STATUTORY HARBOUR BOARD ACCOUNTS

Noted Committee 1 paper

AI summaryArgyll and Bute Harbour Board noted 2024/25 annual statements for its 8 statutory harbour authorities; the accounts show a combined surplus of £88,201 across all piers and harbours.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFor the 8 Statutory Harbour Authorities, year 2024/25
Money£88,201 combined surplusAcross all piers and harbours for year ended 31 March 2025
What happens nextConsolidation work aheadSingle Statutory Harbour Authority Order to follow Oban HRO
Who it affects8 statutory harbours and all piersAcross the Argyll and Bute Council area

What was decided

The Harbour Board noted the annual statements for each of the Council's 8 Statutory Harbour Authorities for 2024/25. Report 2.1

The 8 statutory harbours recorded a combined surplus of £595,116 for the year ended 31 March 2025. Report 3.6

All other piers and harbours recorded a combined deficit of £506,916, giving an overall surplus of £88,201 across all piers and harbours. Report 3.7

Why

Section 42 of the Harbours Act 1964 requires every statutory harbour undertaker to prepare an annual statement of accounts relating to harbour and associated activities. Report 3.1

The Council previously included statutory harbour income and expenditure within the overall Council Accounts and is now, as best practice, providing a separate annual statement for each of the 8 authorities. Report 3.2

Resources are pooled across the 8 harbours because marine infrastructure costs are significant, especially at remote or island locations, and large works need to be funded without short-term spikes. Report 3.5

What happens next

The Council intends to pursue consolidation of its main ports and harbours under a single Statutory Harbour Authority Order, once the ongoing Oban HRO process is completed. Report 3.9, 3.10

Further work will assess whether harbour asset information can be more clearly set out in a balance sheet format in future. Report 3.3

Where the cumulative total moves into surplus, it will be ring-fenced at the end of the financial year for future spending on piers and harbours. Report 3.8

The money

  • £595,116 Combined surplus for the 8 statutory harbour authorities, year ended 31 March 2025 Report 3.6
  • £506,916 Combined deficit for all other piers and harbours, year ended 31 March 2025 Report 3.7
  • £88,201 Overall surplus across all piers and harbours, year ended 31 March 2025 Report 3.7
  • (1.142) 2020-21 surplus/(deficit) in £m for all piers and harbours Report P11
  • (0.295) 2021-22 surplus/(deficit) in £m Report P11
  • 0.318 2022-23 surplus/(deficit) in £m Report P11
  • 0.384 2023-24 surplus/(deficit) in £m Report P11
  • 0.088 2024-25 surplus/(deficit) in £m Report P11

Implications

  • Financial: Pooling resources across the 8 harbours allows large or expensive works to be funded through fees, charges and borrowing, without short-term spikes at any one location. Report 3.5
  • Risk: The Council must maintain marine infrastructure across its entire area regardless of any individual location's ability to raise income.
  • Legal: Annual statement preparation is a statutory duty under Section 42 of the Harbours Act 1964. Report 3.1
  • Other: The Council intends to pursue a single Statutory Harbour Authority Order covering its main ports and harbours, after the Oban HRO process is completed. Report 3.9, 3.10
  • Other: Further work will examine whether harbour asset information can be presented in a clearer balance sheet format in future. Report 3.3
  • Other: Policy implication: income and expenditure is now reported for each Statutory Harbour Authority rather than only within overall Council Accounts. Report 5.1, 3.2

Who and where

  • The 8 Statutory Harbour Authorities: Bruichladdich, Carradale, Campbeltown, Craignure, Dunoon, Oban, Port Askaig, Rothesay Report P32, 3.2
  • All other council piers and harbours across Argyll and Bute Report 3.7
  • Users of marine infrastructure across the Argyll and Bute Council footprint, including remote and island locations
  • Argyll and Bute Council as harbour authority and pooled fund manager Report 3.5

Timeline

  • 31 March 2025: Year end for the 2024/25 financial statements Report 3.6
  • 29 January 2026: Council approved the audited accounts Report 3.6
  • 10 March 2026: Report by Executive Director/Section 95 Officer dated Report P29
  • 19 March 2026: Argyll and Bute Harbour Board meeting, agenda item 6

Plain English for the jargon

  • Statutory Harbour Authority: A harbour authority with statutory duties under the Harbours Act 1964, required to prepare annual statements of accounts under Section 42.
  • HRO (Harbour Revision Order): A statutory instrument that can change a harbour authority's powers or boundaries; the Oban HRO process is currently ongoing.
  • Section 95 Officer: The local authority officer with statutory responsibility for the proper administration of the council's financial affairs (Scottish term).
  • Pooling of funds: Combining the income and expenditure of the 8 harbours so costly works can be funded without short-term spikes in any single location.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

Decision The Argyll and Bute Harbour Board noted the annual statements for each of the Council’s Statutory Harbour Authorities for financial year 2024/25. (Reference: Report by Executive Director/Section 95 Officer, dated 10 March 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Argyll and Bute Harbour Board

Recommendations

2.1It is recommended that the Argyll and Bute Harbour Board consider and note the annual statements for each of the Council’s Statutory Harbour Authorities for financial year 2024/25.

3. DETAIL

3.1Section 42 of the Harbours Act 1964 at paragraph (1) states the following: “It shall be the duty of every statutory harbour undertaker to prepare an annual statement of accounts relating to the harbour activities and to any associated activities carried out by him”.

3.2The Council has previously included the statutory harbour income and expenditure within the overall Council Accounts, and now, developing on best practice, an annual statement of income and expenditure for each of the 8 Statutory Harbour Authorities will be provided to the Harbour Board upon completion of the audit of the Council Accounts.

3.3Harbour assets are set out in the Council’s Accounts which contain information in relation to assets equivalent to a balance sheet. Further work will be undertaken to assess whether and how information may be more clearly set out in a balance sheet format in future.

Pooling of Funds 3.4 It should be noted that the Council is the harbour authority across 8 Harbours and has a duty to maintain its marine infrastructure throughout the Argyll and Bute Council footprint irrespective of the individual location’s ability to raise income. The cost of maintaining marine infrastructure is significant, especially so at remote or island locations.

3.5Large scale or expensive works need to be paid for often within short timescales with available funds and borrowing, which is paid back through fees and charges. To allow this to be done without short term spikes and to better suit budget planning, it is sensible to pool the resources and the expenses of the marine portfolio together.

3.6The Council approved the Council’s Audited Accounts on 29 January 2026. Appendix 1 provides an annual statement for each of the 8 Statutory Harbour Authorities for the year ended 31 March 2025. There is an overall surplus of £595,116 when added together.

3.7The total income and expenditure for all other piers and harbours totals a deficit of £506,916. This together with the surplus outlined in paragraph 3.6 results in an overall surplus for all piers and harbours for the year ended 31 March 2025 of £88,201.

3.8Looking back at the accounts over the last 5 years, there is an overall deficit and therefore the pooled surplus generated in 2024-25 will be paying back previous years cumulative deficits. Where the cumulative total moves into a surplus, this will be ring-fenced at the end of the financial year for future years spending on piers and harbours.

Year Surplus/(Deficit) £m 2020-21 (1.142) 2021-22 (0.295) 2022-23 0.318 2023-24 0.384 2024-25 0.088 Total (last 5 years) (0.647)

Consolidated HRO

3.9It has been the reported intention of Argyll and Bute Council to consolidate its main ports and harbours under one Statutory Harbour Authority Order. CMAL and Cornwall Council are two examples of a Statutory Harbour Authority with multiple ports and harbours consolidating some or all their harbour areas under one single Statutory Harbour Authority order. The single legislation means that among other important aspects, the Authority can then account across the entire undertaking as one entity.

3.10The benefits are similar to the pooling of resources in that an Authority can better cover planned and unexpected works that are invariably expensive without that burden being borne by a single location. Argyll and Bute Council intend to pursue this on completion of the ongoing Oban HRO process.

4. CONCLUSION

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
STATUTORY HARBOUR BOARD ACCOUNTSReport 247 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 11 attended
JS
Julieann SmallSecretary, expected
KM
Katie McKenzieSecretary, expected
JA
Councillor John ArmourVice-Chair, present
GB
Councillor Gordon BlairMember, present
MC
Councillor Maurice CorryMember, present
AK
Councillor Andrew KainMember, present
LM
Councillor Liz McCabeMember, absent
DM
Councillor Dougie McFadzeanMember, present
RM
Councillor Ross MorelandChair, present
AV
Councillor Andrew VennardMember, present
HM
Hazel MacInnesSecretary, expected

On this subject at Argyll and Bute

Search all
  1. STATUTORY HARBOUR BOARD ACCOUNTSThis decision
  2. Statutory harbour board accountsNoted

More from Argyll and Bute Argyll and Bute Harbour Board

All decisions
MeetingDecisionOutcome
9 Oct 2026 Piers and harbours marine asset management plan - works updateDecision The Argyll and Bute Harbour Board noted the updates on capital works currently being progressed within the M... Noted Open
9 Oct 2026 Piers and harbours - performance reportingDecision The Argyll and Bute Harbour Board – 1. agreed the proposed approach and structure to annual performance repo... Agreed Open
9 Oct 2026 Carradale harbourDecision The Argyll and Bute Harbour Board noted the content of the report. (Reference: Report by Executive Director ... Noted Open
9 Oct 2026 Piers and harbours marine asset management plan fees and charges 2027 / 2028Decision The Argyll and Bute Harbour Board – 1. noted that officers were of the view that a review is required to con... Noted Open
9 Oct 2026 Argyll and bute harbour board workplanDecision The Argyll and Bute Harbour Board noted the content of the workplan. (Reference: Argyll and Bute Harbour Boa... Noted Open