CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Planning, Protective Services and Licensing Committee, Wednesday 20 April 2022 at 10.30am

THE SCOTTISH GOVERNMENT ON BEHALF OF ENERGIEKONTOR UK LTD: ELECTRICITY ACT SECTION 36 CONSULTATION RELEVANT TO NARACHAN WIND FARM: NARACHAN HILL, LAND EAST OF TAYINLOAN (REF: 20/00212/S36)

Agreed Planning 3 papers

Planning, Protective Services and Licensing Committee agreed this item on Wednesday 20 April 2022. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision The Committee agreed that the Council should not object to this proposal, subject to the Energy Consents Unit considering the pre determination matters and conditions as detailed in Appendix A (section X) of the report. (Reference: Report by Head of Development and Economic Growth dated 11 April 2022 and supplementary report number 1 dated 14 April 2022, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Planning, Protective Services and Licensing Committee

Argyll and Bute Council Development & Economic Growth

This report is a recommended response to the Scottish Government’s Energy Consents and Deployment Unit (ECDU) Section 36 consultation regarding the proposed Narachan wind farm on land east of Tayinloan, Argyll & Bute

Reference No: 20/00212/S36 Applicant: The Scottish Government on behalf of EnergieKontor UK Ltd Proposal: Electricity Act Section 36 consultation relevant to Narachan Wind Farm Site Address: Narachan Hill, land east of Tayinloan, Argyll & Bute

(A) Section 36 application made up of the following elements:

 Construction, 35 year operation and subsequent decommissioning, of up to 11 wind turbines with a tip height of up to 180m  Associated turbine transformers  Associated turbine foundations  Crane hardstandings  On-site tracks, watercourse crossings, passing places and turning heads  4MW Battery Storage Compound  Underground cables linking the turbines to the substation  Up to three borrow pits for the extraction of stone on-site  Aviation lighting  A temporary construction compound  On-site substation  Forestry felling and replanting  Habitat Management Plan Area  Permanent Met Mast  Two Site Access points from A83 (only one to be constructed)

Associated works, but which do not form part of this application, include a connection from the on-site sub-station to the grid network. Final details of the grid connection would be subject to a separate design and consent process at a later date and as determined by the District Network Operator (DNO). It is likely that a connection point may be located at Carradale. _________________________________________________________________________ (B) RECOMMENDATION:

Officers recommend that Members agree that the Council does not object to this proposal subject to the Energy Consents Unit considering the pre-determination matters and conditions detailed in Section X of this report. ___________________________________________________________________ (C) CONSULTATIONS:

ENERGY CONSENT UNIT RESPONSES:

NatureScot (6th April 2020) – in response to the original EIAR advised the ECU that the proposal could affect internationally important natural heritage interests and they object. The objection is due to a lack of information in the Habitats Regulation Appraisal of the proposal in relation to the Kintyre Goose Roosts Special Protection Area (SPA). Advice is provided on ornithology and protected habitats and species only. No detailed landscape advice is provided as in NatureScot’s view, the landscape and visual assessment is not currently fit for purpose as it does not contain key information requested by them during the pre-application process. NatureScot objects due to a lack of information of impacts on national interests and required further information before being able to advise on regional ornithological impacts. They also require the following information prior to the determination of this proposal: provision of night time visualisation(s) from within the North Arran Wild Land Area (WLA) and elevated parts of the North Arran National Scenic Area (NSA) and further assessment visualisations and assessment points from within the WLA, NSA and wider countryside; Habitat Management Plan; Bird Protection Plan; and Protected species and habitat survey on the chosen route as well as detailed information on required track construction and upgrades.

NatureScot response to Additional Information consultation (FEI) – it is understood that the ECU and the Applicant have agreed an extension with NatureScot until June. The reason for this is that the Applicant needs to submit further Ornithological information for their consideration. It is Officer’s understanding that following receipt of this, NatureScot will provide full consultation advice to the ECU.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
20_00212_S36, 11/04/2022 Pre-Agenda Briefing of the Planning, Protective Services and Licensing CommitteeAgenda 1.7 MB Download
PDF
Narachan Supplementary Report 1Supplementary 371 KB Download
PDF
THE SCOTTISH GOVERNMENT ON BEHALF OF ENERGIEKONTOR UK LTD: ELECTRICITY ACT SECTION 36 CONSULTATION RELEVANT TO NARACHAN WIND FARM: NARACHAN HILL, LAND EAST OF TAYINLOAN (REF: 20/00212/S36)Report 639 KB DownloadRead as text

At this meeting

Whole meeting
3MINUTESOn the agenda 4CIVIC GOVERNMENT (SCOTLAND) ACT 1982: DESIGNATED LIST OF WHEELCHAIR ACCESSIBLE TAXI AND PRIVATE HIRE VEHICLESAgreed
5THE SCOTTISH GOVERNMENT ON BEHALF OF ENERGIEKONTOR UK LTD: ELECTRICITY ACT SECTION 36 CONSULTATION RELEVANT TO NARACHAN WIND FARM: NARACHAN HILL, LAND EAST OF TAYINLOAN (REF: 20/00212/S36)This decision
6MR RUSSELL CHOPPING & MRS SUSAN KERR: ERECTION OF FENCING AND DECKING; ERECTION OF TWO WOOD STORES; AND SITING OF STORAGE BOX (RETROSPECTIVE): 5 ARDENCRAIG CHALET, ARDENCRAIG ROAD, ROTHESAY, ISLE OF BUTE (REF: 21/02023/PP)Agreed 7MR RICHARD STEIN: ERECTION OF DETACHED GARDEN ROOM ANCILLARY TO DWELLINGHOUSE: EILEAN DA MHEINN, HARBOUR ISLAND, CRINAN, LOCHGILPHEAD (REF: 21/02308/PP)Agreed 8MRS CAROLINE JANE KEENAN: SITE FOR THE ERECTION OF DWELLINGHOUSE, 3 HOLIDAY CABINS AND ANCILLARY BUILDING: LAND ADJACENT TO BRAESIDE, PORTNAHAVEN, ISLE OF ISLAY (REF: 21/02393/PPP)Agreed 9MR & MRS ADAM & LISA MURPHY: ERECTION OF DWELLINGHOUSE, FORMATION OF VEHICULAR ACCESS AND INSTALLATION OF A PRIVATE WASTEWATER TREATMENT PLANT: LAND NORTH OF 1 ARDMINISH, ISLE OF GIGHA (REF: 21/02465/PP)Agreed 10AUCH ESTATE: PROPOSAL OF APPLICATION NOTICE FOR DEMOLITION OF EXISTING LODGE AND FARM BUILDINGS, ERECTION OF NEW REPLACEMENT GUEST LODGE AND NEW GUEST STEADING ACCOMMODATION, WALLED GARDEN, ANCILLARY BUILDINGS, LANDSCAPE, ACCESS (MAIN ROADNoted 14The Committee resolved in terms of Section 50(A)(4) of theOn the agenda 11UPDATE ON REQUEST FOR TREE PRESERVATION ORDERPrivate

Who was there

11 of 14 attended
GB
Councillor Gordon BlairMember, present
RC
Councillor Rory ColvilleVice-Chair, present
MD
Councillor Mary-Jean DevonMember, absent
AF
Councillor Audrey ForrestMember, apologies
GF
Councillor George FreemanMember, present
KG
Councillor Kieron GreenMember, present
GH
Councillor Graham HardieMember, apologies
DK
Councillor David KinniburghChair, present
DM
Councillor Donald MacMillan BEMMember, present
RM
Councillor Roderick McCuishMember, present
JM
Councillor Jean MoffatMember, present
AR
Councillor Alastair RedmanMember, present

All 14 on the meeting page

On this subject at Argyll and Bute

Search all
  1. THE SCOTTISH GOVERNMENT ON BEHALF OF ENERGIEKONTOR UK LTD: ELECTRICITY ACT SECTION 36 CONSULTATION RELEVANT TO NARACHAN WIND FARM: NARACHAN HILL, LAND EAST OF TAYINLOAN (REF: 20/00212/S36)This decision
  2. National Islands Plan and Scottish Government Population PoliciesNoted
  3. Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Agreed
  4. Esb asset development (uk) ltd: scottish government section 36 consultation for west torrisdale wind farm comprising of up to 9 wind turbines with a tip height of up to 149.9 metres with a predicted output of up to 6 mw per wind turbine, inAgreed
  5. Scottish government consultation response - draft national climate change plan 2026-2040Approved
  6. Voltalia uk ltd (scottish government consultation): section 36 consultation to construct and operate 6 wind turbines with a ground to blade tip height of 200 metres, and associated infrastructure including battery energy storage system andAgreed

More from Argyll and Bute Planning, Protective Services and Licensing Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Beaufort wind limited: erection of 7 turbines (up to 149.9m to tip) and ancillary development and decommissioning of existing beinn ghlas wind farm: existing beinn ghlas wind farm, taynuilt (ref: 25/01240/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. PP - A... Agreed Open
15 Sep 2026 Mr tony coogan: alterations to guesthouse to facilitate lawful use of existing roof space as ancillary guest house owner's accommodation: greencourt, benvoullin road, oban (26/00434/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Mrs faulkes: proposed alterations and erection of extension: 30 the green, craobh haven (ref: 26/01009/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Decision The Committee agreed that the Scottish Government’s Marine Directorate should be notified that Argyll and Bu... Agreed Open
15 Sep 2026 Development management performance update - fq1 2026/27Decision The Committee reviewed and agreed the content of the report. (Reference: Report by Executive Director with r... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies