Decision The Policy and Resources Committee – 1. agreed that the Council increase the amount set aside from the Priorities Investment Fund from £0.700m to £0.850m to cash flow the development costs for the Council, noting that the cash flow support would be fully paid back by the end of Year 10; and 2. delegated to the Internal Programme Board (Chief Executive and Executive Directors), in consultation with the Leader and Depute Leaders to approve pre-development funding requests relating to Council led projects up to a maximum threshold of 15% of each project, subject to there being sufficient cash flow available, noting that this was an increase to the £0.250m threshold agreed in December 2024. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 22 July 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
DEVELOPMENT AND ECONOMIC 21ST AUGUST 2025 GROWTH
RURAL GROWTH DEAL – PROJECT DEVELOPMENT COSTS UPDATE
1.0EXECUTIVE SUMMARY 1.1 The Rural Growth Deal, signed on 10 March 2025, will deliver £50m of investment from the Scottish and UK Governments for projects that are a driver for inclusive and transformational economic growth across the region. The Council and key delivery partners will also provide a minimum of £20m of match funding throughout the 10-year Deal programme. 1.2 This report provides an update on the Rural Growth Deal (RGD) and specifically costs associated with project development and follows on from the report presented to the Policy and Resources Committee on 5 December 2024. 1.3 Following on from the approvals at the Policy and Resources Committee on 5 December 2024, the RGD Programme Management Office (PMO) continue to review project timescales and development costs and have identified that the current threshold of delegated authority to the Internal Programme Board is likely to be insufficient for some projects and risks slowing progress with the programme. The overall value of maximum cash flow requirement has also been updated. 1.4 The total estimated development costs for all projects (as shown in Table 2) are now estimated to be £2.831m – this is reduced from the estimated figure of £3.183m reported in December 2024. 1.5 As agreed at Policy and Resources Committee on 5 December 2024, the Council would set aside a fund from the Priorities Investment Fund to the value of £0.700m that can pay for the development costs for Council projects on the basis that all will be paid back by the end of Year 10. This cash flow support requirement has now increased to £0.850m (see Table 5, Year 5). The maximum cash flow exposure is based on the assumption that the Full Business Cases are approved and the development costs become claimable. Members are asked to note that there remains a risk of abortive development costs if projects do not progress beyond Full Business Case. 1.6 As part of the review of project development costs, it has now been identified that there are likely to be instances where the agreed delegated authority threshold of £250k will be insufficient to meet pre-construction project development costs. Where project development costs exceed £250k, there is currently a requirement for approval to be sought from the Policy and Resources Committee. This creates risk of delay to projects. It is therefore considered prudent to ask the Policy and Resources Committee to consider increasing the current level of delegated authority to the Internal Programme Board up to a maximum threshold of 15% of each project.
1.7The monitoring of cash flow spend/income against the funds allocated from the Priority Investment Fund will require to be regularly reported by officers from the Rural Growth Deal PMO and Financial Services to the Internal Programme Board initially and when required to the Policy and Resources Committee.
RECOMMENDATIONS The Policy and Resources Committee are asked to:- a) Agree that the Council increases the amount set aside from the Priorities Investment Fund from £0.700m to £0.850m to cash flow the development costs for the Council. This cash flow support will be fully paid back by the end of Year 10. b) Delegate to the Internal Programme Board (Chief Executive and Executive Directors), in consultation with the Leader and Depute Leaders to approve pre-development funding requests relating to Council led projects up to a maximum threshold of 15% of each project, subject to there being sufficient cash flow available. (This is an increase to the £0.250m threshold agreed in December 2024.) ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
DEVELOPMENT AND ECONOMIC 21ST AUGUST 2025 GROWTH
RURAL GROWTH DEAL – PROJECT DEVELOPMENT COSTS UPDATE
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.