Decision The Policy and Resources Committee – 1. noted the early progress of the Business Grant Scheme; 2. noted the implementation of a new data dashboard incorporated into Area Scorecards to ensure quarterly updates are provided on empty property rates by administration area; 3. agreed that future updates on the Empty Business Property Grant Scheme would be reported as part of the 6 monthly Transformational Projects and Regeneration Team reports to the Environment, Development and Infrastructure Committee; and 4. noted that the Empty Business Grant Scheme would continue to be administered in line with the approved governance procedures. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 13 August 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The purpose of this paper is to update the Policy and Resources Committee on the implementation of the Empty Business Property Grant Scheme.
1.2On 19 June 2025, the Environmental, Development and Infrastructure Committee approved the approach and governance of the business grant scheme for up to £786,000 in the financial year 2025/26.
1.3To date, twelve grant offers have been made for a cumulative value of £203,429.19. The council’s Empty Business Property Officer is currently engaged with a further eighteen applications and a pipeline of enquiries.
1.4Grant applications are accepted on a rolling basis; however, it is projected that live applications could contain grant requests for around £355,000, with ongoing enquires likely to advance this figure further.
1.5To help provide a baseline and ongoing monitoring, a new dashboard has been added to Area Scorecards to report on Empty Business Property rates. This will help explore the impact of policy changes, the grant scheme and other factors.
1.6It is recommended that the Policy and Resources Committee:-
i. Notes the early progress of the business grant scheme. ii. Notes the implementation of a new data dashboard incorporated into Area Scorecards. This will ensure quarterly updates are provided on empty property rates by administration area. iii. Agrees that future updates on the Empty Business Property Grant scheme will be reported as part of the 6 monthly Transformational Projects and Regeneration Team reports to the Environment, Development and Infrastructure Committee. iv. Notes that the Empty Business Grant Scheme will continue to be administered in line with the approved governance procedures. ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE DEVELOPMENT AND ECONOMIC GROWTH 9 OCTOBER 2025
EMPTY BUSINESS PROPERTY – UPDATE ON BUSINESS GRANT SCHEME
2.0INTRODUCTION
2.1The purpose of this paper is to update the Policy and Resources Committee on the early progress of the Empty Property Business Grant Scheme.
2.2This paper seeks to outline how the grant scheme is helping to incentivise and support owners and tenants of empty business properties to return them to productive use.
2.3The following table, provides a summary of the current empty property rate per administration area, the number of grant approvals and a summary of live applications that are at different stages in the development or assessment process. Table 1: Empty Business Property Grant Scheme Sumamry Area Empty No. of Grant Value No. of Live Projected Grant Property Completed Grant Applications Value Rate Approvals B&C 4.8% 5 £92,068.10 7 £163,000.00 H&L 2.5% 2 £28,150.00 1 £10,000.00 MAKI 4.1% 5 £83,211.09 7 £125,000.00 OLI 2.2% 0 £0 3 £57,000.00 A&B 3.4% 12 £203,429.19 18 £355,000
2.4In addition to the live applications detailed in Table 1, the Empty Business Property Officer is supporting a number of owners and tenants across Argyll and Bute to address barriers and develop projects to a stage where they are ready to be considered for grant funding applications. 2.5 It is considered that there will be considerable on-going demand via the Empty Business Property Grant Scheme to support property owners and tenants repurpose, refurbish and invest in vacant commercial properties which will in turn support wider place based regeneration and economic growth initiatives being delivered by the Council and key partners. 2.6 To help baseline, monitor progress and measure the impact of the policy changes and grant scheme, a new data dashboard for Empty Business Properties has been added to the quarterly Area Scorecards. This will support the council to advance data-driven decision-making, and help to establish a suite of place based analytics that will support future investment priorities.
Recommendations
It is recommended that the Policy and Resources Committee:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.