Decision The Policy and Resources Committee – 1. noted the allocation of Crown Estate funding provided from the period 2019-2023; 2. noted the agreed allocation of the Crown Estate funding during the period 2019-2023 to the projects in Table 1 and paragraph 4.4 of the submitted report; 3. approved the amendments to the funding allocation as detailed in paragraph 4.6 of the submitted report; 4. noted the update on each of the individual projects as detailed in Table 1 of the submitted report; 5. agreed to the continuation of delegated powers, as agreed in February 2023, to the Executive Director with responsibility for Development and Economic Growth to allow any subsequent amendment to approved Crown Estate grant allocations to ensure that any risk relating to having to payback any grant is minimised; noting that this may involve swapping Crown Estate allocations with Place Based Investment Programme allocations of grants against individual projects but would not affect the projects but simply the grant source. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 14 September 2023, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1Scottish Ministers made a commitment in 2014 that they would provide 100% of the net revenue from Scottish Crown Estate marine assets out to 12 nautical miles to Local Authorities for coastal community benefit if management of the assets was devolved.
1.2Scottish Government has written each year to Councils advising of the distribution of the net revenue generated from the Scottish Crown Estate’s marine asset out to 12 nautical miles for their respective Council area. These annual revenue allocations are distributed in arrears following the finalisation of the annual accounts for the Scottish Crown Estate.
1.3The expectation is that Local Authorities would use the funding for additional expenditure that specifically benefits coastal communities, with individual authorities making decisions on funding of projects to benefit coastal communities and being transparent and accountable to their communities and others for expenditure.
1.4This report focuses on the last four tranches of payments paid to local authorities commencing in 2019/20 with the objective of ensuring that coastal communities benefit from the net revenue generated by the Scottish Crown Estate’s marine assets. The allocation for each year relates to the net revenue generated from 2 financial years previous to the financial year the payment is received.
1.5Over the last four tranches of payments to Argyll and Bute a total of £5,785,106.55 has been received. The Council is still awaiting confirmation of the allocation for this financial year (2023/24).
1.6The annual payment made to each relevant local authority is based on the distribution method agreed by the Settlement and Distribution Group (SDG). It remains Scottish Governments preference that the allocations should be used to deliver coastal community benefit. 1.7 This report will updating members on the respective individual project allocations. In addition the report will provide an update on any subsequent changes made to the allocations as well as provide an update on progress of each of the projects. All projects, with the exception of the 2019/20 projects, are listed in Table 1.
1.8The Crown Estate fund is targeted at the sustainability of coastal communities within the categories noted below and the Council has to advise how the funding is spent as part of the annual reporting requirements. Categories of expenditure are:-
Environment Community Climate Change Economic Development
1.9The funding can be used by the Council to deliver Council projects or can be provided as a grant to third sector organisations to assist in the delivery of a community project.
1.10Where the funding is being provided as a grant a contract needs to be drawn up and issued and the grant and associated drawdown managed by officers of the Council.
1.11The fund links closely to the ongoing reprioritisation focus of the Council, the Economic Growth service and Roads and Infrastructure Service, and associated Economic Strategy and Economic Recovery Plan. The fund also builds on and adds value to other investment funding including Place Based Investment Programme as well as regeneration and infrastructure initiatives taken forward by the Council.
Recommendation
It is recommended that Policy and Resources Committee:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.