Mid Argyll, Kintyre & the Islands Area Committee noted this item on Wednesday 2 June 2021. Below is the council's own wording, with the papers it was decided on.
Decision The Mid Argyll, Kintyre and the Islands Area Committee considered and noted the update on Traffic Regulation Order progress. (Reference: Report by Executive Director with Responsibility for Development and Infrastructure Services dated May 2021, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Recommendations
2.1It is recommended that the Area Committee note and consider the update on TRO progress.
3.0DETAIL 3.1 The processing of Temporary TROs and Notices has become an increasing resource pressure on Roads and Infrastructure Services. The current workload specifically in relation to Temporary Traffic Regulation Orders (TTROs) and Notices has increased from 33 in 2016/17 to 117 in 2019/20 [a 354% increase]. Notices and Temporary TROs are a statutory duty and are often time constrained, this significant increase in demand has made it extremely challenging to process TROs.
3.2Figure 1 below shows the increase in demand by order type from 2016-17 to 2019-20. The demand for Temporary TROs increased suddenly between 2016/17 and 2017/18 but has held steady at that rate since. The demand for Notices, however, shows a steep trend line which suggests that demand may continue to increase year on year.
Figure 1
3.3The rise in demand for Temporary TROs and Notices is driven by a number of factors; these include the withdrawal of Police Scotland’s traffic management of events and an increase in the formalisation of road or lane closures by Public Utilities.
3.4The volume of Temporary TROs / Notices now processed by the service leave very little time to allow the progression of permanent TROs. Appendix 1 contains the current programme list of outstanding TRO’s; Members should note that the service has been unable to progress a disabled bay TRO within the last 2 years due to competing demands.
3.5The current TRO programme list contains proposals ranging from control of off- street car parks, introduction of speed limits, disabled bays and on street restrictions (including road safety issues arising from irresponsible parking). There are, at this time, 29 outstanding TROs listed in the programme.
3.6The timescale to progress a single TRO varies depending on the complexity of the proposals and the number and type of objections submitted. As a minimum timescale, it is estimated that a TRO which receives either no objections or has easily resolved objections, this in the main will take at least 6 months to progress. Appendix 1 provides a high level view of the TRO process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.