CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Business Continuity Committee, Thursday 16 April 2020 at 10.30am

SKIPNESS (CONSULTATION) (SCOTLAND) ACT 2010 - SKIPNESS PRIMARY SCHOOL

Agreed Committee 1 paper

Business Continuity Committee agreed this item on Thursday 16 April 2020. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

Decision The Committee:- 1. Agreed to the extension of the current consultation period, due to end on 15 May 2020 to 31 August 2020. 2. Agreed that the public meeting scheduled for 6 May 2020 is cancelled and a new date established once the current UK/Scottish Government restrictions on public assemblies are reduced or lifted. (Ref: Report by Executive Director with responsibility for Education dated 31 March 2020, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Business Continuity Committee

Executive summary

1.1In response to the current Coronavirus (Covid-19) pandemic this report sets out proposals to extend the current six week statutory consultation exercise with regard to the proposal to close Skipness Primary School and to re-schedule the public meeting, currently set for 6th May 2020, when the Covid-19 situation subsides.

1.2Members are asked to:-

1.2.1 Agree the extension of the current consultation period, due to end on 15th May 2020, to 31st August 2020;

1.2.2 Agree that the public meeting scheduled for 6th May 2020 is cancelled and a new date established once the current UK/Scottish Government restrictions on public assemblies are reduced/lifted. ARGYLL AND BUTE COUNCIL BUSINESS CONTINUITY COMMITTEE EDUCATION 16 APRIL 2020

SCHOOLS (CONSULTATION) (SCOTLAND) ACT 2010 – SKIPNESS PRIMARY SCHOOL

2.0INTRODUCTION

2.1Skipness Primary School has been mothballed since October 2016 and since that time has had no pupils enrolled.

2.2On 5th September 2019 the Community Services Committee agreed that the Education Service would undertake the required preliminary consultation and an Options Appraisal for Skipness Primary School. A report providing details of the Options Appraisal, which was carried out in accordance with Section 12A of the Schools (Consultation) (Scotland) Act 2010, was tabled at the Community Services Committee held on 10th December 2019, where the Committee agreed to note the outcome of the preliminary requirements and requested that officers formulate a draft proposal.

2.3At the Community Services Committee held on 12th March 2020, Members considered and agreed to adopt the draft proposal as a “relevant proposal” that would proceed to a statutory consultation under the Schools (Consultation) (Scotland) Act 2010, as amended.

Recommendations

Members are asked to:-

3.1Agree the extension of the current consultation period, due to end on 15th May 2020, to 31st August 2020;

3.2Agree that the public meeting scheduled for 6th May 2020 is cancelled and a new date established once the current UK/Scottish Government restrictions on public assemblies are reduced/lifted.

3.0DETAIL

4.1Following agreement of the draft proposal at the Community Services Committee on 12th March 2020, Officers have commenced the statutory consultation exercise under the Schools (Consultation) (Scotland) Act 2010, with regard to the proposed closure of Skipness Primary School with effect from 28th October 2020.

4.2As part of the consultation exercise the Education Authority has published the proposal paper, advertised it, and notified Education Scotland and all of the relevant consultees as prescribed by Schedule 2 of the Act, inviting them to make representations on the proposal.

4.3The 6 week consultation period commenced on 19th March and is due to end at close of business on 15th May 2020, which meets the statutory requirements and includes at least 30 school days. A public meeting has also been arranged for 6th May at 7pm in Skipness Village Hall.

4.4Given the current situation surrounding Covid-19 and the UK/Scottish Government restrictions on public assemblies it is recommended that the public meeting scheduled for 6th May 2020 is postponed until such time as the current restrictions are reduced/lifted to allow public gatherings. Section 7 of the Act states that the public meeting must be held during the consultation period and, given that the current consultation period is due to end on 15th May, it is recommended that this is extended until 31st August 2020. This will allow more flexibility in terms of rearranging the public meeting and also provides stakeholders with an extended timeframe to participate in the consultation process. If the position regarding restrictions on public gatherings changes, then re-scheduling of the public meeting can be brought forward/looked at again.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SKIPNESS (CONSULTATION) (SCOTLAND) ACT 2010: SKIPNESS PRIMARY SCHOOLReport 86 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
RC
Councillor Rory ColvilleMember, present
RC
Councillor Robin CurrieMember, present
LD
Councillor Lorna DouglasMember, present
FF
Fiona FergusonSecretary, expected
KG
Councillor Kieron GreenMember, present
YM
Councillor Yvonne McNeillyMember, apologies
AM
Councillor Aileen MortonChair, present
GM
Councillor Gary MulvaneyVice-Chair, present
DP
Councillor Douglas PhilandMember, present
ST
Councillor Sandy TaylorMember, present

On this subject at Argyll and Bute

Search all
  1. SKIPNESS (CONSULTATION) (SCOTLAND) ACT 2010 - SKIPNESS PRIMARY SCHOOLThis decision
  2. Schools (consultation) (scotland) act 2010 - skipness primary schoolNoted
  3. Schools (consultation) (scotland) act 2010 - skipness primary schoolAgreed
  4. Schools (consultation) (scotland) act 2010 - skipness primary schoolAgreed
  5. Schools (consultation) (scotland) act 2010 - skipness primary schoolAgreed
  6. Schools (consultation) (scotland) act 2010 - skipness primary schoolNoted

More from Argyll and Bute Business Continuity Committee

All decisions
MeetingDecisionOutcome
13 Aug 2020 Financial report monitoring pack - 30 june 2020Decision The Committee:- 1. Considered the revenue budget monitoring report as at 30 June 2020 and noted the comments... Noted Open
13 Aug 2020 Budget update 2020-21Decision The Committee:- 1. Noted the current estimated additional costs as a result of the Covid-19 pandemic across ... Noted Open
13 Aug 2020 Budget outlook 2021-22 to 2025-26Decision The Committee noted the current estimated budget outlook position for the period 2021-22 to 2025-26. (Ref: R... Noted Open
13 Aug 2020 Budget planning 2021-22 and beyondDecision The Committee:- 1. Agreed to the overall budget approach for 2021-22 and the themed reviews as identified in... Agreed Open
13 Aug 2020 Public conveniences remobilisationDecision The Committee:- 1. Agreed to Option 2, that is to keep the current 35 public conveniences open until the end... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies