CROWN ESTATES FUNDING ALLOCATIONS 2025/26

Agreed Committee 1 paper

AI summaryArgyll and Bute's Policy and Resources Committee approved £949.5k of remaining 2025/26 Crown Estate funding for nine coastal projects, with delegated authority for changes to the agreed programme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedNine priority projects for coastal communities
Money£2,358,044.07Total 2025/26 Crown Estate net allocation to council
What happens nextDelegate authority for changesExecutive Director with Leader of Council to vary project list
Who it affectsCoastal communities across Argyll and ButeTown centres, businesses, schools and visitors

What was decided

The committee agreed to allocate the remaining 2025/26 Crown Estate funding to the nine priority projects set out in Table 1, paragraph 4.2.1. Report P6, 4.2

Members noted that these projects are additional to the £800k of funding approved by the same committee on 21 August 2025, listed in Table 2. Report P6

Authority was delegated to the Executive Director with responsibility for Development and Economic Growth, in consultation with the Leader of the Council, to endorse changes to the approved programme, with no new projects expected but possible transfers between agreed ones. Report P14, P29

Why

The Scottish Government wrote to councils on 25 November 2025 confirming Argyll and Bute's 2025/26 net Crown Estate revenue allocation, which comes from a £15.98m pot distributed across 26 Scottish councils. Report 1.3, 2.2, P31

Funding is intended for additional expenditure that specifically benefits coastal communities, with councils expected to be transparent and accountable for their decisions. Report 1.2, 2.1, P17

The report follows the earlier approval of £800k by the Policy and Resources Committee in August 2025, leaving £949.5k of the 2025/26 allocation to allocate. Report 1.4, 2.3, P19

What happens next

Project leads will deliver the nine new schemes, with the Executive Director able to move money between agreed projects if circumstances change, for example if a project is no longer viable. Report P14, P29

The Transformational Projects and Regeneration Team will ensure all committed funds are compliant with grant funding conditions. Report 6.3

The money

  • £2,358,044.07 Total 2025/26 net Crown Estate revenue allocation to Argyll and Bute Report 1.3, 2.2, P31
  • £15.98m Total Crown Estate funding distributed to 26 Scottish local authority regions Report 1.3, 2.2, P31
  • £949.5k Total of nine new priority projects being approved in this report Report 1.4, 2.3, P6
  • £800k Previously approved by P&R Committee on 21 August 2025 (Table 2 projects) Report P6, P14
  • £1,407,000 Total previously agreed by Council before this report Report 1.4
  • £260k Town Centre shopfront and empty business property support across Argyll and Bute Report P23, P56
  • £300k Gallanach Road Rock Slope Protection (approved August 2025) Report P26
  • £150k Albert Pier Car Park Resurfacing match funding for Place Based Investment project Report P23, P59

Options considered

  • Chosen: Approve the allocation of remaining 2025/26 Crown Estate funding to the nine priority projects in Table 1 and delegate authority for in programme changes. Recommended by the Executive Director to use the remaining £949.5k for coastal community benefit in line with Scottish Government guidance Report P5, P6, 3.1, P14

Implications

  • Financial: Grant funding is provided for all projects identified, and projects will be monitored to ensure funds can be spent and meet Scottish Government criteria. Report 6.2, 6.6
  • Legal: The Transformational Projects and Regeneration Team will ensure all funds committed are compliant with grant funding conditions. Report 6.3
  • Climate: Funds can support activities which promote the drive towards net zero, and align with priorities around tackling the twin crises of climate and biodiversity. Report 2.1, 6.7, P17
  • Equalities: The KSS project could enhance opportunities for all ages and abilities to take part in marine leisure and training activities. Report 6.9
  • Other: KSS has introduced more than 120 Campbeltown Grammar School pupils to sailing, with 56 gaining internationally recognised sail and powerboat qualifications, in a school where more than 10% of the 360 pupils are Registered Young Carers. Report 6.12
  • Other: The fund has the potential to align with and add value to other funding programmes such as the Islands Programme, PBIP and RCGF. Report 6.11
  • Staffing: Resourced from existing staff. Report 6.4

Who and where

  • Coastal communities across Argyll and Bute, including town centres, businesses and property owners Report 1.2, 2.1, P17
  • Project leads within Council services including Development and Economic Growth and Roads and Infrastructure Services Report P23
  • Third sector organisations that may receive grants to help deliver community projects Report P18
  • Scottish Association for Marine Science and the SAMS STEM Hub at the European Marine Science Park, Dunstaffnage Report P23, P60
  • Campbeltown Grammar School pupils, through the KSS sailing project Report 6.12
  • Event and festival applicants in the Council's SEF Round 8 programme Report P23, P64

Timeline

  • 21 August 2025: Policy and Resources Committee approved an initial £800k of Crown Estate funding (Table 2 projects) Report P6, P14
  • 25 November 2025: Scottish Government wrote to local authorities confirming the 2025/26 net Crown Estate revenue allocations Report 1.3, 2.2, P31
  • 8 January 2026: Report by the Executive Director with responsibility for Development and Economic Growth dated Report P50, P47
  • 19 February 2026: Decision taken by the Policy and Resources Committee Report P7, P8

Plain English for the jargon

  • Crown Estate: Scottish Crown Estate marine assets out to 12 nautical miles, with net revenue distributed to local authorities for coastal community benefit
  • CARS: Conservation Area Regeneration Scheme, in this case for Helensburgh
  • SAMS: Scottish Association for Marine Science, leading the STEM Hub project at the European Marine Science Park, Dunstaffnage
  • SEF: Strategic Events and Festivals, the Council's funding programme for events
  • P&R Committee: Policy and Resources Committee of Argyll and Bute Council
  • RGD: Rural Growth Deal, the Council's programme that the SAMS STEM Hub is part of
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17

Resolved

Decision The Policy and Resources Committee – 1. agreed to the allocation of the remaining Crown Estate funding for 2025/26 to the priority projects outlined in Table 1, paragraph 4.2.1 of the report; 2. noted that these projects were additional to the £800k of funding approved by Policy and Resources Committee on 21 August 2025 and detailed in Table 2 of this report; and 3. agreed to delegate authority to the Council’s Executive Director with responsibility for Development and Economic Growth in consultation with the Leader of the Council to endorse changes to the approved programme of projects. It was not considered that new projects would be introduced however, there may be the requirement to move funding between agreed projects. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 8 January 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy and Resources Committee

Executive summary

1.1The Scottish Government has written each year to Councils advising of the distribution of the net revenue generated from the Scottish Crown Estate’s marine asset out to 12 nautical miles for their respective council area. These annual revenue allocations are distributed in arrears following the finalisation of the annual accounts for the Scottish Crown Estate.

1.2The expectation is that Local Authorities will use the funding for additional expenditure that specifically benefits coastal communities, with individual authorities making decisions on funding of projects to benefit coastal communities and being transparent and accountable to their communities and others for expenditure.

1.3The Scottish Government wrote to Local Authorities on 25th November 2025 confirming that Argyll and Bute Council’s net Crown Estate revenue allocation for the 2025/26 financial year is £2,358,044.07. This is from a total funding allocation of £15.98m distributed to 26 local authority regions.

1.4The Council have previously agreed to allocate £1,407,000 and this report brings forward proposals for a further £949.5k of funding from the remaining 2025/26 Crown Estates funding allocation. A full breakdown of proposed and approved spend is provided in Appendix 1 of this report.

Recommendations

It is recommended that Policy and Resources Committee:

a) Agree to the allocation of the remaining Crown Estate funding for 2025/26 to the priority projects outlined in Table 1, paragraph 4.2.1. b) Note that these projects are additional to the £800k of funding approved by Policy and Resources Committee on 21st August 2025 and detailed in Table 2 of this report. c) Members are asked to delegate authority to the Council’s Executive Director with responsibility for Development and Infrastructure Services in consultation with the Leader of the Council to endorse changes to the approved programme of projects. It is not considered that new projects will be introduced however, there may be the requirement to move funding between agreed projects. ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE

DEVELOPMENT AND ECONOMIC GROWTH 19 FEBRUARY 2026

CROWN ESTATES FUNDING ALLOCATIONS 2025/26

2.0INTRODUCTION

2.1Scottish Ministers made a commitment in 2014 that they would provide 100% of the net revenue from Scottish Crown Estate marine assets out to 12 nautical miles to Local Authorities for coastal community benefit if management of the assets was devolved. It is for each local authority to determine how best to spend their allocation to best benefit coastal communities and Councils are advised to follow their own processes to ensure that monies spent deliver value for money. The Scottish Government have also advised that Councils may wish to consider how Crown Estates funding can be used to contribute towards realising Scotland’s Blue Economy Vision and other priorities around tackling the twin crises of climate and biodiversity.

2.2The Scottish Government wrote to Local Authorities on the 25th November 2025 confirming that Argyll and Bute Council’s net Crown Estate revenue allocation for the 2025/26 financial year is £2,358,044.07. This is from a total funding allocation of £15.98m distributed to 26 local authority regions.

2.3This report brings forward proposals for a further £949.5k of funding from the remaining 2025/26 Crown Estates funding allocation and follows the report approved by Policy and Resources (P&R) Committee on 21st August 2025 where an initial £800k of investment was approved. A full breakdown of proposed and approved spend is provided in Appendix 1 of this report.

3.1It is recommended that Policy and Resources Committee:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CROWN ESTATES FUNDING ALLOCATIONS 2025/26Report 224 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 19 attended
KM
Katie McKenzieSecretary, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairMember, present
MC
Councillor Math Campbell-SturgessMember, present
AF
Councillor Audrey ForrestMember, apologies
KG
Councillor Kieron GreenMember, present
AH
Councillor Amanda HampseyMember, present
MI
Councillor Mark IrvineMember, absent
RK
Councillor Reeni Kennedy-BoyleMember, present
JL
Councillor Jim LynchChair, present

All 19 on the meeting page

On this subject at Argyll and Bute

Search all
  1. CROWN ESTATES FUNDING ALLOCATIONS 2025/26This decision
  2. Crown estates funding allocations 2025/26 and redirection of previously allocated project fundingAgreed
  3. Crown estates funding allocation 2025/26Approved
  4. Redirection of crown estates fundingAgreed
  5. Other funding streams: crown estates, islands infrastructure fund and place based investment fundApproved

More from Argyll and Bute Policy and Resources Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... Agreed Open
20 Aug 2026 Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... Noted Open
20 Aug 2026 Potential impact of iran conflict - updateDecision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section ... Noted Open
20 Aug 2026 Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... Agreed Open
20 Aug 2026 Scottish languages act 2025 - areas of linguistic significanceDecision The Policy and Resources Committee – 1. noted the progress being made to ensure that the Council meets its s... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies