THE SCOTTISH GOVERNMENT ON BEHALF OF SLR CONSULTING LIMITED: ELECTRICITY ACT SECTION 36 CONSULTATION RELEVANT TO SHEIRDRIM RENEWABLE ENERGY DEVELOPMENT: LAND AT GARTNAGRENACH FOREST, WHITEHOUSE, ARGYLL (REF: 19/02424/S36)

Agreed Planning 2 papers

Planning, Protective Services and Licensing Committee agreed this item on Wednesday 20 May 2020. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

Decision The Committee agreed to object to this proposal for the reasons outlined in the report of handling subject to including reference to the proposed development having an adverse landscape and visual impact on the villages of Clachan and Whitehouse and that the Scottish Government be notified accordingly. Reference: Report by Head of Development and Economic Growth dated 6 May 2020, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Planning, Protective Services and Licensing Committee
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
1902424S36 planReport 888 KB Download
PDF
THE SCOTTISH GOVERNMENT ON BEHALF OF SLR CONSULTING LIMITED: ELECTRICITY ACT SECTION 36 CONSULTATION RELEVANT TO SHEIRDRIM RENEWABLE ENERGY DEVELOPMENT: LAND AT GARTNAGRENACH FOREST, WHITEHOUSE, ARGYLL (REF: 19/02424/S36)Report 408 KB Download

At this meeting

Whole meeting

Who was there

12 of 15 attended
GB
Councillor Gordon BlairMember, present
RC
Councillor Rory ColvilleVice-Chair, present
RC
Councillor Robin CurrieMember, present
MD
Councillor Mary-Jean DevonMember, present
LD
Councillor Lorna DouglasMember, present
AF
Councillor Audrey ForrestMember, apologies
GF
Councillor George FreemanMember, present
GH
Councillor Graham HardieMember, apologies
DK
Councillor David KinniburghChair, present
DM
Councillor Donald MacMillan BEMMember, apologies
RM
Councillor Roderick McCuishMember, present
JM
Councillor Jean MoffatMember, present

All 15 on the meeting page

On this subject at Argyll and Bute

Search all
  1. THE SCOTTISH GOVERNMENT ON BEHALF OF SLR CONSULTING LIMITED: ELECTRICITY ACT SECTION 36 CONSULTATION RELEVANT TO SHEIRDRIM RENEWABLE ENERGY DEVELOPMENT: LAND AT GARTNAGRENACH FOREST, WHITEHOUSE, ARGYLL (REF: 19/02424/S36)This decision
  2. National Islands Plan and Scottish Government Population PoliciesNoted
  3. Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Agreed
  4. Esb asset development (uk) ltd: scottish government section 36 consultation for west torrisdale wind farm comprising of up to 9 wind turbines with a tip height of up to 149.9 metres with a predicted output of up to 6 mw per wind turbine, inAgreed
  5. Scottish government consultation response - draft national climate change plan 2026-2040Approved
  6. Voltalia uk ltd (scottish government consultation): section 36 consultation to construct and operate 6 wind turbines with a ground to blade tip height of 200 metres, and associated infrastructure including battery energy storage system andAgreed

More from Argyll and Bute Planning, Protective Services and Licensing Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Beaufort wind limited: erection of 7 turbines (up to 149.9m to tip) and ancillary development and decommissioning of existing beinn ghlas wind farm: existing beinn ghlas wind farm, taynuilt (ref: 25/01240/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. PP - A... Agreed Open
15 Sep 2026 Mr tony coogan: alterations to guesthouse to facilitate lawful use of existing roof space as ancillary guest house owner's accommodation: greencourt, benvoullin road, oban (26/00434/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Mrs faulkes: proposed alterations and erection of extension: 30 the green, craobh haven (ref: 26/01009/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Decision The Committee agreed that the Scottish Government’s Marine Directorate should be notified that Argyll and Bu... Agreed Open
15 Sep 2026 Development management performance update - fq1 2026/27Decision The Committee reviewed and agreed the content of the report. (Reference: Report by Executive Director with r... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies