OCTOBER 2023 WEATHER EVENT - UPDATE

Noted Committee 3 papers

Policy and Resources Committee noted this item on Thursday 15 August 2024. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

Decision The Policy and Resources Committee – 1. acknowledged the sheer scale and severity of the impact on local infrastructure during the storms of October 2023 and recognised the complexity and speed of the response delivered by the Council at pace to restore vital routes and reinstate access to cut-off communities; 2. noted the updates on works undertaken, completed and ongoing; 3. noted the revised forecast overspend of £3.853m that was currently unfunded; 4. agreed that the roads reconstruction schemes should continue and the overspend be funded as follows: £m Utilise some of the unallocated capital funding for street lighting and cable and column replacements 0.100 Use Priorities Investment Fund 0.944 Use Crown Estate Funding * 0.780 Borrowing for additional expenditure and use £50k in the loans fund for street lighting improvements towards the cost of borrowing** 2.029 Total 3.853 *It being noted that the Crown Estate Funding for 2024-25 had not been confirmed as yet and therefore requested the Section 95 Officer to advise Members by the end of the calendar year if funding had not been confirmed by that time or if funding confirmed was insufficient (further noting that £0.500m had already been confirmed as part of the 2024-25 budget). **It being noted that much of the overspend was revenue in nature and that the Council could not borrow for revenue expenditure. Further noting that the funding created from the additional borrowing would be substituted towards capital programme expenditure that was originally being funded by earmarked reserves and those earmarked reserves used for the weather related revenue expenditure. The cost to borrow was estimated to be £130k and £50k could be used from the loans fund revenue set aside for street lighting, leaving a net cost pressure of £80k that should be built into future years budget estimates. 5. recognised that local authorities require additional support to cope with increasingly challenging and unforeseen impacts of severe weather and climate change, especially for Argyll and Bute whose rural and island communities absolutely depend upon reliable lifeline routes and infrastructure, and therefore agreed to lobby for both the funding that was needed now, and effective forward/longer term planning which addresses the need to maintain and safeguard infrastructure resilience as a key contributor to growing, thriving local and national economies. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated 5 August 2024, submitted; and Motion By Councillor Jim Lynch and seconded by Councillor Gary Mulvaney, tabled)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy and Resources Committee, 11 pages

ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE

ROAD AND INFRASTRUCTURE 15 AUGUST 2024 SERVICES

OCTOBER 2023 WEATHER EVENT – UPDATE

1.0INTRODUCTION 1.1 This is a follow up to the report presented to Council on 25 April 2024 in respect of the October 2023 weather event. A number of projects have become increasingly more complex as the full extent of the damage, underlying ground conditions and a number of other factors have emerged. This report provides a detailed update on the various flood sites, provides information relating to the estimated overspends within the various projects and also proposes a range of measures for Members to consider which could be used to cover the estimated overspends.

2.0RECOMMENDATIONS 2.1 It is recommended that the Policy and Resources Committee:- a. Note the updates on the works undertaken and completed and those that are ongoing. b. Notes the revised forecast overspend of £3.853m that is currently unfunded. c. Approves that options 1, 2 and 3 as detailed in the table at paragraph 3.10 are used to fund the overspend and defer consideration of the remainder of the overspend once the Crown Estate Funding and Place Based Investment funding is confirmed for 2024-25.

3.0DETAIL 3.1 Following a period of unprecedented wet weather where there was a level of rainfall that left ground conditions very wet and in many cases saturated, over a months’ worth of rain fell over a 36 hour period starting Friday 6 October 2023 and running into Saturday 7 October 2023. This was the wettest 2-day period on record for Scotland since 1891 (MET Office report). Argyll and Bute was the worst affected area as shown in the chart below: 3.2 The works carried out following the rain event were extensive with dozens of locations requiring attention from simple cleansing of a small drain to significant landslides and bridge replacements.

3.3A significant amount of work has been undertaken and completed thus far. Some examples include:

• Various bridges – Tree and debris clearance to minimise flood risk at Bridgend Bridge, Upper Stronafian Bridge and Victoria Bridge (Cowal) and Glenmallon Bridge and Lindowan Burn Bridge (Helensburgh & Lomond). Confined space inspections and clearance was also completed to reduce the flood risk at structures in Helensburgh.

• B828 Glenmore Bridge (Cowal) – Repairs to damaged parapets and training walls caused landslide. Works undertaken by internal Structures Maintenance Team

• B839 Lochgoilhead Bridge (Cowal) – Repairs to the scoured and exposed bridge abutments and central pier foundations, reinstatement of erosion protection along the riverbank and riverbed. Working with Ross MacArthur Contractors to ensure bridge remained open to public and local community was not shut off, especially given the closure of the nearby B828 road due to landslips.

• B828 Glenmore Road (Cowal) – Rock anchor repairs to rebuild eroded and missing road edges and verges, damaged road culverts and road restrain systems caused by landslip and rockfall. Working with Geo-Rope to completion, the road was reopened following separate remedial works by Forestry and Land Scotland to remove further risk of rockfall to users.

• Ri Cruin Bridge – bridge abutment repair, scour protection works and invert pitching repairs carried out in conjunction with DA MacDonald and the Council’s Bridge Squad team.

• A815 Landslip clearance to reopen the road in conjunction with the reopening of the A83 as a vital route to and from Cowal. This site is immediately adjacent to the “Dunoon Road End Straights” section of the A83 beside the Rest and Be Thankful and ongoing monitoring of this site continues.

3.4The following table summarises locations where works are still outstanding. The most significant area of work relates to the A816, Kintraw, Ardfern landslide and further information on this is also provided within Appendix A. Further information relating to the financial estimates is included within the table at paragraph 3.6.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
OCTOBER 2023 WEATHER EVENT: UPDATEAppendix 2 pages Download
PDF
OCTOBER 2023 WEATHER EVENT: UPDATEReport 11 pages DownloadRead as text
PDF
P_R 150824 Item 18 Weather Update MotionReport 1 pages Download

At this meeting

Whole meeting

On this subject at Argyll and Bute

Search all
  1. OCTOBER 2023 WEATHER EVENT - UPDATEThis decision
  2. October 2023 weather event updateNoted
  3. October 2023 weather event - november 2024 updateNoted
  4. October 2023 weather event - updateNoted
  5. October 2023 weather event - updateNoted

More from Argyll and Bute Policy and Resources Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... Agreed Open
20 Aug 2026 Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... Noted Open
20 Aug 2026 Potential impact of iran conflict - updateDecision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section ... Noted Open
20 Aug 2026 Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... Agreed Open
20 Aug 2026 Scottish languages act 2025 - areas of linguistic significanceDecision The Policy and Resources Committee – 1. noted the progress being made to ensure that the Council meets its s... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies