Resolved
The Audit and Scrutiny Committee agreed to endorse the contents of the report. (Ref: Report by Chief Internal Auditor, dated 21 January 2020, submitted.)
Audit and Scrutiny Committee agreed this item on Friday 24 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
The Audit and Scrutiny Committee agreed to endorse the contents of the report. (Ref: Report by Chief Internal Auditor, dated 21 January 2020, submitted.)
2.1To endorse the contents of the report.
3.0DETAIL
3.1The two tables below provide a numerical summary of open audit actions with a split between actions due between 01 July and 30 November 2019 and actions due after 30 November 2019.
Actions Due between 01 July 2019 and 30 November 2019
Service Complete Delayed / Total Rescheduled INTERNAL AUDIT Cross Cutting 1 5 6 Development & Economic Growth 2 1 3 Learning & Teaching 3 0 3 Legal & Regulatory 2 1 3 TOTAL 8 7 15
Actions due after 30 November 2019
Service Complete On Delayed & Total Course Rescheduled INTERNAL AUDIT Adult Care 0 5 0 5 Commercial Services 0 1 0 1 Cross Cutting 1 1 6 8 Customer & Support Services 1 0 0 1 Customer Support Services 0 5 0 5 Education 0 9 1 10 Financial Services 2 3 0 5 Legal & Regulatory Support 1 10 0 11 Lifelong Learning & Support 0 1 0 1 Roads & Infrastructure 0 6 1 7 Services EXTERNAL AUDIT Financial Services 0 1 0 1 TOTAL 5 42 8 55
3.2Appendix 1 provides further detail on actions that have either been delayed and rescheduled or for which Internal Audit have received no response from the service to inform this follow up.
4.0CONCLUSION
4.1Satisfactory progress continues to be made implementing audit actions.
5.0IMPLICATIONS
5.1Policy - None 5.2 Financial - None 5.3 Legal - None 5.4 HR - None 5.5 Fairer Scotland Duty - None 5.5.1 Equalities – None 5.5.2 Socio-Economic Duty – None 5.5.3 Islands Duty - None 5.6 Risk –None 5.7 Customer Service – None
Laurence Slavin Chief Internal Auditor 24 January 2020
For further information please contact: Laurence Slavin, Chief Internal Auditor, 01436 657694
APPENDICES Appendix 1 – Action Plan Points Delayed & Rescheduled or with No Response Appendix 1 - Action Plan Points Delayed & Rescheduled or with No Response
Action Plan Points Due between 01 July 2019 and 30 November 2019 Service / Finding Priority Agreed Action Dates Comment Responsible Report Officer / Status Cross Cutting Values in action N/A Create a 31 Jul 2019 Delayed due to lack of Comms Rep or – communication plan to 10 Sep 2019 resources in Comms CSG/Director of Organisational continue the roll out of 31 Dec 2019 Team Development Culture & 2019 the new corporate 31 Mar 2020 and Employee values and raise staff Delayed and Infrastructure Survey Action awareness of them Rescheduled Plan Cross Cutting Management Employee N/A Introduce a rolling 31 Aug 2019 Delayed due to SMT – links programme of SMT 31 Oct 2019 restructure within SMT Organisational blogs 30 Nov 2019 including creation of Culture & 2019 31 Mar 2020 extended SMT Employee Survey Action Delayed & Plan Rescheduled
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal and External Audit Report Follow Up 2019-20Report | 88 KB | DownloadRead as text |
Follow Audit and Scrutiny Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | Internal Audit and Counter Fraud Summary of ActivitiesDecision The Audit and Scrutiny Committee reviewed and endorsed the Summary of Activities report. (Reference: Report ... | Decided | Open |
| 3 Sep 2026 | Internal and External Audit Report Follow Up 2026-27Decision The Audit and Scrutiny Committee endorsed the contents of the report. (Reference: Report by Chief Internal A... | Decided | Open |
| 3 Sep 2026 | Internal Audit Reports to Audit and Scrutiny Committee 2026/2027Decision The Audit and Scrutiny Committee reviewed and endorsed the summary report and detail within each individual ... | Decided | Open |
| 3 Sep 2026 | External Audit Progress UpdateDecision The Audit and Scrutiny Committee agreed to note the information provided. | Agreed | Open |
| 3 Sep 2026 | Verbal Update by Chair(s) of Scrutiny PanelDecision The Audit and Scrutiny Committee noted the information provided. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.