ROTHESAY PAVILION TO ALBERT PIER ACTIVE TRAVEL PROJECT - UPDATED REPORTS

Approved Committee 3 papers

Bute and Cowal Area Committee approved this item on Tuesday 3 June 2025. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

Decision The Bute and Cowal Area Committee approved the amendments made to the initial feasibility and concept design reports for the Rothesay Pavilion to Albert Pier Active Travel Project. (Reference: Report by Executive Director with responsibility for Development and Economic Growth, dated May 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Bute and Cowal Area Committee

Rothesay Pavilion to Albert Pier Active Travel Project Stage 1&2 Engagement Report DATE: February 2025 REF: 501053 VERSION: FINAL v2 Contents 1 APPROACH TO TRAVEL BEHAVIOUR CHANGE AND COMMUNITY ENGAGEMENT .............................. 1

2 STAGE 1 SURVEY QUESTIONNAIRE RESULTS ................................................................................. 15

3 STAGE 1 COMMUNITY FEEDBACK TOOL (CFT) RESULTS ................................................................. 28

4 STAGE 1 STAKEHOLDER FEEDBACK ................................................................................................ 33

5 STAGE 1 BARRIERS AND OPPORTUNITIES ..................................................................................... 37

6 STAGE 2 – COMMUNITY ENGAGEMENT ........................................................................................... 39

7 STAGE 2 - SURVEY QUESTIONNAIRE RESULTS ............................................................................... 44

8 STAGE 2 - COMMUNITY FEEDBACK TOOL (CFT) RESULTS .............................................................. 64

9 STAGE 2 - STAKEHOLDER FEEDBACK .............................................................................................. 76

10 OUR LESSONS LEARNT .................................................................................................................... 80

APPENDIX A – PROJECT HANDS UP SURVEY RESULTS .............................................................................. 83

APPENDIX B – STAGE 1 AND 2 PUBLIC EVENT ATTENDEES LIST (EVIDENCE)........................................... 84

APPENDIX C – ISLE OF BUTE NEWS SAMPLE EXTRACTS ............................................................................ 85

APPENDIX D – STAGE 2 SURVEY COMMENTS............................................................................................. 86

MARK RINKUS Managing Director [email removed] ` T N O D O L . IA N T D E F I N C O L Y CT R I S T 2|Page www.connectedtp.com APPROACH TO TRAVEL BEHAVIOUR CHANGE AND COMMUNITY ENGAGEMENT 1 APPROACH TO TRAVEL BEHAVIOUR CHANGE The process was collaborative with members of the study steering group including Bute Community Council helping to define the stakeholder mapping AND COMMUNITY ENGAGEMENT which evolved through the project lifecycle. 1.1 Relevant Previous Engagement and Consultation 1.3 Engagement Planning This project seeks to improve pedestrian links into Rothesay Town Centre and to A consultation and engagement plan were developed setting out the studies the Rothesay Pavilion making allowances for potential future active travel stage 1 engagement programme. The plan was used to identify all proposed connections. activities, the activity order, potential audience and engagement method. The study is aligned with the 2017, Rothesay Town Heritage Initiative (THI), town centre spatial strategy and was identified by the community during 2016 Rethink Rothesay Charrette.

1.2Stakeholder Mapping

A stakeholder mapping matrix was developed in conjunction with the design team's relevant experience. The stakeholder mapping aims to identify all stakeholders to be involved within the study and seeks to quantify each stakeholders forecast level of interest in the project and likely influence over the project.

The stakeholder’s mapping process was led by the council and supported by Bute Community Council using their knowledge of the community. The stakeholders were categorised into engagement tiers reflecting their engagement hierarchy using the mapping matrix (shown opposite).

Tiered stakeholder mapping developed mapping matrix

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
501053 Rothesay Engagement Report_Stage1&2_ FINALReport 4 MB DownloadRead as text
PDF
501053 Rothesay Options Feasibility_Stage12_FINALReport 3 MB Download
PDF
ROTHESAY PAVILION TO ALBERT PIER ACTIVE TRAVEL PROJECT: UPDATED REPORTSReport 114 KB Download

At this meeting

Whole meeting

Who was there

7 of 10 attended
GB
Councillor Gordon BlairChair, present
AF
Councillor Audrey ForrestMember, present
DH
Councillor Daniel HampseyMember, present
RK
Councillor Reeni Kennedy-BoyleVice-Chair, apologies
LM
Councillor Liz McCabeMember, present
YM
Councillor Yvonne McNeillyMember, apologies
RM
Councillor Ross MorelandMember, present
JS
Julieann SmallSecretary, expected
WS
Councillor William SinclairMember, present
PW
Councillor Peter WallaceMember, present

On this subject at Argyll and Bute

Search all
  1. ROTHESAY PAVILION TO ALBERT PIER ACTIVE TRAVEL PROJECT - UPDATED REPORTSThis decision
  2. Rothesay pavilion to albert pier active travel project: updated reportsAgreed
  3. Rothesay pavilion update reportNoted
  4. Rural growth deal – rothesay pavilionNoted
  5. Rothesay Pavilion UpdateNoted
  6. Scrutiny of Business Case Review (Rothesay Pavilion)Agreed

More from Argyll and Bute Bute and Cowal Area Committee

All decisions
MeetingDecisionOutcome
1 Sep 2026 Charts (argyll and the isles)Decision The Bute and Cowal Area Committee considered and noted the information provided in the presentation. (Refere... Noted Open
1 Sep 2026 Area committee quarterly performance reports fq1 2026/27Decision The Bute and Cowal Area Committee noted the performance and supporting commentary as presented. (Reference: ... Noted Open
1 Sep 2026 Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with... Agreed Open
1 Sep 2026 Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director... Noted Open
1 Sep 2026 Cruach mhor and clachan flats windfarm trustsDecision The Bute and Cowal Area Committee noted these updates, which are the most recent of the annual updates requi... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies