AI summaryArgyll and Bute Council's Environment, Development and Infrastructure Committee noted that the £1.1m approved in September 2025 for the A816 Bealach Mor was for development work only, with permanent road realignment now expected between 2029 and 2032.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted four key points on the permanent solution
Money£1.1m approved September 2025Covers business case, investigations and procurement, not construction
What happens nextTender issued, contract award early 2027Professional services tender for business case and design
Who it affectsA816 users and island ferry linksCommunities between Oban and Lochgilphead
What was decided
The Committee noted that the £1.1m approved in September 2025 was for development work only and did not approve construction. Report 3.1, 4.3
It noted that progress has been made on investigations, environmental requirements, business case scoping and procurement preparation since September 2025. Report 3.1, 4.1
It noted that a formal tender for professional services has been issued to the open market to support the business case, detailed investigations and Design and Build procurement process. Report 3.1, 4.1
Why
Simple widening of the temporary bypass is technically insufficient due to severe, evolving geotechnical risks on the hillside, including a 25 metre tension crack and embankment instability. Report 2.1, 4.1
The October 2023 weather event deposited around 6,000 tonnes of material and severed the primary transport link between Oban and Lochgilphead. Report 2.1
The chosen approach involves realigning and structurally upgrading the bypass to current design standards, with development and procurement proceeding under HM Treasury Green Book and Department for Transport appraisal standards. Report 4.1
What happens next
Specialist consultancy contract award is anticipated by early 2027, with Stage 2 Strategic Outline Business Case and outline design completion estimated in 2028. Report 4.1, 4.2
Design and Build construction for the permanent realigned road is forecast for the 2029 to 2032 window, subject to further Council approvals and budget allocation. Report 3.1, 4.1, 4.2
Interim measures continue, including a permanent electrical connection with Scottish and Southern Electricity Networks to replace the temporary battery and generator setup powering the traffic signals. Report 4.1
The money
£1.1 million Capital allocation for business case, outline design, investigations, environmental assessment and Design and Build procurement Report 4.1, P15
£5.155m Allocation to the emergency recovery phase of the project Report P15
£7.25m, £8.5m Estimated cost of permanent works contract, subject to refinement Report 4.2, P15
£14.8m Total intervention estimate covering emergency recovery, business case and future construction Report 4.1, P15
Options considered
Rejected: Simple widening of the temporary bypass. Technically insufficient due to complex hillside instability, a 25 metre tension crack and residual landslip risks Report 2.1, 4.1
Chosen: Realigning and structurally upgrading the bypass to current design standards. Eliminates residual geotechnical hazards permanently and produces a road corridor compliant with current standards Report 4.1
Implications
Financial: The £1.1m covers the current development phase only and does not fund the future construction phase, which is currently estimated at £7.25m to £8.5m. Report 6.0, P15
Legal: The Council must continue to discharge its statutory Client duties under the Construction (Design and Management) Regulations 2015, with further legal input needed on land access, consents and contracts. Report 6.0, P16
Risk: Key risks include further landslip, continued reliance on temporary traffic management, environmental consenting, land and legal matters, affordability, procurement outcomes, and finite internal professional capacity alongside other complex infrastructure priorities including Millbrae, Iona Breakwater and Gribun rockfall. Report 6.6, P18
Staffing: Delivery is dependent on finite professional engineering, project management, procurement and technical capacity within Infrastructure Design, supported by specialist external consultancy. Report 6.0
Climate: The permanent solution will support climate resilience on a route affected by extreme weather, while construction will have embodied carbon impacts to be considered through design and procurement. Report 6.0
Equalities: No specific Fairer Scotland Duty, Consumer Duty or Children's Rights and Wellbeing implications have been identified at this stage, though any future consultation and traffic management will need to consider these matters. Report 6.8, 6.10, 6.12
Who and where
Road users of the A816 between Oban and Lochgilphead Report 2.1, 6.0
Communities served by the A816 corridor, including onward ferry connections to island communities Report 6.0
Local businesses, visitors and residents along the route Report 6.0
The affected landowner (negotiations on permanent grid connection and land permissions) Report 4.1
Timeline
7 October 2023: Extreme rainfall triggered three debris flows that severed the A816 at Bealach Mor Report 2.1
16 December 2023: Temporary bypass opened under convoy Report 2.1
13 September 2024: Traffic returned to original A816 under single lane traffic signal control, with bypass held as emergency fallback Report 2.1
11 September 2025: Committee approved £1.1 million capital allocation for business case development Report 4.1, P15
September 2026: Professional services tender pack issued to the market Report 4.1
early 2027: Specialist consultancy contract award anticipated Report 4.1
2028: Estimated completion of Stage 2 Strategic Outline Business Case and outline design Report 4.2
2029-2032: Current anticipated delivery window for the permanent fully realigned road Report 3.1, 4.1, 4.2
Plain English for the jargon
EIA: Environmental Impact Assessment
SOBC: Strategic Outline Business Case
CDM 2015: Construction (Design and Management) Regulations 2015
SSSI: Sites of Special Scientific Interest
SSE: Scottish and Southern Electricity Networks
DfT: Department for Transport
TAG: Transport analysis guidance used by the Department for Transport
HM Treasury Green Book: Government guidance on appraisal and evaluation of policies, programmes and projects, structured around a Five Case Model
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4
Resolved
Decision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m approved in September 2025 was for development work only - business case preparation, ground investigations, environmental appraisal, Environmental Impact Assessment and procurement - not direct approval to move to construction; 2. progress had been made since September 2025 on investigations, environmental requirements, business case scoping and procurement preparation; 3. a formal tender for professional services had been issued to the open market to support the business case, detailed investigations and Design & Build procurement process; and 4. the current anticipated delivery window for the permanent fully realigned road was 2029–2032, reflecting geotechnical complexity and statutory pre-construction requirements. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated September 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee, 9 pages
Executive summary
1.1This report sets out the background and current status of the infrastructure recovery project following the severe October 2023 weather event and subsequent temporary bypass operations. It details the approval of the £1.1 million capital allocation by the Environment, Development, and Infrastructure Committee in September 2025 to advance detailed business case development, outlines the findings of the options assessment which confirmed that simple bypass widening is insufficient due to complex geotechnical risks, and describes ongoing internal progress including environmental impact screening, procurement of a specialist consultancy via a Professional Services Contract, and crucial interim operational resilience measures, including robust fallback inspection protocols and permanent power supply negotiations to address recent temporary traffic management vulnerabilities.
RECOMMENDATIONS It is recommended that Members of the Environment, Development and Infrastructure Committee note and consider the following key points: • The £1.1m approved in September 2025 was for development work only — business case preparation, ground investigations, environmental appraisal, EIA and procurement — not direct approval to move to construction. • Progress has been made since September 2025 on investigations, environmental requirements, business case scoping and procurement preparation. • A formal tender for professional services has been issued to the open market to support the business case, detailed investigations and Design & Build procurement process. • The current anticipated delivery window for the permanent fully realigned road is 2029–2032, reflecting geotechnical complexity and statutory pre- construction requirements. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE ROADS AND INFRASTRUCTURE 9 OCTOBER 2026
A816 BEALACH MOR PERMANENT SOLUTION UPDATE
2.0INTRODUCTION
2.1On 7 October 2023, extreme rainfall equivalent to a month’s worth of precipitation falling over 36 hours triggered three closely spaced debris flows across the steep slopes of Bealach Mor, depositing approximately 6,000 tonnes of material over a 200-metre section of the A816 and completely severing the primary transport link between Oban and Lochgilphead. To re-establish emergency connectivity, the Council constructed a temporary bypass route through a constrained corridor, opened under convoy on 16 December 2023. Built to a non-highway standard (Forestry Land Scotland specification), the bypass featured single-lane running, passing places, steep inclines, and sharp corners. Following extensive clearance operations (totalling over 15,000 tonnes of debris handled across the project timeline), the installation of rockfall barrier systems, and catch-pit construction, traffic was officially returned to the original A816 route under single-lane traffic signal control on 13 September 2024, allowing the temporary bypass loop to be closed and held in reserve as an emergency fallback route. 2.2 This report builds upon the previous findings reported to Members in September 2025, which set out the outcomes of the options assessment commissioned by the Council and undertaken by specialist contractors and consultants. Following comprehensive geotechnical evaluation—which concluded that simple widening of the temporary bypass is unviable due to complex hillside instability and residual landslip risks—four primary engineering options were shortlisted. This report details how these shortlisted options are now being progressed through the Strategic Outline Business Case (SOBC) framework to identify a single preferred permanent solution. 3.0 RECOMMENDATIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.