Resolved
Decision The Committee agreed to refer this item, without recommendation, for consideration by the Council at their meeting on 23 February 2017. (Reference: Report by Head of Strategic Finance dated 6 February 2017, submitted) *
Policy and Resources Committee agreed this item on Thursday 16 February 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee agreed to refer this item, without recommendation, for consideration by the Council at their meeting on 23 February 2017. (Reference: Report by Head of Strategic Finance dated 6 February 2017, submitted) *
1.1This report details the revisions proposed to the capital plan approved in August 2016 for the period 2016-20. The revisions are based on updated capital funding assumptions, phasing, cost changes and proposed additions.
1.2There are two changes to the presentation of the capital plan: Information is now included in relation to the proposed asset disposals. The assets used by the Health and Social Care Partnership (HSCP) are shown separately from Community Services.
1.3There is an increase in the capital funding available of £2.738m as a result of: An increase in the General Capital Grant advised for 2017-18 of £2.490m and an increase to the 2016-17 reallocated to future years of £0.004m. An increase to the assumption on the likely level of capital grant for 2018-19 and 2019-20 of £1m for each year, raising the estimate from £12m to £13m each year. Additional Specific Grant in respect of Cycling, Walking and Safer Streets of £0.119m. A reduction in the likely level of capital receipts by £1.875m.
1.4When the capital plan was updated at the Council meeting on 18 August 2016, there was an under commitment at that time of £1.812m and it was agreed to earmark this as a contingency against implementation and development of the capital programme.
1.5The revised under commitment, taking into consideration the change in capital funding is £4.550m. There are three proposals to be funded from this balance, leaving an uncommitted balance of £3.231m. Legionella related Property Works – estimated to cost around £1.000m. Stage 2 submission of Rothesay THI project - £0.200m. Cycling, Walking and Safer Streets £0.119m (matched to specific grant).
1.6The restricted capital funding of £12.711m is noted within Appendix 1. This relates to income which is restricted to specific projects and this has been matched with expenditure against the project, thereby showing the gross cost of the project.
1.7The capital plan has been updated to reflect phasing and cost changes and details are contained in Appendix 2. Community Services have proposed a number of new projects which are funded from block allocations within the Page 2
previously approved capital plan; these are detailed in Appendix 3.
1.8The updated capital plan reflecting all the proposed changes is detailed in Appendix 4. Page 3
ARGYLL AND BUTE COUNCIL COUNCIL
STRATEGIC ASSET MANAGEMENT BOARD 23 FEBRUARY 2017
CAPITAL PLAN SUMMARY REPORT
2. INTRODUCTION
2.1This report details the revisions proposed to the capital plan approved in August 2016 for the period 2016-20. The revisions are based on updated capital funding assumptions, phasing, cost changes and proposed additions.
2.2There are two changes to the presentation of the capital plan: Information is now included in relation to the proposed asset disposals. The assets used by the Health and Social Care Partnership (HSCP) are showing separately from Community Services.
3. DETAIL
3.1The detail of the report is split into five main sections: Estimated Capital Funding 2017 to 2020 Capital Plan reported as at 31 December 2016 Proposed Revisions to Capital Plan Comparison of Revised Plan to Estimated Capital Funding Proposals for Allocating the Under Commitment.
3.2Estimated Capital Funding 2017 to 2020
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BUDGETING PACKReport | 3.2 MB | DownloadRead as text |
PDF |
Introductory Report for Budget PapersReport | 107 KB | Download |
PDF |
Revenue Budget Pack: NumberedReport | 9.6 MB | Download |
Follow Policy and Resources Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Aug 2026 | Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... | Agreed | Open |
| 20 Aug 2026 | Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... | Noted | Open |
| 20 Aug 2026 | Potential impact of iran conflict - updateDecision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section ... | Noted | Open |
| 20 Aug 2026 | Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... | Agreed | Open |
| 20 Aug 2026 | Scottish languages act 2025 - areas of linguistic significanceDecision The Policy and Resources Committee – 1. noted the progress being made to ensure that the Council meets its s... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.