HEALTH AND SOCIAL CARE PARTNERSHIP 2020/21 OUTTURN AND DEBT REPAYMENT SCHEDULE

Noted Committee 1 paper

Policy and Resources Committee noted this item on Thursday 13 May 2021. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision The Policy and Resources Committee – 1. Noted the HSCP favourable outturn position which resulted in a further £1.089m of the outstanding debt being repaid early. 2. Agreed the revised schedule of debt repayment as outlined within paragraph 4.4 of the submitted report and as amended by the verbal update. (Reference: Report by Section 95 Officer dated 29 April 2021, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy and Resources Committee

Executive summary

1.1At the Council’s budget meeting on 25 February 2021 the Council approved a base allocation to the Health and Social Care Partnership (HSCP) of £62.211m for 2021/22, with a net payment of £62.011m once the debt repayment schedule requested by the HSCP, and an early repayment of £1.0m was taken into account. The schedule, including future years indicative payments, was also approved.

1.2The final outturn for the HSCP is a £1.010m underspend, which is after accounting for the original repayment and subsequent £1m early repayment in 2020-21. This amount will be used to reduce the outstanding debt to the Council, in line with the Scheme of Integration.

1.3It is recommended that the Policy and Resources Committee a) Note the HSCP favourable outturn position which results in a further £1.010m of the outstanding debt being repaid early. b) Agree the revised schedule of debt repayment as outlined within paragraph 4.4. ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE

FINANCIAL SERVICES 13 MAY 2021

HEALTH AND SOCIAL CARE PARTNERSHIP 2020/21 OUTTURN AND DEBT REPAYMENT SCHEDULE

2. INTRODUCTION

2.1This report advises of the favourable outturn position of the HSCP in financial year 2020/21 and following a request from the IJB Chief Financial Officer recommends a revised profile of the remaining outstanding debt.

Recommendations

3.1It is recommended that the Policy and Resources Committee a) Note the HSCP favourable outturn position which results in a further £1.010m of the outstanding debt being repaid early. b) Agree the revised schedule of debt repayment as outlined within paragraph 4.4.

4. DETAIL

Health and Social Care Partnership Financial Position

4.1There is currently a debt due to the Council from the HSCP of £3.848m for overspends incurred in 2018/19 and 2019/20.

4.2The HSCP have confirmed that their final 2020/21 outturn is an underspend of £1.010m. The approved Scheme of Integration outlines what should happen in the event of an underspend at the year end:

8.2.21 Subject to there being no outstanding payments due to the partner bodies, the IJB may retain any underspend to build up its own reserves and the Chief Financial Officer will maintain a reserves policy for the IJB.

4.3As there are outstanding payments due to the Council from the HSCP the underspend of £1.010m will be used to reduce the outstanding balance from £3.848m to £2.838m.

Repayment of Remaining Outstanding Debt

4.4The IJB Chief Financial Officer has requested that the repayment schedule be updated with the repayments still being made over the following 4 years but the repayments between 2022/23 to 2024/25 being reduced by the early repayment in 2020/21. The revised repayment profile is set out in the table below. Repayment Repayment Total 2018/19 2019/20 Repayment Overspend Overspend £000 £000 £000 2021/22 200 200 2022/23 900 900 2023/24 572 328 900 2024/25 838 838 Total 1,672 1,166 2,838

5. CONCLUSION

5.1The HSCP is £1.010m underspent in 2020/21 and this underspend will be used to pay down the HSCP’s debt to the Council from £3.848m to £2.838m in line with the terms of approved Scheme of Integration.

5.2It is recommended that the repayment of the remaining £2.838m is deducted from the Council’s payment to the HSCP over the four year period 2021/22 to 2024/25.

6. IMPLICATIONS

6.1Policy – In line with the Scheme of Integration 6.2 Financial – The repayment of £1.010m of the outstanding debt will increase the Council’s General Fund balance. 6.3 Legal - None 6.4 HR - None 6.5 Fairer Scotland Duty - None 6.5.1 Equalities – None 6.5.2 Socio-Economic Duty – None 6.5.3 Islands Duty - None 6.6 Risk – None. 6.7 Customer Service - None

Kirsty Flanagan Executive Director/Section 95 Officer 29 April 2021

Policy Lead for Financial Services and Major Projects: Councillor Gary Mulvaney

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HEALTH AND SOCIAL CARE PARTNERSHIP 2020/21 OUTTURN AND DEBT REPAYMENT SCHEDULEReport 211 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 18 attended
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
RC
Councillor Rory ColvilleMember, present
RC
Councillor Robin CurrieChair, present
MD
Councillor Mary-Jean DevonMember, present
BG
Councillor Bobby GoodMember, present
KG
Councillor Kieron GreenMember, present
JF
Councillor Jim FindlayMember, present
AF
Councillor Audrey ForrestMember, apologies
JL
Councillor Jim LynchMember, present
DK
Councillor David KinniburghMember, present
YM
Councillor Yvonne McNeillyMember, present

All 18 on the meeting page

On this subject at Argyll and Bute

Search all
  1. HEALTH AND SOCIAL CARE PARTNERSHIP 2020/21 OUTTURN AND DEBT REPAYMENT SCHEDULEThis decision
  2. Health and social care integration scheme - amendment of voting membershipNoted
  3. Argyll and bute health and social care partnership annual performance report 2025/26Approved
  4. Argyll and bute health and social care partnership performance report fq1 2026/27 (april to june 2026)Decided
  5. Argyll & bute health & social care partnership - performance report - fq4 2025/26 (january - march)Decided
  6. Standards commission advice note for member of health and social care integration joint boardsNoted

More from Argyll and Bute Policy and Resources Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... Agreed Open
20 Aug 2026 Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... Noted Open
20 Aug 2026 Potential impact of iran conflict - updateDecision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section ... Noted Open
20 Aug 2026 Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... Agreed Open
20 Aug 2026 Scottish languages act 2025 - areas of linguistic significanceDecision The Policy and Resources Committee – 1. noted the progress being made to ensure that the Council meets its s... Noted Open