REVIEW OF ROADS AND INFRASTRUCTURE SERVICES UPDATE

Noted Committee 1 paper

AI summaryArgyll and Bute's EDI Committee noted progress on the Roads and Infrastructure Services Review covering organisational restructure, fleet, parking, transport and waste. A further update will come to the next committee meeting.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted update; next report to next meeting
MoneySchool transport budget around £12.000mAbout £9.000m paid to external operators
What happens nextNext EDI Committee meetingFurther progress report to be presented
Who it affectsCommunities across Argyll and ButeRoad users, pupils, island areas, residents

What was decided

The committee noted the progress to date on the Roads and Infrastructure Services Review. Report 1.1

The committee noted that a further report on progress will be presented at the next meeting of the committee. Report P3

Why

The review is moving from planning into implementation across several workstreams, with the aim of strengthening service delivery, value for money, resilience and compliance. Report 1.1

Recent tender outcomes have required extra budget for school and public transport, showing the need for a more structured and sustainable approach. Report P30

The organisational reshape is intended to create clearer accountability and reduce service disruption without adding to the revenue cost of the staffing establishment. Report P13

What happens next

The new organisational structure goes live on 31 August 2026, with remaining vacancies continuing to be recruited to. Report P14

A further phase of work begins through a review of business support within Roads and Infrastructure Services. Report P15

A new Parking Strategy and a review of Fleet Services are each expected to run over 12 to 18 months, with the School and Public Transport review planned to start implementation on 1 February 2027. Report P22, P26, P31

The money

  • £12.000m Total school and public transport budget Report P30
  • £9.000m Paid to external operators for school and public transport Report P30
  • £0.876m Additional budget provision for 2025/26 from recent tender exercises Report P30
  • £0.400m Additional budget provision for 2026/27 from recent tender exercises Report P30

Implications

  • Financial: The review is intended to support improved value for money, stronger cost control and more transparent financial planning, with specific financial implications considered through project governance and future reports. Report 6.2
  • Legal: No immediate legal implications arise from this update; legal advice will be sought on statutory duties, contracts, consultation, Traffic Regulation Orders and procurement as workstreams progress.
  • Staffing: The organisational reshape will continue to be managed under Council HR policies, with engagement of employees, trade unions and HR on any further staffing implications.
  • Risk: Key risks relate to delivery capacity, workforce planning, cost pressures, contractor and market capacity, statutory compliance and the sequencing of change across multiple workstreams.
  • Climate: Several workstreams, including fleet planning, waste collection routing, parking and transport strategy, have potential to support the Council's climate change objectives.
  • Equalities: No direct equalities implications from this update; impacts on protected characteristics and the Fairer Scotland Duty will be assessed for individual workstreams.
  • Other: The review recognises particular operational challenges in delivering services across island communities, with island impacts to be considered in transport, waste, fleet and access to services.

Who and where

  • Communities across Argyll and Bute using roads, transport, waste and parking services
  • Around 3,500 pupils transported to 78 schools each day Report P30
  • External school and public transport operators Report P30
  • Island communities facing particular operational challenges
  • Children and young people whose rights and wellbeing are considered in transport decisions

Timeline

  • 2024: Initial stage 1 review of Roads and Infrastructure Service began Report 2.1
  • 20 June 2024: Initial review with 119 recommendations first reported to EDI Committee Report 2.1
  • 19 March 2026: EDI Committee agreed an eight point action plan for school and public transport Report P28
  • 24 June 2026: Council agreed to develop a new Parking Strategy Report P23
  • 31 August 2026: New organisational structure goes live Report P14
  • 9 October 2026: This progress update considered by EDI Committee Report P4
  • 1 February 2027: Planned start of school and public transport review implementation Report P31
  • 30 June 2027: Planned closure of school and public transport project Report P31

Plain English for the jargon

  • RIS Review: Roads and Infrastructure Services Review, the ongoing service review underway since 2024
  • RIAMS: Roads Information and Asset Management System used for asset data, works management and customer service
  • EDI Committee: Environment, Development and Infrastructure Committee of Argyll and Bute Council
  • PPP: Public-Private Partnership, referenced in the context of the waste disposal contract with Biffa
  • UNCRC: United Nations Convention on the Rights of the Child
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

Decision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review; and 2. noted that that a further report on progress would be presented to the next meeting of the Environment, Development and Infrastructure Committee. (Reference: Report by Executive Director with responsibility for Development and Infrastructure Services dated 29 July 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Environment, Development and Infrastructure Committee, 8 pages

Executive summary

1.1This report provides Members with an update on progress with the Review of Roads and Infrastructure Services. The review continues to move from planning into implementation, with progress across organisational reshaping, digital asset and works management, and household waste reduction. 1.2 New workstreams are underway to strengthen value for money, resilience and compliance. These include a review of fleet services, development of a new Parking Strategy, and review of school and public transport arrangements. Together, these activities will improve service delivery, strengthen financial control, support compliance and improve the overall support that the Council provides to communities across Argyll and Bute. 1.3 Members are asked to consider the progress to date and note that further reports will be presented to future meetings of the Environment, Development and Infrastructure Committee as workstreams progress through implementation, consultation, delivery and review.

Recommendations

It is recommended that Members of the Environment, Development and Infrastructure Committee:

a) Consider the progress to date on the RIS Review. b) Note that that a further report on progress will be presented to the next meeting of the Environment, Development and Infrastructure Committee. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE ROAD AND INFRASTRUCTURE SERVICES 9 OCTOBER 2026

REVIEW OF ROADS AND INFRASTRUCTURE SERVICES UPDATE

2.0INTRODUCTION

2.1Roads and Infrastructure Service has been undergoing a significant service review since 2024. The initial stage 1 review was completed by PeopleToo consultancy and provided 119 recommendations, along with indicative timescales and priorities. These were first reported to the Environment, Development and Infrastructure (EDI) Committee on 20 June 2024. An update on progress was provided at the last meeting of this Committee in June, along with an update on the 12 priority improvement actions.

2.2Since the initial report, progress updates have been provided to EDI in: • December 2024 • March 2025 • June 2025 • September 2025 • December 2025 • March 2026, and • June 2026

2.3This report provides a further update on progress with implementing the main recommendations within the original report.

3.1It is recommended that Members of the Environment, Development and Infrastructure Committee:

a) Consider the progress to date on the RIS Review. b) Note that that a further report on progress will be presented to the next meeting of the Environment, Development and Infrastructure Committee. 4.0 DETAIL

4.1Organisational Reshaping.

4.1.1 The organisational reshape has moved into its final implementation phase. All directly matched employees and all employees in ring-fenced pools have been appointed into appropriate positions, with no requirement for interviews. Full organisation structures, including named post-holders, have been prepared for input into back-office systems. Remaining vacancies are now being recruited to, including key posts in marine operations, community transport, traffic services, fleet, and waste management.

4.1.2 The organisational reshape will strengthen service delivery by creating a more balanced, resilient and clearly accountable management structure. Additional capacity in key areas such as marine operations, waste management, fleet and infrastructure design will improve operational oversight, support more consistent front-line delivery, and reduce the risk of service disruption. Clearer roles and responsibilities will also help teams respond more effectively to statutory duties, strategic priorities and day-to-day service demands. The changes to the organisation structure have been achieved without growth in the revenue cost of the staffing establishment.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
REVIEW OF ROADS AND INFRASTRUCTURE SERVICES UPDATEReport 8 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 20 attended
IP
Councillor Iain PatersonMember, expected
JP
Julieann PenmanSecretary, expected
KM
Katie McKenzieSecretary, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourChair, expected
GH
Councillor Graham HardieMember, expected
WH
Councillor Willie HumeMember, expected
AK
Councillor Andrew KainMember, expected
JL
Councillor Jim LynchMember, expected
TM
Councillor Tommy MacPhersonMember, expected
IM
Councillor Ian MacQuireMember, expected

All 20 on the meeting page

On this subject at Argyll and Bute

Search all
  1. REVIEW OF ROADS AND INFRASTRUCTURE SERVICES UPDATEThis decision
  2. Review of roads and infrastructure services updateNoted
  3. Review of roads and infrastructure services - updateNoted
  4. Review of roads and infrastructure services - updateNoted
  5. Review of roads and infrastructure services - updateNoted
  6. Review of roads and infrastructure services - updateNoted

More from Argyll and Bute Environment, Development and Infrastructure Committee

All decisions
MeetingDecisionOutcome
9 Oct 2026 A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... Noted Open
9 Oct 2026 Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... Noted Open
9 Oct 2026 Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... Approved Open
9 Oct 2026 Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... Noted Open
9 Oct 2026 Supporting our pollinatorsDecision The Environment, Development and Infrastructure Committee – 1. acknowledged the success of the support for o... Agreed Open