Decision The Policy and Resources Committee – 1. noted that the total estimated essential development costs to inform Treasury Five compliant Full Business Cases for all projects amounted to £3.183m and these costs required to be incurred in advance of Central Government endorsement at risk to the Council and lead delivery partners; 2. agreed that the Council sets aside a fund from the Priorities Investment Fund to the value of £0.700m that can pay for the development costs for Council projects on the basis that all will be paid back by the end of Year 10; 3. agreed that any cash flow funding requests for projects led by external partners would be brought to the Policy and Resources Committee for approval as and when a request for funding was made and considered on a case by case basis; and 4. delegated to the Internal Programme Board (Chief Executive and Executive Directors) to approve pre-development funding requests relating to Council led projects up to a threshold of £250k per project from the new Fund. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 20 November 2024, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Policy and Resources Committee, 12 pages
ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
DEVELOPMENT AND ECONOMIC 5th DECEMBER 2024 GROWTH
RURAL GROWTH DEAL – PROJECT DEVELOPMENT COSTS
1.0EXECUTIVE SUMMARY 1.1 This report provides an update on the Rural Growth Deal (RGD) and specifically costs associated with Business Case and Project Development. The RGD will deliver £50m of investment from the Scottish and UK Governments for projects that are a driver for inclusive and transformational economic growth across the region. The Council and key delivery partners will also provide a minimum of £20m of match funding throughout the 10-year Deal programme. 1.2 The RGD Programme Management Office (PMO) continue to work with the UK and Scottish Governments to confirm the signing of the Full Deal Agreement, which represents the next key milestone for the Rural Growth Deal. This was postponed in June 2024 following the announcement of the General Election. 1.3 A number of RGD projects now have approved Outline Business Cases and further project development work is necessary to inform the Full Business Cases which will enable drawdown of funding from Central Government. This includes detailed design, procurement, site investigation works and statutory consents such as planning. 1.4 To date, costs associated with business case and project development works have largely been funded from the Council’s Inward Investment Fund. Match funding has also been secured from a number of key partners such as Highlands and Islands Enterprise and Scottish Enterprise. The Policy and Resources Committee have previously approved the release of 5 tranches of funding totalling £750k from the Inward Investment Fund (IIF). The RGD Internal Programme Board have delegated authority to authorise spend from the IIF to support RGD project development work. At the time of writing this report, total approved spend on RGD business case and project development work stands at £572,658. 1.5 Where possible, the RGD PMO will seek to recoup project costs from RGD capital funding allocations however, it will not be possible to submit any claims for funding until Full Business Cases for projects are endorsed by Central Government. As such, any costs incurred in advance are at risk to the Council and strategic partners. 1.6 It is currently estimated that there could be a cost pressure in the region of £3.183m over the lifetime of the Rural Growth Deal, which can be associated with project development costs. The majority of these costs will be reclaimed through RGD capital funding, once Full Business Cases are endorsed by Government. It is also anticipated that an estimated further £220k of funding will be required to be spent on Business Cases. This is not reclaimable from RGD capital funds and will be met by the Internal Investment Fund and through partner match funding. RECOMMENDATIONS:
The Policy and Resources Committee are asked to: a) Note that the total estimated essential development costs to inform Treasury Five compliant Full Business Cases for all projects amount to £3.183m and these costs require to be incurred in advance of Central Government endorsement at risk to the Council and lead delivery partners. b) Agree that the Council sets aside a fund from the Priorities Investment Fund to the value of £0.700m that can pay for the development costs for Council projects on the basis that all will be paid back by the end of Year 10. c) Agree that any cash flow funding requests for projects led by external partners will be brought to P&R for approval as and when a request for funding is made and considered on a case by case basis. d) Delegate to the Internal Programme Board (Chief Executive and Executive Directors) to approve pre-development funding requests relating to Council led projects up to a threshold of £250k per project from the new Fund. ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
DEVELOPMENT AND ECONOMIC 5th December 2024 GROWTH
RURAL GROWTH DEAL – PROJECT DEVELOPMENT COSTS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.