Decision The Committee: 1. Noted the detail of the 45 responses received during the 6 week consultation period, set out in Appendices 1 and 2; 2. Agreed the revised Integration Scheme (Appendix 3), which had been further updated to take account of feedback received as part of the consultation process; 3. Noted that additional revisions to the Integration scheme may be required in respect of the power to delegate functions in terms of the Children and Young People (Scotland) Act 2014, once in receipt of advice from the Scottish Government; and 4. Noted that a similar report was tabled at the NHS Highland Board on 31 March 2020 where the revised Integration scheme was approved; and 5. Agreed that the Chief Executives of the two parent bodies jointly submit the revised Scheme to the Scottish Government for their consideration, at the appropriate time. (Ref: Report by Executive Director with responsibility for Legal and Regulatory Support dated 3 March 2020, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The full Council and NHS Highland Board, at their meetings held on 28th and 26th November 2019 respectively, approved revisions made to the Health and Social Care Integration Scheme following a review process and agreed that Officers should proceed with arrangements for a 6 week joint consultation exercise, running from 9th December 2019 to 17 January 2020. During this period a total of 45 responses were received and details of these are attached at appendices 1 and 2.
1.2A review of all the consultation responses has been undertaken by the Working Group that was set up to up to initiate the 5 year review process, at their meeting held on 28 January 2020. Having taken account of all feedback received, a number of further revisions are proposed to the Scheme. The detail of these can be found in the last column of the table within Appendix 1, which outlines the Working Group’s response to the consultation feedback. The Scheme has been updated to reflect the proposed changes arising from the consultation process (highlighted in yellow) and a copy is attached at Appendix 3 for consideration and approval.
Recommendations
Members are asked to:-
2.1Note the detail of the 45 responses received during the 6 week consultation period, set out in Appendices 1 and 2;
2.2Agree the revised Integration Scheme (Appendix 3), which has been further updated to take account of feedback received as part of the consultation process;
2.3Note that additional revisions to the integration Scheme may be required in respect of the power to delegate functions in terms of the Children and Young People (Scotland) Act 2014, once in receipt of advice from the Scottish Government; and
1 2.4 Note that a similar report was tabled at the NHS Highland Board on 31 March 2020, where the revised Integration Scheme was approved; and
2.5Agree that the Chief Executives of the two parent bodies jointly submit the revised Scheme to the Scottish Government for their consideration, at the appropriate time.
3. DETAIL
3.1The legal requirement to complete a review of an Integration Scheme is set out in Section 44 of the Public Bodies (Joint Working) (Scotland) Act 2014 (the Act). The Scheme must be reviewed each subsequent period of 5 years beginning with the day on which the Scheme was approved, in the case of Argyll and Bute, 27 June 2015. On this basis the review of the Scheme in Argyll and Bute is required by law to be completed by 27 June 2020. The statutory responsibility to review the Scheme sits with the Board of NHS Highland and Argyll and Bute Council.
3.2Following a joint review process, the Council and NHS Highland approved the revised Integration Scheme at their respective meetings held at end November 2019 and agreed that, in accordance with Section 46(4) of the Public Bodies (Joint Working) (Scotland) Act 2014, the Council and the Health Board should undertake a joint consultation on the revised Scheme.
3.3Arrangements for the joint consultation, which ran from 9th December 2019 until 17th January 2020, were put in place, including:-
Email/postal correspondence issued to all prescribed stakeholders and any others deemed appropriate (870+ targeted) Use of Council ‘Keep in the Loop’ service to promote the consultation to customers who have advised they would like to be engaged in consultation activity (3890+ targeted) Details of the consultation uploaded to Council and NHS Highland Websites Posts on social media Press release issued Hard copies placed in Council Customer Service Points and issued upon request
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2021-22 to 2025-26Decision The Committee noted the current estimated budget outlook position for the period 2021-22 to 2025-26. (Ref: R...
Budget planning 2021-22 and beyondDecision The Committee:- 1. Agreed to the overall budget approach for 2021-22 and the themed reviews as identified in...
Public conveniences remobilisationDecision The Committee:- 1. Agreed to Option 2, that is to keep the current 35 public conveniences open until the end...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.