Resolved
Members agreed to note the presentation and content of the report. (Ref: Report by Acting Executive Director of Community Services, dated 5 April 2017, submitted.)
Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 5 April 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Members agreed to note the presentation and content of the report. (Ref: Report by Acting Executive Director of Community Services, dated 5 April 2017, submitted.)
1.1This report provides Members with progress on the Council’s Schools Redevelopment Project in partnership with hubNorth Scotland Ltd (hubNorth) to build a new secondary school in Campbeltown.
1.2The project continues to make good progress. The concrete floor slabs have been completed on all floors. The roofing works and secondary steelwork are nearing completion and the cladding to the building along with the external blockwork has commenced.
1.3Progress on the construction of the new school building is illustrated in a series of photographs in Paragraph 4.3.
1.4The third quarterly newsletter was made available at the end of February and through the dedicated Campbeltown Grammar School project website, hosted by Morrison Construction, at www.cgsproject.co.uk
1.5The school redevelopment projects have provided already a number of community benefits and through the projects it has been agreed that three modern apprenticeships will be provided at each site. Separate discussions are ongoing with the Facilities Management (FM) contractor to provide apprenticeships over the 25 year life span of the Design Build Finance and Maintain (DBFM) contract.
1.6Planning for the decant of pupils, staff and resources has commenced. Regular meetings will continue to take place and information will be issued at appropriate times from now through to the decant itself which is due to take place in February 2018.
1.7Partnerships Bulletin – Partnerships Awards 2017
HubNorth Scotland Ltd and Galliford Try nominated the Campbeltown and Oban DBFM project for the Partnerships Awards 2017 and the Project Team has been notified that the Campbeltown/Oban DBFM project has been shortlisted under two separate categories: Best Education Project; and Public Sector Procurer of the Year. 1 Separately, ABC Schools has nominated the current NPDO schools project which has been shortlisted for Best Operational Project.
The Gold and Silver Award winners in each category will be announced on Thursday 11 May 2017.
It is recommended that Members note the content of this report.
2 ARGYLL AND BUTE COUNCIL MAKI AREA COMMITTEE
COMMUNITY SERVICES 5 APRIL 2017 CUSTOMER SERVICES
NEW SCHOOLS REDEVELOPMENT PROJECT UPDATE CAMPBELTOWN GRAMMAR SCHOOL
2.0INTRODUCTION
2.1This report provides Members with progress on the Council’s Schools Redevelopment Project in partnership with hubNorth Scotland Ltd (hubNorth) to build a new secondary school in Campbeltown.
It is recommended that Members note the content of this report.
4.0DETAIL
4.1The new Campbeltown Grammar School Redevelopment Project is a Design Build Finance and Maintain (DBFM) Project being delivered as part of the Scottish Government’s Schools for the Future Programme pipeline with hubNorth Scotland Ltd, the Council’s project partner.
4.2Key Programme Dates The key programme dates are:
Date Description Comment May 2016 – Phase 1 – Construction of February new school building 2018 Pupils/staff move February Campbeltown Grammar into new school 2018 School Decant building Demolition of existing school April – Phase 2 buildings and November External Works construction of 2018 new 3G pitch and car park All works completed November Phase 2 Completion and whole school 2018 availability At this stage in the Phase 1 construction period, there is no change to the intended programme. 3 4.3 Construction Update The construction of the new building is progressing well with the following works completed since the previous update report provided to Members on 1 February 2017. Namely: Concrete floor slabs to ground, first and second floors; Underfloor heating pipes installed to ground floor atrium; Concrete shuttering to perimeter beam; and Secondary steel frame.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
New Schools Redevelopment Project: Campbeltown Grammar School UpdateReport | 1.8 MB | DownloadRead as text |
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... | Noted | Open |
| 2 Sep 2026 | Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... | Agreed | Open |
| 2 Sep 2026 | Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... | Noted | Open |
| 2 Sep 2026 | Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... | Noted | Open |
| 2 Sep 2026 | Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.