Resolved
Members agreed to note the contents of the report. (Ref: Report by Executive Director of Development and Infrastructure Services dated 5 April 2017, submitted.)
Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 5 April 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Members agreed to note the contents of the report. (Ref: Report by Executive Director of Development and Infrastructure Services dated 5 April 2017, submitted.)
1.1This report provides the Committee with an outline of the current position with alleviating flood risk in Campbeltown.
1.2It is recommended that Members note the report. ARGYLL AND BUTE COUNCIL MID ARGYLL, KINTYRE AND THE ISLANDS AREA COMMITTEE
DEVELOPMENT AND INFRASTRUCTURE 5 APRIL 2017
CAMPBELTOWN FLOODING
2.0INTRODUCTION
2.1This report provides the Committee with an outline of the current position with alleviating flood risk in Campbeltown.
3.1It is recommended that Members note the report.
4.0DETAIL
4.1There has been a history of flooding in Campbeltown and in recent years this has mainly been at Millknowe and Dalaruan burns with the culverts unable to take the flow. This results in water overtopping the culvert headwalls and flowing along the public roads.
4.2The position was exacerbated when Scottish Water made changes to the sewerage system in the 2000s, preventing the burn water entering what had been historically the natural flow paths to the sea. This gradually became culverted as the town developed and in a bid to reduce flows into the Scottish Water system (and subsequent treatment works) access to the sewerage network was closed off. No alternative provision was provided to take the water that previously could use the Scottish Water system. Consequently, the existing fresh water culvert in Dalaruan/High Street could not cope with flows, and overtopping occurs in periods of heavy rainfall.
4.3In 2008 a report was completed for the Council by Halcrow and it identified potential solutions. For both Millknowe and Dalaruan watercourses the options were to attenuate flows higher up in each catchment and/or increase pipe sizes to cope with the anticipated flows. The report did include some Benefit/Cost figures which have allowed the scheme to be included in the “works” category in the national Flood Risk Management Strategy.
4.4In June 2016 the Local Flood Risk Management Plans were published by the Scottish Environment Protection Agency (SEPA). This included the Campbeltown Scheme and is the only one in Argyll and Bute in the national strategy listed for actual works – compared with studies and Surface Water Management Plans. 4.5 Campbeltown is included as works in the first of the 6 year cycles that are about to start to reduce flood risk in Scotland. If the scheme is successful in terms of estimated costs/benefits, permissions and consents together with budget being allocated and it progresses to actual construction it is expected that a site start could be made about 2021. The value of the project is currently expected to be circa £9m. The first step is to engage a consultant (Aecom were appointed on 16 March) to review and update the Halcrow report and identify the current options to reduce the flood risk in Campbeltown. With the expectation that there will be options that are worth further preliminary design work, these will be taken forward.
4.6There are many unknowns with regard to what might affect the options and these will have to be investigated further for the viable solutions. These include land ownership, public utilities and suitable hydraulic solutions. Legal powers to construct any works would need to be obtained, followed by full detailed design of the chosen scheme, procurement of a contractor and finally construction. It is currently expected that construction would be in 5 to 6 years’ time depending on suitable finance being made available both from the Council and the Scottish Government. It is expected that the project could cost in the region of £9m and the Council receive 80% funding through the Scottish Government flooding allocation. The Scottish Government has provided £80k as a first allocation to start the project work. The Council has yet to consider how it will provide its (20%) share of the project.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Campbeltown FloodingReport | 81 KB | DownloadRead as text |
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... | Noted | Open |
| 2 Sep 2026 | Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... | Agreed | Open |
| 2 Sep 2026 | Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... | Noted | Open |
| 2 Sep 2026 | Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... | Noted | Open |
| 2 Sep 2026 | Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.