Decision The Committee considered and noted: 1. The Rothesay Pavilion Adaptive Restoration and Extension works contract had been fully funded with an anticipated final cost of £13,991,536 2. The contract had been awarded to Messrs CBC Ltd who remain on schedule to complete on 31 st July 2019. 3. The Project Manager left the Council on 4 th May 2018 to take up a new post with Highlands and Islands Enterprise (HIE). (Ref: Report by CHORD Programme Manager dated 5 th June 2018, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The purpose of this report is to provide members with an update on progress with the Rothesay Pavilion Adaptive Restoration and Extension Works project following completion of the funding package in September 2017 and the award of the construction contract to Messrs CBC Ltd in November 2017.
1.2In September 2017 the final approvals were received for additional funding from the Heritage Lottery Fund, European Regional Development Fund and Historic Environment Scotland to allow the project to proceed. Total anticipated final cost is £13,991,536
1.3Messrs CBC Ltd were awarded the construction contract and started work on site on 29th November 2017. The contract value is £10,688,023. The forecast completion date is 31st July 2019.
Recommendations
Bute and Cowal Area Committee is asked to Consider and Note:
2.1that the Rothesay Pavilion Adaptive Restoration and Extension Works contract has been fully funded with an anticipated final cost of £13,991,536
2.2that the contract has been awarded to Messrs CBC Ltd who remain on schedule to complete on 31st July 2019.
2.3that the Project Manager left the Council on 4th May 2018 to take up a new post with Highlands and Islands Enterprise (HIE). ARGYLL AND BUTE COUNCIL Bute and Cowal Area Committee
DEVELOPMENT & INFRASTRUCTURE 5th June 2018 SERVICES
Rothesay Pavilion Progress Report
3.0INTRODUCTION
3.1The project comprises the comprehensive refurbishment of the grade A listed Rothesay Pavilion which is a key component of the Council’s ambitious and forward looking programme to assist regeneration and economic development in five of its waterfront towns; Campbeltown, Helensburgh, Oban, Rothesay and Dunoon.
3.2The project will bring Rothesay Pavilion back into viable economic use by allowing a mix of new commercial, cultural and community activities to be provided within it. This will bring new life to this iconic building as well as stimulating wider regeneration and local economic activity.
3.3On completion the building will be managed by Rothesay Pavilion Charity (RPC) who will lease the building from the Council for a term of 25 years. The charity’s board comprises a mix of people who live on the island or who have links to it. However, they have the necessary skills and experience to successfully manage and programme the Pavilion and to ensure it has a sustainable future.
3.4Full funding for the project was achieved in September 2017 and a construction contract was awarded to Messrs CBC Ltd on 29th November 2017 with a projected completion date of 31st July 2019.
Bute and Cowal Area Committee is asked to Consider and Note:
4.1that the Rothesay Pavilion Adaptive Restoration and Extension Works contract has been fully funded with an anticipated final cost of £13,991,536. 4.2 that the contract has been awarded to Messrs CBC Ltd and a start on site was achieved on 29th November 2017 with a projected completion date of 31st July 2019. 4.3 that the Project Manager left the Council on 4th May to take up a new post with Highlands and Islands Enterprise (HIE) in their Strengthening Communities team. 5.0 DETAIL
5.1CBC has been on site since 29th November 2017 and at the time of writing they remain on programme to complete on 31st July 2019.
5.2Funding is now being actively drawn down from our four major external funding partners (HLF, HES, HIE and ERDF) with over £1M being received since the contract started. Funding applications are being submitted on an ongoing basis.
5.3In addition to the funding secured by the Council, Rothesay Pavilion Charity had a fundraising target of £400,000 to achieve. The Council agreed to underwrite this amount pending successful funding applications by the charity. Thus far the charity has been successful in securing £132,546 of this target made up as follows;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.