Resolved
Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided in the report. (Reference: Report by Area Manager, Transport Scotland, submitted)
AI summaryMid Argyll area committee notes Transport Scotland update on the A83, including £7.04m spent this year and ongoing landslide and storm management.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided in the report. (Reference: Report by Area Manager, Transport Scotland, submitted)
Transport Scotland Update
The Rest and Be Thankful experienced a number of events through last year with the most notable being;
Hillside Movements – We had 2 significant hillside movements affecting the A83t during early September at the Rest and Be Thankful itself as well as at Butterbridge which were dealt with successfully,
Boulder removal – We successfully removed a sizable boulder, around 20 tonnes in weight, from the hillside at the Rest during mid-October with images available of the BBC website The ground investigation works relating to the design of the debris flow shelter were completed during September 2025.
The A83t was also impacted by several weather events, increasing the risk of landslides and as per our Landslide Management Plan, that required the closure of the A83t and use of the Old Military Road.
All of the above incidents resulted with the following number of closures/use of OMR and the long diversion route;
Although, we continue to manage the hillside as per the Landslide Management Plan, this will continue through the forthcoming years to ensure that access to Argyle & Bute is maintained.
A number of storms hit the peninsula during the last 12 months, such as Storm Eowyn very early in 2025, Storm Floris in August, Strom Amy during early October & Storm Bram more recently, all of which affected the A83t. These storms resulted with fallen trees as well as areas of flooding on the trunk road which in turn affected the travelling public. All incidents being dealt with safely and effectively by BEAR operatives with a view to have the A83 opened as soon as practicable. Although, we continue some storm clearance works in isolated areas.
Most recently, BEAR, A&BC, TS and other agencies all worked in collaboration, after the unfortunate building fire on Lochnell Street, Lochgilphead to finding a workable solution to have the A83 road open as soon as possible and resulting with minimal disruption.
Financial Information;
As regards to the A83t, between Tarbet & Campbeltown, currently during this financial year & works to date, there has been a financial investment in the region of £7.04 million was spent on Road Maintenance. This includes £4.48 million on road surfacing schemes, £227,500 on road safety improvements, £118,400 on drainage improvements, £122,500 on bridge repairs and strengthening works with the remainder on various improvement schemes, landscaping and storm clear up works.
We anticipate that the remainder of this financial year a further £1.7 million will be spent on various road maintenance works. This is in contract to the 2024/25 investment figures of £6.99 million.
Noteworthy works completed this financial include;
• Landslip remedial works north of Furnace
• Vehicle Restraint System (Barrier) replacement at Clachan
• Road safety improvements at the approach to Kilmory Roundabout and bend treatments (PRIME) between Minard and Lochgilphead
• Road surfacing at Port Ann, Adrishaig, North of Tayinloan & Barfad Brae
We still have a number of schemes we aim to commence this financial year (i.e. before the end of March 2026) and these include the signalised pedestrian crossing facilities in Campbeltown, a couple of road surfacing schemes at Arrochar and road restraint works at Kinglas. Moving into next year, we have a number of schemes already planned & programmed incl. 17 road re-surfacing schemes, 9 bridge & drainage improvement works as well as road safety improvements and works on the adjacent hillsides to ensure the resilience of the A83 trunk road. The commencement of these schemes will be advised to stakeholders as per our usual notification process.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
TRANSPORT SCOTLAND UPDATEReport | 123 KB | DownloadRead as text |
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... | Noted | Open |
| 2 Sep 2026 | Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... | Agreed | Open |
| 2 Sep 2026 | Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... | Noted | Open |
| 2 Sep 2026 | Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... | Noted | Open |
| 2 Sep 2026 | Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.