THE SCOTTISH GOVERNMENT ON BEHALF OF ENERGIEKONTOR UK LTD: ELECTRICITY ACT SECTION 36 CONSULTATION RELEVANT TO NARACHAN WIND FARM: NARACHAN HILL, LAND EAST OF TAYINLOAN (REF: 20/00212/S36)
AgreedPlanning3 papers
Planning, Protective Services and Licensing Committee agreed this item on Wednesday 20 April 2022. Below is the council's own wording, with the papers it was decided on.
Decision The Committee agreed that the Council should not object to this proposal, subject to the Energy Consents Unit considering the pre determination matters and conditions as detailed in Appendix A (section X) of the report. (Reference: Report by Head of Development and Economic Growth dated 11 April 2022 and supplementary report number 1 dated 14 April 2022, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Planning, Protective Services and Licensing Committee
Argyll and Bute Council Development & Economic Growth
This report is a recommended response to the Scottish Government’s Energy Consents and Deployment Unit (ECDU) Section 36 consultation regarding the proposed Narachan wind farm on land east of Tayinloan, Argyll & Bute
Reference No: 20/00212/S36 Applicant: The Scottish Government on behalf of EnergieKontor UK Ltd Proposal: Electricity Act Section 36 consultation relevant to Narachan Wind Farm Site Address: Narachan Hill, land east of Tayinloan, Argyll & Bute
(A) Section 36 application made up of the following elements:
Construction, 35 year operation and subsequent decommissioning, of up to 11 wind turbines with a tip height of up to 180m Associated turbine transformers Associated turbine foundations Crane hardstandings On-site tracks, watercourse crossings, passing places and turning heads 4MW Battery Storage Compound Underground cables linking the turbines to the substation Up to three borrow pits for the extraction of stone on-site Aviation lighting A temporary construction compound On-site substation Forestry felling and replanting Habitat Management Plan Area Permanent Met Mast Two Site Access points from A83 (only one to be constructed)
Associated works, but which do not form part of this application, include a connection from the on-site sub-station to the grid network. Final details of the grid connection would be subject to a separate design and consent process at a later date and as determined by the District Network Operator (DNO). It is likely that a connection point may be located at Carradale. _________________________________________________________________________ (B) RECOMMENDATION:
Officers recommend that Members agree that the Council does not object to this proposal subject to the Energy Consents Unit considering the pre-determination matters and conditions detailed in Section X of this report. ___________________________________________________________________ (C) CONSULTATIONS:
ENERGY CONSENT UNIT RESPONSES:
NatureScot (6th April 2020) – in response to the original EIAR advised the ECU that the proposal could affect internationally important natural heritage interests and they object. The objection is due to a lack of information in the Habitats Regulation Appraisal of the proposal in relation to the Kintyre Goose Roosts Special Protection Area (SPA). Advice is provided on ornithology and protected habitats and species only. No detailed landscape advice is provided as in NatureScot’s view, the landscape and visual assessment is not currently fit for purpose as it does not contain key information requested by them during the pre-application process. NatureScot objects due to a lack of information of impacts on national interests and required further information before being able to advise on regional ornithological impacts. They also require the following information prior to the determination of this proposal: provision of night time visualisation(s) from within the North Arran Wild Land Area (WLA) and elevated parts of the North Arran National Scenic Area (NSA) and further assessment visualisations and assessment points from within the WLA, NSA and wider countryside; Habitat Management Plan; Bird Protection Plan; and Protected species and habitat survey on the chosen route as well as detailed information on required track construction and upgrades.
NatureScot response to Additional Information consultation (FEI) – it is understood that the ECU and the Applicant have agreed an extension with NatureScot until June. The reason for this is that the Applicant needs to submit further Ornithological information for their consideration. It is Officer’s understanding that following receipt of this, NatureScot will provide full consultation advice to the ECU.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
THE SCOTTISH GOVERNMENT ON BEHALF OF ENERGIEKONTOR UK LTD: ELECTRICITY ACT SECTION 36 CONSULTATION RELEVANT TO NARACHAN WIND FARM: NARACHAN HILL, LAND EAST OF TAYINLOAN (REF: 20/00212/S36)Report
5THE SCOTTISH GOVERNMENT ON BEHALF OF ENERGIEKONTOR UK LTD: ELECTRICITY ACT SECTION 36 CONSULTATION RELEVANT TO NARACHAN WIND FARM: NARACHAN HILL, LAND EAST OF TAYINLOAN (REF: 20/00212/S36)This decision
THE SCOTTISH GOVERNMENT ON BEHALF OF ENERGIEKONTOR UK LTD: ELECTRICITY ACT SECTION 36 CONSULTATION RELEVANT TO NARACHAN WIND FARM: NARACHAN HILL, LAND EAST OF TAYINLOAN (REF: 20/00212/S36)This decision
Follow Planning, Protective Services and Licensing Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.