Decision The Committee noted and considered: 1. the Scottish Government had recently confirmed the timescales for the next round of Learning Estate Investment Programme (LEIP) ie inviting submissions by 31 October; 2. that an Outline Business Case was being prepared for a potential submission to the LEIP process for a new Campus on mull in line with the adopted Learning Estate Strategy; 3. that pre-engagement activity had been ongoing with Mull community about the potential LEIP bid over recent weeks and there had been a number of workshops and meetings in August 2022. Further statutory consultation would take place if a bid was made and successfully progressed to the next stage; 4. the financial position and affordability of a LEIP bid as set out in attached Appendix B. The appendix is publically exempt due to the commercially sensitive nature of financial forecast information contained; and 5. that a paper outlining the Council’s approach to LEIP, including feedback from the pre-engagement with the community, would be presented to Council on 29 September. If a bid was progressed a submission would be required by 31 October 2022. (Reference: Report by Executive Director with responsibility for Commercial Services and Education dated 25 August 2022, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The Learning Estate Investment Programme (LEIP) is the Scottish Government’s flagship programme for investment in education and is now into Phase 3. It is the successor to the ‘Schools for the Future’ programme which our Council has delivered new builds or substantial refurbishments across our education estate at Oban, Kirn, Dunoon, Campbeltown, Lochgilphead etc. Our Council has not applied for previous phases of LEIP and there has been encouragement for a Scotland wide engagement with the programme. There is currently no assurance there would be a subsequent phase of LEIP or prioritised funding for education in future years of this parliament until 2026.
1.2The Scottish Government has recently clarified the timescales and application process for LEIP Phase 3 and this report aims to update Community Services Committee where our team are with the development of a potential bid for this nationally competitive fund. It also seeks to update on engagement recently taken place with our communities that will assist our bid and inform the next steps of the application process should we progress to the next stage following backing from the Scottish Government.
1.3The Council’s Learning Estate Strategy (adopted November 2021) has identified the priorities in terms of education new build are focussed on delivery of new campus opportunities on our islands of Mull and Islay based on the assessed fabric condition and learning suitability. Of these two locations, Mull is our preferred bid for LEIP funding and top priority based on a number of suitability criteria, most notability the current suitability of our current estate in Tobermory. Given that LEIP will only fund up to 50% of construction costs with remainder having to be resourced by Council or other sources it would be unaffordable to progress with 2 bids at this current time. Furthermore, given the nationally competitive nature and likelihood of oversubscription to this fund we are also looking to consolidate with a single unified bid for Mull – rather than twin tracking multiple applications.
1.4Given the financial – which will be measured in several tens of millions of pounds - and political commitment it is essential there is a clear mandate by Council to progress with a bid of this scale and significance. To this extent, a report with outcomes from the community engagement process will be presented to full Council on 29th September 2022 and will seek a direction to make a submission to LEIP, or not. ARGYLL AND BUTE COUNCIL COMMUNITY SERVICES COMMITTEE
EDUCATION COMMERCIAL SERVICES 25 AUGUST 2022
LEARNING ESTATE INVESTMENT PROGRAMME (LEIP) UPDATE POTENTIAL BID FOR NEW MULL CAMPUS
Recommendation
That the Community Services Committee note and consider:
2.1.1 The Scottish Government has recently confirmed the timescales for the next round of the Learning Estate Investment Programme (LEIP) i.e. inviting submissions by 31st October.
2.1.2 That an Outline Business Case is being prepared for a potential submission to the LEIP process for a new Campus on Mull in line with the adopted Learning Estate Strategy;
2.1.3 That pre-engagement activity has been ongoing with Mull community about the potential LEIP bid over recent weeks and there have been a number of workshops and meetings in August 2022. Further statutory consultation will take place if a bid is made and successfully progresses to the next stage;
2.1.4 The financial position and affordability of a LEIP bid is set out in attached Appendix B. This appendix is publically exempt due to the commercially sensitive nature of financial forecast information contained.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.