Resolved
Decision The Audit and Scrutiny Committee agreed to endorse the contents of the report. (Reference: Report by Chief Internal Auditor, dated 16 March 2023, submitted)
Audit and Scrutiny Committee agreed this item on Thursday 16 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Audit and Scrutiny Committee agreed to endorse the contents of the report. (Reference: Report by Chief Internal Auditor, dated 16 March 2023, submitted)
2.1To endorse the contents of the report.
3.0DETAIL
3.1The two tables below provide a numerical summary of open audit actions with a split between actions due by and due after 31 December 2022.
3.2Appendix 1 provides further detail on actions that have either been delayed and rescheduled or for which Internal Audit have received no response from the service to inform this follow up. Table 1 - Actions Due by 31 December 2022
Rescheduled Complete
Delayed &
Total Service
INTERNAL AUDIT CE – Financial Services 1 1 2 DH – Commercial Services 0 1 1 DH – Learning & Teaching 1 0 1 DH – Legal & Regulatory 1 3 4 KF – Customer Support Services 1 0 1 KF – Development & Economic Growth 0 1 1 KF – Roads & Infrastructure Services 1 6 7 H&SCP (IJB) – Adult Services (Older Adults & Community Hospitals) 0 1 1 H&SCP (IJB) – Finance & Transformation 0 1 1 H&SCP (SW) – Adult Services (Mental Health Learning Disability, 0 1 1 Addictions & Lifelong Conditions) EXTERNAL AUDIT Nil TOTAL 5 15 20
Table 2 - Actions due after 31 December 2022
Rescheduled On Course Complete
Delayed &
Total Service
INTERNAL AUDIT CE – Financial Services 0 5 1 6 H&SCP (SW) – Adult Services (Mental Health Learning 1 0 0 1 Disability, Addictions & Lifelong Conditions) DH – Commercial Services 0 4 0 4 DH – Learning & Teaching 0 2 0 2 DH – Legal & Regulatory 0 3 0 3 DH – Lifelong Learning & Support 0 0 1 1 KF – Customer Support Services 0 1 0 1 KF – Development & Economic Growth 0 3 0 3 KF – Roads & Infrastructure Services 0 0 1 1 H&SCP (IJB) – Adult Services (Older Adults & Community 0 3 0 3 Hospitals) H&SCP (IJB) – Strategic Planning & Performance 0 5 0 5 LiveArgyll 0 1 0 1 EXTERNAL AUDIT Nil TOTAL 1 27 3 31 4.0 CONCLUSION
4.1Satisfactory progress continues to be made implementing audit actions ….
5.0IMPLICATIONS
5.1Policy - None 5.2 Financial - None 5.3 Legal - None 5.4 HR - None 5.5 Fairer Scotland Duty - None 5.5.1 Equalities – None 5.5.2 Socio-Economic Duty – None 5.5.3 Islands Duty - None 5.6 Risk –None 5.7 Customer Service – None
Paul MacAskill Chief Internal Auditor 16 March 2023
For further information contact: Paul MacAskill, 01546 604108 [email protected]
APPENDICES Appendix 1 – Action Plan Points Delayed & Rescheduled or with No Response Appendix 1 - Action Plan Points Delayed & Rescheduled or with No Response
Action Plan Points Due by 31 December 2022 Finding & Priority Agreed Action Dates Comment / Status Responsible Officer
FINANCIAL SERVICES - SYSTEMS INTERFACES & RECONCILIATIONS General Ledger Reconciliations Reconciliations will be performed 31 Mar 2021 Senior Accountant is liaising Resourcelink - There is no reconciliation performed following consideration of data and 31 Dec 2021 with the systems Pensions & Payroll between the source system and the technical requirements. 30 Jun 2022 administrator for Resource Officer general ledger for ResourceLink, PECOS, 30 Sep 2022 Link and continuing to try and Concerto and Tranman and the SEEMiS 31 Oct 2022 find a solution using cognos. interface for clothing grants. 28 Feb 2023 We hope to conclude this by end of February 2023. Medium Delayed and Rescheduled
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal and External Audit Report Follow Up 2022-23Report | 289 KB | DownloadRead as text |
Follow Audit and Scrutiny Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | Internal Audit and Counter Fraud Summary of ActivitiesDecision The Audit and Scrutiny Committee reviewed and endorsed the Summary of Activities report. (Reference: Report ... | Decided | Open |
| 3 Sep 2026 | Internal and External Audit Report Follow Up 2026-27Decision The Audit and Scrutiny Committee endorsed the contents of the report. (Reference: Report by Chief Internal A... | Decided | Open |
| 3 Sep 2026 | Internal Audit Reports to Audit and Scrutiny Committee 2026/2027Decision The Audit and Scrutiny Committee reviewed and endorsed the summary report and detail within each individual ... | Decided | Open |
| 3 Sep 2026 | External Audit Progress UpdateDecision The Audit and Scrutiny Committee agreed to note the information provided. | Agreed | Open |
| 3 Sep 2026 | Verbal Update by Chair(s) of Scrutiny PanelDecision The Audit and Scrutiny Committee noted the information provided. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.