ARGYLL AND BUTE COUNCIL COUNCIL STRATEGIC FINANCE 28 June 2018
CAPITAL BUDGET MONITORING REPORT – 31 March 2018
1 EXECUTIVE SUMMARY 1.1 This provides an update on the position of the capital budget as at 31 March 2018. The report provides information on the financial position in respect of the capital plan and also the performance in terms of delivery of capital plan projects.
1.2Financial Position: • Outturn for 2017-18 – Expenditure for the full financial year is £31,094k compared to an annual budget of £38,537k giving rise to an underspend for the year of £7,443k (19.3%). The main projects contributing to this underspend are outlined below and further detail can be found in Appendix 1.
Block Allocation (DIS-RAMS) £513K. Scope and allocation of block allocations to be confirmed. Effects on projects to be advised. Street Lighting LED Replacement £1,211K. Current project expected to end in 2018/19. Still progressing the current project which was delayed slightly due to resourcing levels. Balance not spent in 17-18 has been forecast for 18-19. CHORD – Helensburgh £764K. Paper submitted to spend this surplus therefore not available for spending elsewhere. CHORD – Oban £724K. Budget for this project is awaiting virement to the Transit Berthing Facility Dunoon CARS £500K. Grants to be paid out in 18/19 and 19/20.
• Total Capital Plan – the forecast total net project costs on the total capital plan are £219,650k compared to a total budget for all projects of £219,152k giving rise to a forecast overspend for the overall capital plan of £-498k (-0.23%). The forecast overspend is within the capital programme tolerances and requires no corrective action to be taken as the actual spend will only be determined when the projects are completed.
Page 1 of 8 1.3 Project Delivery:
• Asset Sustainability – Out of 133 projects there are 118 projects (89%) on track and 15 projects (11%) off track and recoverable. • Service Development - Out of 26 projects there are 18 projects (69%) on track and 8 projects (31%) off track and recoverable. • Strategic Change – Out of 35 projects there are 23 projects (66%) on track and 12 projects (34%) off track and recoverable.
1.4The Council has received capital receipts of £5,768k up to 31 March 2018 against a budget of £6,340k (91%). 1.5 The actual capital receipts across the capital programme are now going to be less than budget due to the conclusion of one large sale for less than originally anticipated. The shortfall of £2.668m has been considered as part of the Council’s budget process for 2018-19.
Page 2 of 8 ARGYLL AND BUTE COUNCIL COUNCIL STRATEGIC FINANCE 28 June 2018
CAPITAL BUDGET MONITORING REPORT – 31 March 2018
2 INTRODUCTION
2.1This provides an update on the position of the capital budget as at 31 March 2018. The report provides information on the financial position in respect of the capital plan and also the performance in terms of delivery of capital plan projects.
2.2Financial Position:
• Outturn for 2017-18 – Expenditure for the full financial year is £31,094k compared to an annual budget of £38,537k giving rise to an underspend for the year of £7,443k (19.3%). The main projects contributing to this underspend are outlined below and further detail can be found in Appendix 1.
Block Allocation (DIS-RAMS) £513K. Scope and allocation of block allocations to be confirmed. Effects on projects to be advised. Street Lighting LED Replacement £1,211K. Current project expected to end in 2018/19. Still progressing the current project which was delayed slightly due to resourcing levels. Balance not spent in 17-18 has been forecast for 18-19. CHORD – Helensburgh £764K. Paper submitted to spend this surplus therefore not available for spending elsewhere. CHORD – Oban £724K. Budget for this project is awaiting virement to the Transit Berthing Facility Dunoon CARS £500K. Grants to be paid out in 18/19 and 19/20.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Budget Monitoring Report Year End Report 2017-18Report | 344 KB | DownloadRead as text |
Follow Argyll and Bute Council at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro... | Decided | Open |
| 23 Sep 2026 | Nhs highland director of public health annual report 2025Decision The Council – 1. noted the Director of Public Health Annual Report 2025; and 2. supported the recommendation... | Noted | Open |
| 23 Sep 2026 | Leader's reportDecision The Council – 1. noted the contents of the submitted report; and 2. noted that any reports, briefings or cop... | Noted | Open |
| 23 Sep 2026 | Policy leads reportDecision The Council noted the content of the submitted report. (Reference: Report by Policy Lead Councillors dated 1... | Noted | Open |
| 23 Sep 2026 | Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.