Argyll and Bute Council
Policy and Resources Committee, Thursday 9 October 2025 at 10.30am

LORN ARC TAX INCREMENTAL FINANCE (TIF) UPDATE

Noted Committee 1 paper

Policy and Resources Committee noted this item on Thursday 9 October 2025. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

Decision The Policy and Resources Committee noted – 1. the significant ten-year extension to the TIF project; and 2. the substantive progress that was being made both at Dunbeg Corridor and Oban Airport Business Park. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated August 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy and Resources Committee, 6 pages

Executive summary

1.1This report provides an update on the Lorn Arc Programme and the current live Lorn Arc projects at Dunbeg and Oban Airport Business Park.

1.2The report outlines the agreed changes to the Lorn Arc Tax Incremental Finance (TIF) agreement which will extend its potential operation by ten years and significantly reduce risk associated with the projects. The Lorn Arc TIF initiative is currently holding a positive balance of £2.4m that is ring fenced for this project.

1.3LINK RSL has submitted four planning applications for Phase 4 development at the Dunbeg Corridor, which has already delivered 375 affordable homes and significant infrastructure upgrades. Phase 4 will include circa 430 residential units including social rent, mid-market rent, student housing, shared equity, private sale and plots. In addition, a new trunk road roundabout will be constructed on the A85, a new residential link road, and a commercial area which may include an hotel, drive through restaurants, and small supermarket. The Council is currently processing these applications in tandem.

1.4Substantial progress is being made at Oban Airport Business Park and a detailed report on this project will be presented to Council in November. It is estimated by council officers that the majority of the Oban Airport Business Park works will be completed in 2026.

Recommendation

1.6It is recommended that Council consider the content of the report and note:

• The significant ten-year extension to the TIF project; and • The substantive progress that is being made both at Dunbeg Corridor and Oban Airport Business Park. ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE DEVELOPMENT AND ECONOMIC 9th OCTOBER 2025 GROWTH

LORN ARC TAX INCREMENTAL FINANCE (TIF) UPDATE

2.0INTRODUCTION

2.1This report provides an update on the Lorn Arc (TIF) Programme and the current live Lorn Arc projects at Dunbeg Corridor and Oban Airport Business Park.

Recommendations

3.1It is recommended that Council consider the content of the report and note:

• The significant ten-year extension to the TIF project; and • The substantive progress that is being made both at Dunbeg Corridor and Oban Airport Business Park.

4.0DETAIL

Lorn Arc TIF Programme

4.1In January 2025, following extensive negotiations facilitated by the Scottish Futures Trust and council officers, the Scottish Government agreed a formal amendment to the TIF agreement. The effect of this was to lengthen the agreement period from the current end stop of 2040, to 2050. This is a significant extension as It gives a further ten years for the Council to continue retaining the additional NDR revenue that has been created since the creation of the TIF scheme. The effect of this is to reduce significantly the risk involved in repaying the investment, and to potentially allow a greater investment to be made in infrastructure at both the Dunbeg Corridor and Oban Airport Business Park. 4.2 The following table provides the general financial highlights for the TIF programme and the projects at Dunbeg Corridor and Oban Airport. It shows that the TIF scheme is currently retaining a £2.4m surplus, although this is fully committed in future years for works identified in this report. Finance Highlights Total Current TIF Reserve (opening balance for 2025/26) £2.402m TIF revenue (NDR retained) 2024-25 £0.815m TIF spend – 2025-to date £0.280m

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LORN ARC TAX INCREMENTAL FINANCE (TIF) UPDATEReport 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Argyll and Bute

Search all
  1. LORN ARC TAX INCREMENTAL FINANCE (TIF) UPDATEThis decision
  2. Lorn arc tif programme dunbeg corridor updateNoted
  3. Lorn arc tax incremental finance programme - oban airport business park - updateNoted
  4. Lorn arc tax incremental finance programme - update reportNoted
  5. Lorn arc programme updateNoted
  6. Lorn arc tax incremental finance programme - update reportNoted

More from Argyll and Bute Policy and Resources Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... Agreed Open
20 Aug 2026 Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... Noted Open
20 Aug 2026 Potential impact of iran conflict - updateDecision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section ... Noted Open
20 Aug 2026 Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... Agreed Open
20 Aug 2026 Scottish languages act 2025 - areas of linguistic significanceDecision The Policy and Resources Committee – 1. noted the progress being made to ensure that the Council meets its s... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies