects and initiatives to be delivered by the Council’s Economic Development and Strategic Transportation (EDST) service
Recommendations
3.1Members are asked to: Note that £9,268,259 of funding has been awarded to current existing programmes, projects and initiatives match funded by £1,367,100 of Council investment. This has resulted in £1 of Argyll and Bute Council funding levering in £6.78 of external funding. Note that the EDST service is seeking £9,636,058 of funding with £712,500 of Council match funding. If all sought funding is secured, for every £1 of Argyll and Bute Council funding a total of £13.52 will be levered in of external funding. Endorse the continued efforts of the EDST service to maximise the level of external funding being secured for Argyll and Bute to augment existing and potential projects.
4. DETAILS
4.1The overarching challenge for the Argyll and Bute economy is to retain and grow its population. Therefore along with Council match funding, as appropriate, it is important to maximise external funding, both at the national and European level. This funding can be levered in to the area to enable economic growth and higher value employment which in turn will attract higher earnings and people.
4.2The funding awarded for existing programmes, projects and initiatives currently being delivered throughout the Argyll and Bute Council area is outlined in Table 1 below. Table 1 details the funding awarded for the teams within the EDST Service; Economic Growth (EG), Strategic Transportation & Infrastructure (ST&I), Transformation Projects & Regeneration (TP&R) and CHORD.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.