Argyll and Bute Council
Mid Argyll, Kintyre & the Islands Area Committee, Wednesday 4 March 2026 at 10.30am

TRANSPORT SCOTLAND UPDATE

Noted Committee 1 paper

AI summaryMid Argyll area committee notes Transport Scotland update on the A83, including £7.04m spent this year and ongoing landslide and storm management.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo further action decided at the meeting
Money£7.04 million spent this yearPlus about £1.7m expected before March 2026
What happens nextMore surfacing and bridge works ahead
Who it affectsNot stated

What was decided

The committee noted the information in the Transport Scotland report on the A83 and surrounding area. Report P1

Why

Transport Scotland set out how it has been managing hillside instability, storms and routine maintenance on the A83 trunk road between Tarbet and Campbeltown. Report P2, P3, P4, P5, P7, P8

It also reported on the financial investment made in the road so far this financial year and the works still planned. Report P10, P11, P12, P13

What happens next

Transport Scotland will continue to manage the hillside under the Landslide Management Plan and keep access to Argyll and Bute open. Report P7

Schemes planned to start before the end of March 2026 include a signalised pedestrian crossing in Campbeltown, surfacing at Arrochar and road restraint works at Kinglas, with 17 resurfacing and 9 bridge or drainage schemes set for the following year. Report P18

The money

  • £7.04 million Spent on A83 road maintenance between Tarbet and Campbeltown this financial year to date Report P11
  • £4.48 million Spent on road surfacing schemes this financial year Report P11
  • £227,500 Spent on road safety improvements this financial year Report P11
  • £118,400 Spent on drainage improvements this financial year Report P11
  • £122,500 Spent on bridge repairs and strengthening works this financial year Report P11
  • £1.7 million Anticipated further spend on road maintenance for the rest of this financial year Report P12
  • £6.99 million Total A83 road maintenance investment figure for 2024/25, given for comparison Report P12

Implications

  • Financial: Spending this financial year is already slightly above the £6.99 million spent in 2024/25, with a further £1.7 million still expected. Report P11, P12
  • Risk: The A83 at the Rest and Be Thankful remains subject to hillside movements and storm damage, with closures and diversions via the Old Military Road still likely in coming years. Report P2, P3, P4, P5, P6, P7, P8
  • Other: Ground investigation works to inform the design of a debris flow shelter at the Rest and Be Thankful were completed in September 2025. Report P4

Who and where

  • Road users on the A83 trunk road between Tarbet and Campbeltown, including in Mid Argyll, Kintyre and the Islands Report P7, P8, P11
  • Residents and businesses near Lochnell Street, Lochgilphead, after the recent building fire Report P9
  • BEAR Scotland operatives and Transport Scotland staff managing the route Report P8, P9

Timeline

  • August 2025: Storm Floris hit the peninsula and affected the A83 Report P8
  • Early September 2025: Two significant hillside movements on the A83 at the Rest and Be Thankful and at Butterbridge Report P3
  • September 2025: Ground investigation works for the debris flow shelter design completed Report P4
  • Mid-October 2025: A boulder weighing around 20 tonnes was removed from the hillside at the Rest and Be Thankful Report P4
  • Early 2025: Storm Eowyn hit the peninsula and affected the A83 Report P8
  • Early October 2025: Storm Amy hit the peninsula and affected the A83 Report P8
  • Most recently: Storm Bram hit the peninsula and Storm-led clearance works continue in isolated areas Report P8
  • Most recently: BEAR, the council, Transport Scotland and other agencies worked together after a building fire on Lochnell Street, Lochgilphead, to reopen the A83 Report P9
  • Before the end of March 2026: Schemes due to start include a signalised pedestrian crossing in Campbeltown, surfacing at Arrochar and road restraint works at Kinglas Report P18

Plain English for the jargon

  • A83t: Trunk road section of the A83 between Tarbet and Campbeltown, managed by Transport Scotland
  • OMR: Old Military Road, used as a diversion when the A83 at the Rest and Be Thankful is closed
  • BEAR: BEAR Scotland, the operating company that maintains the trunk road on behalf of Transport Scotland
  • TS: Transport Scotland
  • A&BC: Argyll and Bute Council
  • PRIME: Road safety bend treatment scheme referenced between Minard and Lochgilphead
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided in the report. (Reference: Report by Area Manager, Transport Scotland, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Mid Argyll, Kintyre & the Islands Area Committee

Transport Scotland Update

The Rest and Be Thankful experienced a number of events through last year with the most notable being;

Hillside Movements – We had 2 significant hillside movements affecting the A83t during early September at the Rest and Be Thankful itself as well as at Butterbridge which were dealt with successfully,

Boulder removal – We successfully removed a sizable boulder, around 20 tonnes in weight, from the hillside at the Rest during mid-October with images available of the BBC website The ground investigation works relating to the design of the debris flow shelter were completed during September 2025.

The A83t was also impacted by several weather events, increasing the risk of landslides and as per our Landslide Management Plan, that required the closure of the A83t and use of the Old Military Road.

All of the above incidents resulted with the following number of closures/use of OMR and the long diversion route;

Although, we continue to manage the hillside as per the Landslide Management Plan, this will continue through the forthcoming years to ensure that access to Argyle & Bute is maintained.

A number of storms hit the peninsula during the last 12 months, such as Storm Eowyn very early in 2025, Storm Floris in August, Strom Amy during early October & Storm Bram more recently, all of which affected the A83t. These storms resulted with fallen trees as well as areas of flooding on the trunk road which in turn affected the travelling public. All incidents being dealt with safely and effectively by BEAR operatives with a view to have the A83 opened as soon as practicable. Although, we continue some storm clearance works in isolated areas.

Most recently, BEAR, A&BC, TS and other agencies all worked in collaboration, after the unfortunate building fire on Lochnell Street, Lochgilphead to finding a workable solution to have the A83 road open as soon as possible and resulting with minimal disruption.

Financial Information;

As regards to the A83t, between Tarbet & Campbeltown, currently during this financial year & works to date, there has been a financial investment in the region of £7.04 million was spent on Road Maintenance. This includes £4.48 million on road surfacing schemes, £227,500 on road safety improvements, £118,400 on drainage improvements, £122,500 on bridge repairs and strengthening works with the remainder on various improvement schemes, landscaping and storm clear up works.

We anticipate that the remainder of this financial year a further £1.7 million will be spent on various road maintenance works. This is in contract to the 2024/25 investment figures of £6.99 million.

Noteworthy works completed this financial include;

• Landslip remedial works north of Furnace

• Vehicle Restraint System (Barrier) replacement at Clachan

• Road safety improvements at the approach to Kilmory Roundabout and bend treatments (PRIME) between Minard and Lochgilphead

• Road surfacing at Port Ann, Adrishaig, North of Tayinloan & Barfad Brae

We still have a number of schemes we aim to commence this financial year (i.e. before the end of March 2026) and these include the signalised pedestrian crossing facilities in Campbeltown, a couple of road surfacing schemes at Arrochar and road restraint works at Kinglas. Moving into next year, we have a number of schemes already planned & programmed incl. 17 road re-surfacing schemes, 9 bridge & drainage improvement works as well as road safety improvements and works on the adjacent hillsides to ensure the resilience of the A83 trunk road. The commencement of these schemes will be advised to stakeholders as per our usual notification process.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
TRANSPORT SCOTLAND UPDATEReport 123 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
JA
Councillor John ArmourChair, present
JB
Councillor Jan BrownMember, present
IC
Iona CampbellSecretary, expected
GC
Councillor Garret CornerMember, present
AH
Councillor Anne HornMember, present
JK
Councillor Jennifer KeanMember, present
TM
Councillor Tommy MacPhersonMember, present
DM
Councillor Dougie McFadzeanVice-Chair, present
KM
Katie McKenzieSecretary, expected
JS
Julieann SmallSecretary, expected
DP
Councillor Dougie PhilandMember, present
AR
Councillor Alastair RedmanMember, present

On this subject at Argyll and Bute

Search all
  1. TRANSPORT SCOTLAND UPDATEThis decision
  2. Transport Scotland UpdateNoted
  3. Transport ScotlandNoted
  4. Transport ScotlandNoted
  5. Transport ScotlandNoted
  6. Transport scotlandNoted

More from Argyll and Bute Mid Argyll, Kintyre & the Islands Area Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... Noted Open
2 Sep 2026 Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... Agreed Open
2 Sep 2026 Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... Noted Open
2 Sep 2026 Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... Noted Open
2 Sep 2026 Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies