Tarbert and Lochgilphead Regeneration Fund - Projects Update
NotedCommittee1 paper
Mid Argyll, Kintyre & the Islands Area Committee noted this item on Wednesday 2 June 2021. Below is the council's own wording, with the papers it was decided on.
Decision The Mid Argyll, Kintyre and the Islands Area Committee noted and considered the progress made with the projects as detailed within the report. (Reference: Report by Executive Director with Responsibility for Development and Economic Growth, dated 4 th May 2021, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Executive summary
1.1This report provides an update on the six projects approved to proceed to full business case as part of the Tarbert and Lochgilphead Regeneration Fund.
1.2Following the completion of the car parking works by Tarbert Harbour Authority in March 2021 all approved projects in Tarbert have now been successfully completed.
1.3The Lochgilphead Front Green project is progressing following a second procurement process and approval of the updated Full Business Case by the Executive Director with responsibility for Development and Economic Growth. A contract has been awarded for the works to Hawthorn Heights Ltd and works are expected to be completed during early 2022.
1.4Following an award of funding by The Scottish Government’s Cycling, Walking and Safer Routes Fund, HITRANS and Transport Scotland’s Spaces for People fund, managed by SUSTRANS pavement resurfacing works have been undertaken in Colchester Square and Argyll Street. The works included an upgraded surface to natural stone sets, pavements extensions on both sides of Colchester Square, new cycle parking and demarked, informal crossing points along Argyll Street.
1.5After a further period of online consultation during February 2021 on the Ardrishaig North Public Realm project, the design team are now working on securing planning permission for the proposals and procurement for the main contractor has commenced. A decision on external funding is still awaited.
1.6Discussions have been ongoing in relation to Phase 2 of the Gleaner site.
Recommendations
1.7Members of the Mid Argyll, Kintyre and the Islands Area Committee are asked to note and consider the progress made with the projects as detailed within the report. ARGYLL AND BUTE COUNCIL MID ARGYLL, KINTYRE AND THE ISLANDS AREA COMMITTEE
DEVELOPMENT AND ECONOMIC GROWTH 2 JUNE 2021
Tarbert and Lochgilphead Regeneration Fund – Projects Update
2.0INTRODUCTION
2.1This report provides an update on the six projects which Mid Argyll, Kintyre and the Islands Area Committee agreed on 6 September 2017 (ratified by Policy and Resources Committee) should form the Tarbert and Lochgilphead Regeneration Fund and proceed to full business case. The projects include:
Project Project Status Ref. T02 Barmore Road (A83)/Garvel Road junction Complete improvement T11 Tarbert Harbour facilities Complete LA10 Lochgilphead Front Green Ongoing LA11 Argyll Street Complete LA13 Ardrishaig North Public Realm Improvements Ongoing LA17 Gleaner Oil Site Phase 1 complete, phase 2 ongoing
Whilst some projects have been successfully completed, as agreed, our focus is on successfully delivering the remaining agreed projects.
3.1Members of the Mid Argyll, Kintyre and the Islands Area Committee are asked to note and consider the progress made with the projects as detailed within the report.
4.0DETAIL
Tarbert Projects
4.1Following the completion of the car parking works by Tarbert Harbour Authority in March 2021 all approved projects in Tarbert have now been completed. The car park was completed with the assistance of grant funding from the Tarbert and Lochgilphead Regeneration Fund and for every £1 of Tarbert and Lochgilphead Regeneration Funding provided a further £1.08 of additional funding was expended.
Lochgilphead Front Green (LA10)
4.2Following a two stage procurement process and approval of the updated Full Business Case by the Executive Director with responsibility for Development and Economic Growth, a contract has been awarded for the works at the Front Green to Hawthorn Heights Ltd. Hawthorn Heights have extensive experience in delivering public realm and play projects, including the Council led project at Hermitage Park in Helensburgh.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.