Environment, Development and Infrastructure Committee agreed this item on Thursday 11 September 2025. Below is the council's own wording, with the papers it was decided on.
Decision The Environment, Development and Infrastructure Committee: 1. agreed that the existing budget allocation of £1.1m be used to progress the next phase of detailed business case development required to provide a recommended option with a further and more highly developed budget estimate and outline delivery programme; and 2. noted the difference in the current cost estimate and that originally produced and reported to Members in February 2024 and the reasons for this set out in the body of the report. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated September 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee, 9 pages
Executive summary
1.1This report provides an update on progress towards a permanent repair of the A816 at Ardfern which was damaged during the severe weather event in October 2023.
RECOMMENDATIONS It is recommended that Members of the Environment, Development and Infrastructure Committee:- a) Agree that the existing budget allocation of £1.1m be used to progress the next phase of detailed business case development required to provide a recommended option with a further and more highly developed budget estimate and outline delivery programme. b) Note the difference in the current cost estimate and that originally produced and reported to Members in February 2024 and the reasons for this set out in the body of the report. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE ROADS AND INFRASTRUCTURE 11 SEPTEMBER 2025
A816 ARDFERN PERMANENT REPAIR SOLUTION UPDATE
2.0INTRODUCTION
2.1This report provides an update on progress towards a permanent repair of the A816 at Ardfern which was damaged during the severe weather event in October 2023. 2.2 This report sets out the findings of an options assessment commissioned by the Council and undertaken by specialist consultants. The options assessment provides a number of potential options for a re-constructed road which have been further reviewed by Council officers to create a shortlist of preferred options that it is now proposed are subjected to further more detailed review in order to arrive at a single option which can be recommended to be taken forward.
Recommendations
3.1It is recommended that Members of the Environment, Development and Infrastructure Committee:-
a) Agree that the existing budget allocation of £1.1m be used to progress the next phase of detailed business case development required to provide a recommended option with a further and more highly developed budget estimate and outline delivery programme. b) Note the difference in the current cost estimate and that originally produced and reported to Members in February 2024 and the reasons for this set out in the body of the report.
4.0DETAIL
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.