Decision The Policy and Resources Committee agreed to redirect the Crown Estates Funding previously awarded for the provision of solar powered CCTV at the island airports of Coll and Colonsay, towards the provision of a backup fire appliance vehicle, to meet Civil Aviation Regulations in the provision of fire cover at island licensed airports. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated July 2024, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The main purpose of this report is to gain approval to redirect Crown Estates Funding (CEF), previously approved for solar powered CCTV on the island airports of Coll and Colonsay, towards the purchase of a new fire appliance vehicle. This vehicle will replace a current vehicle considered to be no longer fit for purpose and be used as back up to the island airports when routine/or unplanned maintenance to the island fire appliances takes place. 1.2 Anticipated estimate cost for the new vehicle is approximately £60k, with an option to lease for £1,500 pcm.
Recommendations
It is recommended that Policy and Resources Committee agree to redirect the Crown Estates Funding (CEF), previously awarded for the provision of solar powered CCTV at the island airports of Coll and Colonsay, towards the provision of a backup fire appliance vehicle, to meet Civil Aviation Regulations in the provision of fire cover at island licensed airports. ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
DEVELOPMENT AND ECONOMIC GROWTH 15 AUGUST 2024
REDIRECTION OF CROWN ESTATES FUNDING
2.0INTRODUCTION
2.1Crown Estates Funding – Redirection of Funding Previous agreed awards to the Airports, from the Crown Estates Funding (CEF), for new infrastructure are as follows: - i). £100k – This was for fire training simulator rigs on each of the islands of Coll and Colonsay. A contract has been awarded to Minerva, at a cost of £53,700. The rest of the original allocation was to implement solar powered CCTV on each of the islands. A tender was put out for this, however had to be abandoned due to security concerns.
ii). £120k – Latest allocation from CEF, for connection by Scottish and Southern Electricity Networks (SSEN), to connect Colonsay airport to the power grid. This is in hand, with Property Services pursuing SSEN on delivery. (Colonsay airport is currently powered by a generator).
3.1It is recommended that Policy and Resources Committee agree to redirect the Crown Estates Funding (CEF), previously awarded for the provision of solar powered CCTV at the island airports of Coll and Colonsay, towards the provision of a backup fire appliance vehicle, to meet Civil Aviation Regulations in the provision of fire cover at island licensed airports.
4.0DETAIL
4.1Abandonment of solar powered CCTV tender
4.1.1 The Council abandoned the tender for the above, due to current conflict with some of the products currently marketed, and national guidance in their use at sensitive sites. 4.2 Fire Appliance Vehicles
4.2.1 Argyll and Bute Council currently have two fire appliance vehicles located at Oban airport. The Oban vehicles are equipped to provide a higher level of fire cover due to the equipment and media it carries, allowing Oban to handle larger aircraft due to longer runway (1200m), which the island vehicles cannot. (Island runways of Coll and Colonsay airports are 500m in length, by comparison).
4.2.2 The second vehicle at Oban serves purely as a spare vehicle in case the main vehicle requires maintenance or develops a fault. The second vehicle at Oban, also enables the airport to conduct fire training during operational hours.
4.2.3 There is also one fire vehicle on each of the islands, to provide fire cover at Coll and Colonsay airport. These vehicles are required to meet Civil Aviation Authority regulations regarding provision of fire cover, at each of the Council’s licensed airports.
4.2.4 Argyll and Bute Council did have a fifth fire appliance vehicle, which was an original fire appliance vehicle that was retained from the islands, when the Council replaced the vehicles on each island with newer models. The requirement for this fifth appliance is twofold: -
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.