Decision The Council:- noted the revenue budget monitoring position as at the end of the financial year 2017/18. noted that the unallocated balance within the General Fund as at 31 March 2018, after taking into account the contingency, amounted to £1.868m. (Ref: Report by the Head of Strategic Finance dated June 2018, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The main purpose of this report is to advise Members of the revenue budget position of the Council as at the end of financial year 2017-18. The report also summarises the movement in the General Fund balance.
1.2The performance against budget for financial year 2017-18 was an overall underspend of £2.567m (1.03%).
1.3There was a net underspend of £0.958m in relation to departmental expenditure and a net underspend of £0.877m in relation to other central/non-departmental costs. The remainder of the underspend of £0.732m is in relation to funding and the over-recovery of Council Tax income. Included within the overall underspend are a number of budget underspends which are likely to be one-off in nature or have been adjusted for in the 2018-19 budget process.
1.4The General Fund Balance has moved from £53.489m at the end of financial year 2016- 17 to £50.311m at the end of 2017-18. The movement represents a decrease of £3.178m which is due to the contributions to and from earmarked reserves and the favourable year-end underspend position.
1.5There is a separate report that details the earmarked reserves; it outlines proposals to earmark a total of £43.717m from the General Fund balance, leaving £6.594m unallocated. Of this £4.726m is required to be held as the General Fund contingency, leaving an unallocated balance of £1.868m. ARGYLL AND BUTE COUNCIL COUNCIL
STRATEGIC FINANCE 28 JUNE 2018
REVENUE BUDGET MONITORING – FOR THE YEAR 2017-18
2. INTRODUCTION
2.1This report summarises the revenue budget position of the Council as at the end of the financial year 2017-18. The overall revenue budget monitoring statement for the Council is attached as Appendix 1 and departmental outturn summaries are attached as Appendix 2.
Recommendation
3.1Members to consider the revenue budget monitoring position as at the end of financial year 2017-18.
3.2Members to note that the unallocated balance within the General Fund as at 31 March 2018, after taking into account the contingency, amounts to £1.868m.
4. DETAIL
4.1Final Outturn Variance (Un-audited)
4.1.1 The performance against budget for the financial year 2017-18 was an overall underspend of £2.567m (1.03%). A summary of the final outturn position is noted within the table below: 4.2 Departmental Budget Outturn
4.2.1 The performance against budget shows departmental controllable expenditure being £0.958m (0.61%) under budget. Included in this outturn position is an adjustment to update the 2017-18 budget to reflect the new amounts earmarked by departments at the year-end, these new earmarkings total £2.870m.
4.2.2 The main reasons giving rise to the departmental underspend of £0.958m are noted below and further detail is provided within the departmental outturn reports in Appendix 2.
Underspends within Customer Services due to lower than expected insurance and utility cost savings arising as a result of the annual renegotiation of insurance costs which forms part of the contract management arrangements which are in place for the NPDO, lower than planned expenditure on the Catering Innovation Project which was delayed and lower than expected expenditure on school transport due to reduced contract and fuel costs. Further, within Development and Infrastructure Services, there was an over-recovery of income from charges for fish exports and the appraisal of water supplies. Also, there were higher than expected vacancy savings delivered by the Customer Services and Development and Infrastructure Services Departments.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.