Argyll and Bute Council
Planning, Protective Services and Licensing Committee, Wednesday 21 January 2026 at 11.00am

VOLTALIA UK LTD (SCOTTISH GOVERNMENT CONSULTATION): SECTION 36 CONSULTATION TO CONSTRUCT AND OPERATE 6 WIND TURBINES WITH A GROUND TO BLADE TIP HEIGHT OF 200 METRES, AND ASSOCIATED INFRASTRUCTURE INCLUDING BATTERY ENERGY STORAGE SYSTEM AND

Agreed Planning 3 papers

AI summaryArgyll and Bute Council has objected to a six-turbine wind farm at Cruach Clenamacrie, near Oban, citing landscape and visual impacts. The Council does not object on noise, public access or roads grounds, subject to conditions, and seeks peat landslide risk resolution.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedOn landscape and peat grounds
MoneyNot stated
What happens nextNotify Energy Consents UnitOf the Council's view
Who it affectsVoltalia UK Ltd proposalSix turbine wind farm

What was decided

The Committee agreed the Council objects to the proposal on landscape and visual grounds, as the six-turbine wind farm would result in significant adverse effects contrary to NPF4 Policy 11 and LDP2 Policy 30.

The Committee agreed the Council objects unless the Peat Landslide Hazard Risk Assessment is resolved to the satisfaction of Ironside Farrar before the Energy Consents Unit determines the application.

The Committee agreed the Council does not object on noise, public access or roads grounds, subject to conditions from Mott MacDonald, an access plan, and Transport Scotland respectively, and requested biodiversity and ornithology recommendations be considered.

Why

The proposed wind farm would cause significant adverse landscape and visual effects, contrary to NPF4 Policy 11 and LDP2 Policy 30.

No response was provided by Ironside Farrar on further peat landslide information, and no response was received from the West of Scotland Archaeology Service on archaeological impact.

The Council's Noise Consultant Mott MacDonald recommended a noise condition, Transport Scotland specified road conditions, and NatureScot noted possible impacts on Schedule 1 bird species and a regionally important black grouse population.

What happens next

The Council will notify the Energy Consents Unit of its views on the Section 36 application.

The Peat Landslide Hazard Risk Assessment must be resolved to the satisfaction of Ironside Farrar before determination, otherwise the Council will defer to expert guidance.

The applicant is recommended to continue discussions with NatureScot and SEPA on peat extraction and restoration, monitor bat fatalities, and implement a programme of monitoring fences for black grouse carcasses.

Options considered

  • Chosen: Object on landscape and visual grounds. Significant adverse effects contrary to NPF4 Policy 11 and LDP2 Policy 30
  • Chosen: Object unless peat landslide risk resolved. No response from Ironside Farrar on further information
  • Chosen: Do not object on noise grounds with condition. Mott MacDonald recommended operational noise planning condition
  • Chosen: Do not object on public access with condition. Subject to an approved Access Plan prior to construction
  • Chosen: Do not object on roads grounds with conditions. Subject to Transport Scotland conditions from 04/02/25

Implications

  • Legal: The Council is making a formal objection as part of the Section 36 consultation by the Scottish Government's Energy Consents Unit.
  • Risk: The Council defers to Ironside Farrar or any other expert body appointed by the ECU on peat landslide risk if unresolved.
  • Other: The Council cannot confirm whether the proposal is consistent with NPF4 Policy 7 and LDP2 Policy 21 on archaeology due to no response from the West of Scotland Archaeology Service.

Who and where

  • Voltalia UK Ltd, the applicant
  • The Scottish Government Energy Consents Unit as determining authority
  • Communities near the proposed Cruach Clenamacrie wind farm site Report P2, P4

Timeline

  • 04/02/25: Transport Scotland consultation response provided to the ECU
  • March 2025: Mott MacDonald Review of Evidence on Noise published
  • 6 January 2026: Report by Head of Development and Economic Growth
  • 20 January 2026: Supplementary report number 1

Plain English for the jargon

  • Section 36: Consent under the Electricity Act for large electricity generation developments, determined by the Scottish Government
  • ECU: Energy Consents Unit of the Scottish Government
  • NPF4: National Planning Framework 4, Scottish Government planning policy
  • LDP2: Local Development Plan 2 for Argyll and Bute
  • BESS: Battery Energy Storage System, part of the proposed development
  • PLI: Peat Landslide Incident
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Decision The Committee agreed that the ECU be notified accordingly that: 1. Argyll and Bute Council object to the proposal on landscape and visual grounds, as the proposed wind farm would result in significant adverse landscape and visual effects, contrary to NPF4 Policy 11 and LDP2 Policy 30. 2. Peat Landslide Hazard Risk Assessment - Argyll and Bute Council has been unable to reach a conclusion in respect to the Peat Landslide Hazard Risk Assessment (NPF4 Policies 5 and 11 and LDP2 30 and 79) as no response has been provided by Ironside Farrar on the further information provided by the Applicant. Argyll and Bute Council OBJECT unless this issue is resolved to the satisfaction of Ironside Farrar prior to the determination of this application by the ECU. Should this issue not be resolved the Council would defer to Ironside Farrar (or any other body appointed by the ECU to provide expert guidance on this matter) in the event of a PLI. 3. Archaeological Impact - Argyll and Bute Council has been unable to reach a conclusion within the time afforded in respect to Archaeological Impact as no response has been received from the West of Scotland Archaeology Service. Argyll and Bute Council are therefore not in a position to confirm whether the proposal is consistent with the relevant provisions of NPF4 Policy 7 and LDP2 Policy 21 and would recommend that the ECU consider these matters prior to determination. 4. Argyll and Bute do not object on noise impact grounds, subject to the inclusion of an Operational Noise Planning Condition, as recommended by the Council’s Noise Consultant, Mott MacDonald, specified in their Review of Evidence – Noise, dated March 2025. 5. Argyll and Bute Council do not object on Public Access grounds, subject to the inclusion of a condition requiring the developer to prepare an Access Plan for approval by the Council prior to the commencement of construction. 6. Argyll and Bute Council do not object on Roads grounds, subject to the inclusion of relevant conditions, as specified by Transport Scotland in their consultation response to the ECU dated 04/02/25. 7. Argyll and Bute Council requests that the recommendations of the Council’s Local Biodiversity Officer are considered by the ECU, including: Recommend that the applicant continue discussions with NatureScot and SEPA to ensure best practice for peat extraction and restoration. While the impact to bats is unlikely to be significant, it would be advisable to monitor any fatalities that may occur from collision as they are found to forage within the wind turbine areas. This information will feed into mitigation measures which can be altered accordingly, to ensure any negative impacts to foraging / commuting bats is minimal. Recommend that due to the presence of black grouse in the area, the applicant should ensure the fences are clearly marked and that a programme of monitoring fences for any potential black grouse carcasses is implemented Recommend that the applicant continues discussions with relevant organisations, to ensure that appropriate mitigation and enhancement measures are adhered to and potential impacts are minimal. 8. Ornithology: Whilst NatureScot has not objected to this issue, it is noted that they consider the proposed development may result in significant impacts on Schedule 1 bird species and a regionally important black grouse population. It is recommended that the ECU gives further consideration to this issue before determining the application. 9. Argyll and Bute Council requests that all other conditions recommended by consultees are included in any Consent. (Reference: Report by Head of Development and Economic Growth dated 6 January 2026 and supplementary report number 1 dated 20 January 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Planning, Protective Services and Licensing Committee

Legend Countryside Area Greenbelt Remote Countryside Area Settlement Area

Application Site

0 360 720 1,440 Meters

Location Plan Relative to: 24/02242/S36 O © Crown Copyright and database right 2025 All rights reserved. OS license (customer) account number AC0000849384

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
24-02242-S36Report 1.7 MB DownloadRead as text
PDF
Cruach Clenamacrie WF Supplementary Report v1Supplementary 177 KB Download
PDF
VOLTALIA UK LTD (SCOTTISH GOVERNMENT CONSULTATION): SECTION 36 CONSULTATION TO CONSTRUCT AND OPERATE 6 WIND TURBINES WITH A GROUND TO BLADE TIP HEIGHT OF 200 METRES, AND ASSOCIATED INFRASTRUCTURE INCLUDING BATTERY ENERGY STORAGE SYSTEM AND COMPOUND (BESS): CRUACH CLENAMACRIE WIND FARM: LAND AT GLENReport 757 KB Download

At this meeting

Whole meeting

Who was there

10 of 15 attended
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairChair, present
JB
Councillor Jan BrownMember, present
AF
Councillor Audrey ForrestMember, apologies
KG
Councillor Kieron GreenVice-Chair, present
AH
Councillor Amanda HampseyMember, present
DH
Councillor Daniel HampseyMember, apologies
GH
Councillor Graham HardieMember, present
FH
Councillor Fiona HowardMember, present
MI
Councillor Mark IrvineMember, apologies
AK
Councillor Andrew KainMember, present
PD
Councillor Paul Donald KennedyMember, apologies

All 15 on the meeting page

More from Argyll and Bute Planning, Protective Services and Licensing Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Beaufort wind limited: erection of 7 turbines (up to 149.9m to tip) and ancillary development and decommissioning of existing beinn ghlas wind farm: existing beinn ghlas wind farm, taynuilt (ref: 25/01240/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. PP - A... Agreed Open
15 Sep 2026 Mr tony coogan: alterations to guesthouse to facilitate lawful use of existing roof space as ancillary guest house owner's accommodation: greencourt, benvoullin road, oban (26/00434/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Mrs faulkes: proposed alterations and erection of extension: 30 the green, craobh haven (ref: 26/01009/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Decision The Committee agreed that the Scottish Government’s Marine Directorate should be notified that Argyll and Bu... Agreed Open
15 Sep 2026 Development management performance update - fq1 2026/27Decision The Committee reviewed and agreed the content of the report. (Reference: Report by Executive Director with r... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies