ROTHESAY PAVILION TO ALBERT PIER ACTIVE TRAVEL PROJECT: UPDATED REPORTS

Agreed Committee 3 papers

Bute and Cowal Area Committee agreed this item on Tuesday 4 March 2025. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

Decision The Bute and Cowal Area Committee agreed to continue consideration of this report to the June meeting to allow Officers to reflect on comments made during the meeting, specifically in terms of car parking and loading and servicing provision. (Reference: Report by Executive Director with responsibility for Development and Economic Growth, dated February 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Bute and Cowal Area Committee

Executive summary

1.1This report updates members in relation to changes made to the “Rothesay Pavilion to Albert Pier Active Travel Project Stage 1&2 Combined, Engagement Report” and “Rothesay, Pavilion to Albert Pier Car Park Active Travel Project Stage 1&2 Combined, Options Feasibility Report” documents for the Rothesay Pavilion to Albert Pier Active Travel Project following requests from Bute Community Council and Bute BID at this Committee on 03 December 2024.

1.2References to the Community Council have been updated to the official title of Bute Community Council.

1.3Comments previously attributed to Bute BID have been amended to note that comments provided at a meeting by a previous Bute BID Coordinator were provided in a personal capacity and not as a formal response by Bute BID.

Recommendations

It is recommended that the Bute and Cowal members:

i.Approve the changes made to the initial feasibility and concept design reports for the Rothesay Pavilion to Albert Pier Active Travel Project to update title of Bute Community Council and note that Bute BID did not submit a formal response. ARGYLL AND BUTE COUNCIL Bute and Cowal Area Committee

DEVELOPMENT AND ECONOMIC 04 March 2025 GROWTH

Rothesay Pavilion to Albert Pier Active Travel Project: Updated Reports

2.0INTRODUCTION

2.1This report updates members in relation to changes made to the “Rothesay Pavilion to Albert Pier Active Travel Project Stage 1&2 Combined, Engagement Report” and “Rothesay, Pavilion to Albert Pier Car Park Active Travel Project Stage 1&2 Combined, Options Feasibility Report” documents for the Rothesay Pavilion to Albert Pier Active Travel Project following requests from Bute Community Council and Bute BID at this Committee on 03 December 2024.

3.1It is recommended that the Bute and Cowal members:

i. Approve the changes made to the initial feasibility and concept design reports for the Rothesay Pavilion to Albert Pier Active Travel Project to update title of Bute Community Council and note that Bute BID did not submit a formal response.

4.0DETAIL

4.1At this Committee on 03 December 2024 the Convener of Bute Community Council raised that the Bute Community Council had incorrectly been referred to as “Rothesay Community Council” in a number of places in the reports. Officers agreed to correct the report.

4.2References to the Community Council have been updated to the official title of Bute Community Council. The Convener of Bute Community Council thanked Officers for making this update via email on 27 January 2025.

4.3At this Committee on 03 December 2024 a member of the Bute BID board raised that the Bute BID had not provided a formal response to the consultation and that the comments attributed to the Bute BID in the report were not the formal response of Bute BID. Officers agreed to correct the report.

4.4As part of the consultation in developing the project, a meeting was arranged on 05 August 2024 with the Bute BID Coordinator in post at the time specifically to get Bute BID’s comments on the proposals. The Bute BID Coordinator agreed to distribute the meeting invitation to the wider Bute BID Board. In the event, only the Bute BID Coordinator attended the meeting but at no point stated that they were not speaking on behalf of Bute BID or that any comments made were personal and shouldn’t be attributed to Bute BID. As such, the comments made by the Bute BID Coordinator at the meeting were unknowingly incorrectly included as being a response from Bute BID.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
501053 Rothesay Options Feasibility_Stage12_FINAL KC 2025-02-18Appendix 1 3 MB Download
PDF
501053 Rothesay Engagement Report_Stage1&2_ FINAL KC 2025-02-18Appendix 2 4 MB Download
PDF
ROTHESAY PAVILION TO ALBERT PIER ACTIVE TRAVEL PROJECT: UPDATED REPORTSReport 113 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
GB
Councillor Gordon BlairChair, present
AF
Councillor Audrey ForrestMember, present
DH
Councillor Daniel HampseyMember, present
RK
Councillor Reeni Kennedy-BoyleVice-Chair, present
LM
Councillor Liz McCabeMember, present
YM
Councillor Yvonne McNeillyMember, present
RM
Councillor Ross MorelandMember, present
JS
Julieann SmallSecretary, expected
WS
Councillor William SinclairMember, present
PW
Councillor Peter WallaceMember, present

On this subject at Argyll and Bute

Search all
  1. ROTHESAY PAVILION TO ALBERT PIER ACTIVE TRAVEL PROJECT: UPDATED REPORTSThis decision
  2. Rothesay pavilion to albert pier active travel project - updated reportsApproved
  3. Rothesay pavilion update reportNoted
  4. Rural growth deal – rothesay pavilionNoted
  5. Rothesay Pavilion UpdateNoted
  6. Scrutiny of Business Case Review (Rothesay Pavilion)Agreed

More from Argyll and Bute Bute and Cowal Area Committee

All decisions
MeetingDecisionOutcome
1 Sep 2026 Charts (argyll and the isles)Decision The Bute and Cowal Area Committee considered and noted the information provided in the presentation. (Refere... Noted Open
1 Sep 2026 Area committee quarterly performance reports fq1 2026/27Decision The Bute and Cowal Area Committee noted the performance and supporting commentary as presented. (Reference: ... Noted Open
1 Sep 2026 Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with... Agreed Open
1 Sep 2026 Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director... Noted Open
1 Sep 2026 Cruach mhor and clachan flats windfarm trustsDecision The Bute and Cowal Area Committee noted these updates, which are the most recent of the annual updates requi... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies