HELENSBURGH PARK AND RIDE - GASOMETER SITE LAND PURCHASE

Approved Committee 2 papers

Policy and Resources Committee approved this item on Thursday 16 February 2017. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

Decision The Committee approved the purchase of the former Gasometer Site in Helensburgh, by Argyll and Bute Council, utilising the £80K capital grant funding from SPT. (Reference: Report by Executive Director – Development and Infrastructure Services dated 13 January 2017, submitted) *
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy and Resources Committee

Executive summary

Argyll and Bute Council have had a long standing aspiration to develop a park and ride facility serving Helensburgh Town Centre to cater for commuter parking and free up town centre parking spaces. The Council has been awarded £80k from SPT’s 2016/17 Capital Programme to purchase the former gasometer site adjacent to Grant Street to deliver a park and ride car park and we are seeking approval from the Policy and Resources Committee to proceed with the purchase of the site.

The Gasometer site is located adjacent to Grant Street in Helensburgh Town Centre (see Appendix 1) and is a former gas holder site currently owned by Scottish Gas Networks (SGN). Following extensive negotiations with SGN a fee of £60k has been agreed for the site. The remaining £20k of the budget has been allocated to progress detailed designs and associated survey work. SPT’s grant funding requires to be spent by 31st March 2017 in line with financial year end deadlines.

As the project has progressed a number of risks have been identified that are associated with the purchase of the gasometer site. Officers have however taken steps to mitigate these risks. A summary of the risks and recommendations is set out in the table below with further details provided in Section 4.0:-

Risk Comments / Recommendations Grant funding deadline The land purchase can be completed in 4-6 weeks following (31/03/207) necessary approval from P&R Committee.

Contaminated ground Council’s Environmental Protection officer has been on site consulted and is satisfied the level contamination is low risk given intended use of site as a car park.

Unknown ground A proportion of the site is flooded and it has not been conditions due to possible to survey this area. Upon purchasing the site flood flooding on site. water will require to be pumped from the flooded area and water disposed of appropriately given potential contamination. The flooding is not considered to be a high risk to the development proposals as it is likely this is being caused by impermeable concrete foundations from the former gas holder which will limit potential ground water contamination. Securing Future Grant SPT have indicated they are supportive of the proposals funding. and a funding bid for £300k has been submitted to their 2017/18 Capital Programme. Scotrail have advised that they can potentially provide up to £2k per space in match funding which would equate to approximately £100k. Achieving a cost Atkins is currently progressing designs for the drainage effective drainage infrastructure required working with Council Roads and scheme for the site. Amenity staff. The designers are confident a suitable cost effective drainage connection can be made to the existing drainage infrastructure on Grant Street. Securing planning Pre-application discussions have been undertaken with ABC consent for a park and Planning and Roads who have indicated that they are ride facility on the site comfortable with the development proposals. Re-payment of grant SPT are fully aware of the risks and mitigation undertaken to funding to SPT if the date and have confirmed they are happy for the Council to site is unviable to progress with the purchase of the site based on the risks develop. identified to date. As with all grants provided by SPT they can potentially seek repayment of grant funding if the site proves to be unviable to develop as a park and ride facility. No alternative sites The Gasometer Site is the only viable site in Helensburgh identified for a park currently identified for a park and ride facility that can and ride facility. provide an additional 50 car parking spaces in close proximity to Helensburgh Central.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HELENSBURGH PARK AND RIDE: GASOMETER SITE LAND PURCHASEReport 105 KB DownloadRead as text
PDF
TitlePlan: HelensburghSGNReport 268 KB Download

At this meeting

Whole meeting

Who was there

13 of 18 attended
DW
Councillor Dick WalshChair, present
RC
Councillor Rory ColvilleMember, present
RC
Councillor Robin CurrieMember, present
MD
Councillor Mary-Jean DevonMember, apologies
KG
Councillor Kieron GreenMember, present
RM
Councillor Roderick McCuishMember, present
IM
Councillor Iain MacLeanMember, expected
AM
Councillor Alistair MacDougallMember, present
NM
Councillor Neil MacIntyreMember, present
AM
Councillor Aileen MortonMember, present
EM
Councillor Ellen MortonVice-Chair, present
GM
Councillor Gary MulvaneyMember, present

All 18 on the meeting page

On this subject at Argyll and Bute

Search all
  1. HELENSBURGH PARK AND RIDE - GASOMETER SITE LAND PURCHASEThis decision
  2. Proposed Argyll and Bute Council (Off Street Parking Places and Charges) (Helensburgh) (Amendment) Order 202_Agreed
  3. Helensburgh Waterfront Development - Skatepark optionsDecided
  4. Helensburgh Waterfront Development - SkateparkNoted
  5. Helensburgh waterfront development - car parkingAgreed
  6. Argyll and bute council: erection of new leisure building including swimming pool, improved flood defences, new car park including public realm works and demolition of existing swimming pool: helensburgh swimming pool, 1b west clyde street, helensburgh (ref: 18/01614/pp)Agreed

More from Argyll and Bute Policy and Resources Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... Agreed Open
20 Aug 2026 Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... Noted Open
20 Aug 2026 Potential impact of iran conflict - updateDecision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section ... Noted Open
20 Aug 2026 Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... Agreed Open
20 Aug 2026 Scottish languages act 2025 - areas of linguistic significanceDecision The Policy and Resources Committee – 1. noted the progress being made to ensure that the Council meets its s... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies