AI summaryArgyll and Bute Council's Audit and Scrutiny Committee noted Performance Excellence Project progress and the work to finish Phase Two. [D] Completion of outstanding work packages is anticipated by end of March 2026, with the updated Performance and Improvement Framework to follow. [4.7] [4.8]
Written from the decision and the officer reportPDF Pro
OutcomeNotedOutstanding work packages remain to be completed [4.8]
MoneyNot stated
What happens nextComplete Phase Two work packages [4.8]Anticipated completion by end of March 2026 [4.8]
Who it affectsCouncil performance framework [4.7]Updated PIF will follow completion [4.7]
What was decided
The Audit and Scrutiny Committee noted progress on the Performance Excellence Project and the planned work to conclude Phase Two.
The noted progress included delivery of the Corporate Improvement Plan and self assessment templates for teams and themes. Report 4.3, P13, P16
The public performance reporting workstream was complete in respect of the December 2024 statutory direction. Updated website performance pages were in the process of going live. Report 4.6
Why
The project was set up to simplify the Council's performance management and make it compliant and proportionate. Report 4.1
The approach seeks to reduce manual input by collecting data at source wherever possible. The updated framework is intended to align with the Connect for Success Change Programme and make better use of available technology. Report 4.2, 4.4
Public performance reporting must be proportionate, timely, meaningful and open to scrutiny under the Accounts Commission's SPI directive. Report 4.6, 6.3
What happens next
Complete the outstanding work packages, with completion anticipated by end of March 2026 and sooner in some cases. Report 4.8
Put reporting dashboards in place across the remaining council service areas by 31 March 2026. Report 4.4
Continue strategy rationalisation, assessment of possible Planner use, LGBF work with managers and development of the revised annual report approach. Finalising the annual report approach depends on agreement of Corporate Outcome Indicators. Incorporate lessons learned into the Corporate Programme Office and present the updated PIF when the other work packages conclude. Report P13, P17, P18, P19, 4.7
Options considered
Chosen: Roll out dashboard reporting across council service areas. The approach follows a successful pilot and is intended to reduce manual input by collecting data at source wherever possible. Report 4.4
Rejected: Keep the lessons learned activity in this project. It was removed from this project because parallel Corporate Programme Office work will incorporate it. Report P19
Implications
Other: The project will deliver an updated Performance and Improvement Framework for the Council. Delivery of Best Value through it is intended to give customers value for money. Report 6.1, 6.5
Financial: No financial implications arise directly from this report. Report 6.2
Legal: The Council has a statutory duty to ensure Best Value and comply with the Accounts Commission's SPI directive. Report 6.3
Staffing: No human resources implications arise directly from this report. Report 6.4
Risk: Failure to deliver the project would leave the Council without performance and improvement arrangements that meet the needs of a transforming Council. Report 6.6
Climate: No climate change implications arise directly from this report. Report 6.7
Equalities: No direct Fairer Scotland Duty or protected equalities implications arise. Required Integrated Impact Assessments and Integrated Characteristics Impact Assessments will be completed within the project. Report 6.8, 6.9
Other: No direct consumer duty, island communities or children’s rights implications arise. Required Integrated Impact Assessments and Integrated Wellbeing Impact Assessments will be completed within the project. Report 6.10, 6.11, 6.12
Who and where
Argyll and Bute Council Report 6.1, 6.3, 6.6
Council service areas Report 4.4
Council customers Report 6.5
Members of the public Report 4.6
Senior leaders and Third Tier Managers Report P13
Council teams and managers Report P16, P17, P18
Timeline
May 2020: The Performance Excellence Project commenced. Report 4.1
financial year 2024, 2025: Existing priorities continued while the new Corporate Plan took effect. Report 4.3
November 2024: The Senior Leadership Forum shared the proposed Planner approach and issued a feedback survey. Report P13
December 2024 statutory direction, covering up to and including 2027, 2028: The public performance reporting workstream was completed. Report 4.6
28 October 2025: The officer report was dated. Report P39
16 DECEMBER 2025: The Audit and Scrutiny Committee considered the performance reporting update. Report P4
end of March 2026: Outstanding project work packages are anticipated to be complete, with some completed sooner. Report 4.8
31 March 2026: Reporting dashboards are planned across all council service areas. Report 4.4
Plain English for the jargon
Performance and Improvement Framework (PIF): The Council's framework for performance and improvement activities, which the project will update. [P1] [4.7]
Performance Excellence Project: The project reviewing and simplifying the Council's performance management approach. [4.1]
Phase Two: The project stage focused on an updated PIF, further simplification and use of technology. [4.2]
SPI: The Accounts Commission's Statutory Performance Direction, covering public performance reporting and scrutiny. [4.6] [6.3]
LGBF: The Local Government Benchmarking Framework, whose use within the PIF is under review. [P18]
MS Planner: The planning tool piloted for business activities outside core services. [P13]
Best Value: A duty the Council must ensure, alongside compliance with the Accounts Commission's SPI directive. [6.3]
Benchmarking: The use of benchmarking information to support continuous improvement, reviewed for use within the PIF. [4.1] [P18]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
Decision The Audit and Scrutiny Committee considered and noted the progress of the Performance Excellence Project and activities to conclude Phase Two. (Reference: Report by Executive Director with responsibility for Customer Support Services, dated 28 October 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
The aim of this paper is to update the Audit and Scrutiny Committee with the progress on the review of the Council’s Performance and Improvement Framework (PIF) that is being undertaken as part of the Performance Excellence Project. The main overall deliverable from this project will be an updated PIF which includes a simplified, compliant and proportionate approach to performance and improvement activities.
The report highlights work completed to date on activities in Phase Two of the project and plans for the outstanding work packages.
It is recommended members note and consider the progress of the Performance Excellence Project and activities to conclude Phase Two. ARGYLL AND BUTE COUNCIL AUDIT AND SCRUTINY COMMITTEE
CUSTOMER SUPPORT SERVICES 16 DECEMBER 2025
PERFORMANCE REPORTING UPDATE
2.0INTRODUCTION
2.1The performance excellence project was commenced in May 2020 with the aim of reviewing the council’s approach to performance and improvement activities and simplifying them where possible. The report sets out the progress of Phase Two of the project and the planned activities to bring the remainder to a conclusion and deliver the updated Performance and Improvement Framework (PIF).
Recommendations
3.1It is recommended members note and consider the progress of the Performance Excellence Project and activities to conclude Phase Two.
4.0DETAIL
4.1The initial performance excellence project commenced in May 2020 with a mandate to review the council’s performance management approach and implement a simplified, proportionate and compliant approach which meets the needs of a transforming council. Following a Best Value audit, the project included within its scope actions to improve performance reporting to provide a balanced picture of long term trends in performance against targets, and to use benchmarking information to drive continuous improvement.
4.2The project then progressed to phase two with the overall objective to present an updated Performance and Improvement Framework which is in alignment with the Connect for Success Change Programme, further simplifies our approach to performance and improvement, while maximising the use of the technology available to us. Specifically, the project included five work streams which are largely based on the existing elements of the Performance and Improvement Framework. Progress on activities contained within each workstream is detailed below.
4.3Workstream One: Planning This workstream focused on the design and development of plans that support delivery of the council’s strategic outcomes. As the Administration changed during the project, a new Corporate plan was developed which had not been in the original scope of the project. The pre-existing priorities were continued for the financial year 2024 – 2025 as the new Corporate Plan took effect within this period. This workstream focused on the following activities:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.