SCOTTISH HYDRO ELECTRIC TRANSMISSION PLC: ERECTION OF HIGH VOLTAGE ELECTRICITY SUBSTATION AND FORMATION OF ASSOCIATED ACCESS, LANDSCAPING, DRAINAGE AND MEANS OF ENCLOSURE: APPROXIMATELY 4KM SOUTH WEST OF INVERARAY, 300M WEST OF DOUGLAS WATE

Agreed Planning 2 papers

Planning, Protective Services and Licensing Committee agreed this item on Wednesday 24 May 2023. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. The development shall be implemented in accordance with the details specified on the application form dated 16 th December 2022; the Environmental Appraisal (November 2022), supporting information and, the approved drawings listed in the table below unless the prior written approval of the planning authority is obtained for an amendment to the approved details under Section 64 of the Town and Country Planning (Scotland) Act 1997. Plan Title. Plan Ref. No. Version Date Received Site Location Plan A01 A01 13/01/2023 Figure 1.1 An Suidhe Substation Red Line Boundary A01 A01 13/01/2023 Site Layout Plan 4534a-DR-P-0017 Rev.2 19/12/2022 Substation Compound Layout and Electrical Section Locations 4534a-DR-P-0004 Rev.3 13/01/2023 Proposed Site Access Profiles 4534a-DR-P-0021 07/12/2022 Proposed Site Profiles 4534a-DR-P-0018 Rev.1 07/12/2022 Site Access Details 4534a-DR-P-0008 Rev.1 07/12/2022 Typical Access Track Sections – Sheet 1 4534a-DR-P-0007 Rev.2 07/12/2022 Typical Access Track Sections – Sheet 2 4534a-DR-P-0012 Rev.2 07/12/2022 Typical Deer Fence and Gate 4534a-DR-P-0016 07/12/2022 2.5m High Security Palisade Fencing Details CE/34/2015 Rev.E 19/12/2022 Electrical Layout Elevations 01 4534a-DR-P-0011 Rev.1 07/12/2022 Electrical layout Elevations 02 4534a-DR_P-0013 Rev.2 07/12/2022 Generator Building Elevations 4534a-DR-P-0009 Rev.2 07/12/2022 Generator Building Floor Plan LT288 An SUIDHE_DIESEL_FLOOR Rev.1 13/01/2023 Substation Building Elevations 4534a-DR-P-0006 Rev.2 07/12/2022 Substation Building Layout 4534a-DR-P-0005 Rev.1 07/12/2022 Transformer Building Elevations 4534a-DR-P-0019 07/12/2022 Transformer Building Layout 4534a-DR-P-0020 07/12/2022 An Suidhe Septic Tank and Private Water Supply Location A01 13/01/2023 Reason: For the purpose of clarity, to ensure that the development is implemented in accordance with the approved details. 2. No construction works shall be commenced until a Finalised Construction Environmental Management Document [CEMD] has been submitted to and approved in writing by the Planning Authority, in consultation with SEPA and other consultees, as appropriate. The development shall then proceed in accordance with the approved CEMD unless otherwise agreed in writing by the Planning Authority. The CEMD shall include: a) An updated Schedule of Mitigation (SM) highlighting mitigation set out within each chapter of the Environmental Appraisal (EA), and the conditions of this consent; b) Processes to control/ action changes from the agreed SM; c) Construction Environmental Management Plans (CEMPs) for the construction phase covering: i) Habitat and species protection, including ECoW Details, surveys and species protection plans; ii) Landscape and Mitigation Restoration Plan including compensatory planting (refer to Condition 9); iii) Pollution prevention and control; iv) Dust management, including construction activity and vehicle movements; v) Construction noise and vibration vi) Temporary site lighting; vii) Watercourse crossings; viii) Site waste management ix) Surface and ground water management, including: drainage and sediment management measures from all construction areas including access tracks, mechanisms to ensure that construction will not take place during periods of high flow or high rainfall; and a programme of water quality monitoring; x) Soil Management and Peat Management Plan xi) Mapping of borrow pits and associated habitats identified for restoration; xii) Invasive Non-Native Species Management Plan xiii) Emergency Response Plans; xiv) Timetable for post construction restoration/ reinstatement of the temporary working areas and construction compound; and xv) Other relevant environmental management as may be relevant to the development d) A statement of responsibility to ‘stop the job/ activity’ if a breach or potential breach of mitigation or legislation occurs; and e) Methods of monitoring, auditing, reporting and the communication of environmental management on site and with client, Planning Authority, and other relevant parties. Reason: To ensure protection of surrounding environmental interests and general amenity. 3. No development shall commence until a Construction Traffic Management Plan (CTMP) and Phased Delivery Plan have been prepared and approved in writing by the Local Authority, in consultation with the Roads Authority, and Transport Scotland as the trunk roads Authority. The Plan shall include details of: a) Approved access routes, b) Agreed operational practises (including avoidance of convoy movements, specifying conduct in use of passing places, identification of turning areas, information of wheel cleansing facilities, signage to be installed on the A83 warning of construction traffic, signage or temporary traffic control measures to include for larger or abnormal loads, reporting of verge damage); c) The provision of an appropriate Code of Practice to drivers of construction and delivery vehicles. d) Abnormal load route surveys and finalised plan (including any accommodation measures required including the removal of street furniture, junction widening, traffic management). The development shall be implemented in accordance with the duly approved Traffic Management Plan Reason: To minimise the interference with the safety and free flow of traffic on the trunk road and to ensure that the transportation of abnormal loads will not have any detrimental effect on the trunk road network. 4. No development or ground breaking works shall commence until a programme of archaeological works in accordance with a written scheme of investigation, has been submitted to and approved in writing by the Planning Authority in consultation with the West of Scotland Archaeology Service. The scheme shall be prepared by a suitably qualified person and shall provide for the recording, recovery and reporting of items of interest or finds within the application site. Thereafter the development shall be implemented in accordance with the duly approved details with the suitably qualified person being afforded access at all reasonable times during ground ... view the full minutes text for item 5.
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Planning, Protective Services and Licensing Committee

Argyll and Bute Council Development & Economic Growth

Planning Application Report and Report of Handling as required by Schedule 2 of the Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013 relative to applications for Planning Permission or Planning Permission in Principle

Reference No: 22/02479/PP Planning Hierarchy: National Applicant: Scottish Hydro Electric Transmission Plc Proposal: Erection of high voltage electricity substation and formation of associated access, landscaping, drainage and means of enclosure Site Address: Approximately 4km South West of Inveraray, 300m West of Douglas Water and Upslope of the existing An Suidhe Substation, Inveraray, Argyll and Bute

DECISION ROUTE

☐Delegated - Sect 43 (A) of the Town and Country Planning (Scotland) Act 1997

☒Committee - Local Government Scotland Act 1973

(A) THE APPLICATION

(i) Development Requiring Express Planning Permission  Construction of substation platform of 1.3ha  Installation of Gas Insulated Switchgear (GIS) building, maximum height 22m and single storey control building annex  275/33 kV super grid transformer, rated at 120 MVA located in a ventilated building of maximum height 16m  Two gantries and electrical equipment/down-leads to connect the OHL and proposed substation  Diesel generator housed in a building  Borehole for water  Turning and parking areas  Use and upgrades to existing 1.7km long forestry track for access  Construction of new access tracks, 295m long  Erection of 2.4m high security fence of palisade construction around the substation perimeter  Erection of deer fencing around new areas of woodland planting  Landscape planting  Foul and surface water drainage including Sustainable Urban Drainage (SUDS) pond and outfall pipe.  Tree felling and compensatory planting

(ii) Other specified operations  Temporary site laydown of approximately 0.69ha  Undergrounding of the 33kV interconnector cable

Report of Handling Template for PPSL and Delegated Planning Applications – Updated 08.03.2023 (B) RECOMMENDATION:

It is recommended that Members grant planning permission subject to the conditions and reasons attached.

(C) CONSULTATIONS:

Historic Environment Scotland (23rd January 2023) - no specific comments as the proposal does not affect any heritage assets within their remit.

Scottish Environmental Protection Agency [SEPA] (31st January 2023) – holding objection and seek further information on proposed watercourse engineering works as it is not clear what is proposed and if it will be consentable under The Water Environment (Controlled Activities) (Scotland) Regulations 2011 (As Amended)

(4th May 2023) – following meetings and discussions with the Applicant, SEPA note that the applicant looks to divert the watercourse running north over the hydro pipeline and connecting it back to its natural cause which would require the creation of a culvert underneath an existing hydro pipeline and access track. It is noted that some of these works would be outwith the currently application development boundary. SEPA are satisfied that the proposed watercourse engineering works are consentable under The Water Environment (Controlled Activities) (Scotland) Regulations 2011 (As Amended), provided the following planning condition is attached to any decision: no development to commence until confirmation has been obtained that the diversion works have approval by separate planning application

Transport Scotland (27th January 2023) – no objection subject to the inclusion of planning conditions relating to: a construction traffic method statement, prior approval of the abnormal load route; and signage and temporary traffic control measures.

NatureScot – No response at time of writing.

ARGYLL & BUTE COUNCIL INTERNAL CONSULTATION RESPONSES

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
22_02479PP plan, 15/05/2023 Pre-Agenda Briefing of the Planning, Protective Services and Licensing CommitteeAgenda 373 KB Download
PDF
SCOTTISH HYDRO ELECTRIC TRANSMISSION PLC: ERECTION OF HIGH VOLTAGE ELECTRICITY SUBSTATION AND FORMATION OF ASSOCIATED ACCESS, LANDSCAPING, DRAINAGE AND MEANS OF ENCLOSURE: APPROXIMATELY 4KM SOUTH WEST OF INVERARAY, 300M WEST OF DOUGLAS WATER AND UPSLOPE OF THE EXISTING AN SUIDHE SUBSTATION, INVERARAReport 531 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 15 attended
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairMember, present
JB
Councillor Jan BrownMember, present
AF
Councillor Audrey ForrestMember, apologies
KG
Councillor Kieron GreenChair, present
AH
Councillor Amanda HampseyVice-Chair, present
DH
Councillor Daniel HampseyMember, present
GH
Councillor Graham HardieMember, present
FH
Councillor Fiona HowardMember, present
MI
Councillor Mark IrvineMember, apologies
AK
Councillor Andrew KainMember, apologies
PD
Councillor Paul Donald KennedyMember, present

All 15 on the meeting page

On this subject at Argyll and Bute

Search all
  1. SCOTTISH HYDRO ELECTRIC TRANSMISSION PLC: ERECTION OF HIGH VOLTAGE ELECTRICITY SUBSTATION AND FORMATION OF ASSOCIATED ACCESS, LANDSCAPING, DRAINAGE AND MEANS OF ENCLOSURE: APPROXIMATELY 4KM SOUTH WEST OF INVERARAY, 300M WEST OF DOUGLAS WATEThis decision
  2. SCOTTISH HYDRO ELECTRIC TRANSMISSION PLC (SSEN TRANSMISSION): PROPOSAL OF APPLICATION NOTICE FOR DEVELOPMENT OF ELECTRICITY SUBSTATION ON A NEW SITE TO REPLACE THE EXISTING ARDNADAM STATION: DUNOON ELECTRICITY SUB STATION, HIGH ROAD, SANDBANK (Ref: 26/00366/PAN)Noted
  3. Scottish hydro electric transmission plc: to construct and operate a 275 kilovolt (kv) electricity substation and associated infrastructure.Agreed
  4. Scottish hydro electric transmission plc: erection of high voltage electricity substation and formation of associated access, landscaping, drainage and means of enclosure (craig murrail) substation): achnabreck forest - land approximately 2Agreed
  5. Scottish hydro electric transmission plc: erection of high voltage electricity substation and formation of associated access, landscaping, drainage and means of enclosure (crossaig (north) substation): land adjacent to crossaig substation, skipness (ref: 23/00382/pp)Agreed
  6. The scottish government on behalf of scottish hydro electric transmission plc: construction of approximately 13.3 km of 275 kv overhead line (ohl) from between a proposed substation at creag dhubh to the existing scottish power energy netwoAgreed

More from Argyll and Bute Planning, Protective Services and Licensing Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Beaufort wind limited: erection of 7 turbines (up to 149.9m to tip) and ancillary development and decommissioning of existing beinn ghlas wind farm: existing beinn ghlas wind farm, taynuilt (ref: 25/01240/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. PP - A... Agreed Open
15 Sep 2026 Mr tony coogan: alterations to guesthouse to facilitate lawful use of existing roof space as ancillary guest house owner's accommodation: greencourt, benvoullin road, oban (26/00434/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Mrs faulkes: proposed alterations and erection of extension: 30 the green, craobh haven (ref: 26/01009/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Decision The Committee agreed that the Scottish Government’s Marine Directorate should be notified that Argyll and Bu... Agreed Open
15 Sep 2026 Development management performance update - fq1 2026/27Decision The Committee reviewed and agreed the content of the report. (Reference: Report by Executive Director with r... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies