A83 TARBERT TO WHITEHOUSE ACTIVE TRAVEL PROJECT PROGRESS REPORT

Decided Committee 3 papers

AI summaryMid Argyll area committee approves next design stages for the A83 Tarbert to Whitehouse active travel route, subject to securing external Scottish Government funding.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCommittee welcomed work, agreed to Stages 3 and 4
MoneyNo council funding committedAll work to date funded externally via ATIF
What happens nextOfficers to develop design furtherSubject to securing more external funding
Who it affectsTarbert, Kennacraig and Whitehouse residentsPlus visitors and ferry passengers

What was decided

Members welcomed the design progress made so far on active travel improvements between Tarbert and Whitehouse. Report P16, 1.6

Officers were instructed to carry out the Developed Design and Technical Design stages, but only if further external funding is secured. Report P17, 4.10, 4.11

Members must receive a further paper on the completed design before any construction can begin. Report P18

Why

An active travel route between Tarbert and Whitehouse would let residents and visitors travel more sustainably and help lower the council's carbon footprint. Report 5.1

The project has so far been funded by the Scottish Government's Active Travel Infrastructure Fund, and no council money has been spent or committed. Report 1.2, P21, 4.2

Public consultation in 2024 and 2025 showed majority support for a full route between Tarbert and Whitehouse. Report 4.5, 4.6

What happens next

Officers will seek further external funding to take the project through Developed Design and Technical Design stages. Report P17, 5.2

Further community and stakeholder consultation will take place during the Developed Design stage. Report 4.10

A report on the completed design will come back to members before any construction begins, and any required Traffic Regulation Orders and statutory approvals will be applied for. Report P18, 4.11

Options considered

  • Chosen: Develop the full route from Tarbert to Whitehouse, including Kennacraig Ferry Terminal. Public consultation in 2024 showed support, with 20% backing the full route and only 3% saying no route was needed; scope was extended south to Whitehouse after June 2024 engagement. Report 1.5, 4.6, 4.8
  • Rejected: Limit improvements to within Tarbert. Consultation showed broader demand for connections beyond the village. Report 4.6

Implications

  • Financial: Design and construction are planned to be funded by external applications. The council has not contributed any funding to date. Better active travel could reduce the need for school transport on safety grounds and may cut future health and social care costs.
  • Legal: Continued input from Legal Services will be needed for contracts and any Traffic Regulation Orders required to allow construction.
  • Climate: Active travel is the least carbon intensive mode of travel, so the route is expected to help lower the council's carbon footprint.
  • Equalities: The route is being designed to be Equality Act compliant, providing a safe and accessible route for people with mobility aids, wheelchairs, and parents or guardians with prams or buggies.
  • Risk: There is a reputational risk to the council if the project is not completed within a reasonable timeframe.
  • Other: The project supports the council's Outcomes Improvement Plan outcomes on transport infrastructure and community wellbeing, and supports Scottish Government cycling and walking strategies. Report 6.1

Who and where

  • Residents of Tarbert, Kennacraig and Whitehouse Report 1.1, 1.5
  • Visitors and tourists using the ferry terminals at Tarbert and Kennacraig Report 1.1
  • Island communities that rely on the ferry services
  • Local businesses in Tarbert harbour front and town centre Report 5.1

Timeline

  • May 2024: Feasibility stage (Stage 1) commenced
  • 28 June 2024: First public drop-in event in Tarbert Report 4.5
  • 10 September 2024: Second public drop-in event in Tarbert Report 4.5
  • September/October 2024: Six-week public consultation, 163 survey responses received Report 1.5, 4.5, 4.6
  • November 2024: Feasibility stage completed
  • December 2024: Concept Design stage (Stage 2) commenced Report 4.7
  • Spring 2025: Second round of community engagement during Concept Design Report 1.3
  • Summer 2025: Concept Design stage completed Report 4.7
  • 10 May 2026: Report dated for committee Report P40
  • 3 June 2026: Committee decision taken Report P11

Plain English for the jargon

  • ATIF: Active Travel Infrastructure Fund, Transport Scotland's main competitive fund for active travel projects
  • CTP: Connected Transport Planning, the consultancy awarded the Stages 1 and 2 contract
  • FTE: Full Time Equivalent, used to describe staff resource
  • TRO: Traffic Regulation Order, a legal order that may be needed to allow construction
  • DDA compliant: Designed to meet Disability Discrimination Act accessibility requirements
  • CAPS: Cycling Action Plan for Scotland, a Scottish Government strategy
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

Decision The Mid Argyll, Kintyre and the Islands Area Committee: 1. welcomed the design progress made to date in relation to identifying opportunities to improve the active opportunities between Tarbert and Whitehouse; 2. instructed Officers to undertake Developed Design and Technical Design stages to complete the design process, subject to securing external funding; and 3. instructed Officers to provide a future paper to members on completion of the design process prior to any construction. (Reference: Report by Executive Director with the responsibility for Development and Economic Growth, dated 10 May 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Mid Argyll, Kintyre & the Islands Area Committee

Executive summary

1.1This report updates members on progress made in relation to initial feasibility and concept design to improve active opportunities and infrastructure between Tarbert, Kennacraig Ferry Terminal and Whitehouse.

1.2To date, all work on the A83 Tarbert to Whitehouse Active Travel Project has been externally funded via the Scottish Government’s Active Travel Infrastructure Fund. This highly competitive funding is ring fenced by the Scottish Government for active travel projects which fit the criteria set by the Scottish Government, and cannot be spent on any other activities. For clarity, no Council funding have been expended or committed to this project.

1.3The design team have undertaken community engagement during both of the completed design stages, in September/October 2024 and again in Spring 2025.

1.4The project commenced focusing on the area between the Tarbert Ferry Terminal and the Kennacraig Ferry Terminal. A significant number of potential route options were considered, with the feasibility study narrowing these down to largely following the alignment of the A83 trunk road outside Tarbert, with the route inside Tarbert utilising the existing Tawny Trail and A8015 Pier Road.

1.5A total of 163 survey responses were received to the initial consultation in September/October 2024, with 67 individuals attending the public event in June and 75 attending the September event. Discussions with attendees at the June event indicated a desire for the improvements to extend further south than Kennacraig to include the settlement of Whitehouse. Officers therefore extended the scope of the stage to include exploring options for improvements between Kennacraig Ferry Terminal and Whitehouse. The consultation in September/October sought to identify demand for each section of the route, with 26% of respondents preferring to develop routes with Tarbert, 28% preferred to develop a route between Tarbert to West Loch Shores, 18% preferred to develop a route with between Kennacraig to Whitehouse, 20% thought the focus should be between Tarbert to Whitehouse (full route) while only 3% didn’t think a route was needed.

1.6A potential concept design was developed for the area between the Tarbert Ferry Terminal and Whitehouse taking account of the comments received to the first consultation and sought to balance access and space for all users equitably. To achieve this the design seeks to (a) ensure retention of on street parking and motor vehicle space on roads within Tarbert; (b) retain the function of the A83 trunk road as a strategic route including a high proportion of HGV traffic; and, (c) provide dedicated space for pedestrians and cyclists separate from the existing A83. The proposals also sought to improve wider pedestrian accessibility within Tarbert, as well as proposing renewal of surfacing and lining on streets used by the route within Tarbert.

Recommendations

1.7It is recommended that the Mid Argyll, Kintyre and the Islands members:

1.7.1. Welcome the design progress made to date in relation to identifying opportunities to improve the active opportunities between Tarbert and Whitehouse.

1.7.2. Instruct Officers to undertake Developed Design and Technical Design stages to complete the design process, subject to securing external funding.

1.7.3. Instruct Officers to provide a future paper to members on completion of the design process prior to any construction. ARGYLL AND BUTE COUNCIL Mid Argyll, Kintyre and the Islands

DEVELOPMENT AND ECONOMIC 03 June 2026 GROWTH

A83 Tarbert to Whitehouse Active Travel Project Progress Report

2.0INTRODUCTION

2.1This report updates members on progress made in relation to initial feasibility and concept design to improve active opportunities and infrastructure between Tarbert, Kennacraig Ferry Terminal and Whitehouse.

3.1It is recommended that the Mid Argyll, Kintyre and the Islands members:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A83 TARBERT TO WHITEHOUSE ACTIVE TRAVEL PROJECT PROGRESS REPORTReport 160 KB DownloadRead as text
PDF
A83 Tarbert to Whitehouse Active Travel Project Stage 1 & 2, Options Feasibility ReportAppendix 1 4.9 MB Download
PDF
A83 Tarbert to Whitehouse Active Travel Project Stage 1 & 2, Engagement ReportAppendix 2 4.8 MB Download

At this meeting

Whole meeting

Who was there

8 of 12 attended
JA
Councillor John ArmourChair, present
JB
Councillor Jan BrownMember, present
IC
Iona CampbellSecretary, expected
GC
Councillor Garret CornerMember, present
AH
Councillor Anne HornMember, present
JK
Councillor Jennifer KeanMember, apologies
TM
Councillor Tommy MacPhersonMember, present
DM
Councillor Dougie McFadzeanVice-Chair, present
KM
Katie McKenzieSecretary, expected
JS
Julieann SmallSecretary, expected
DP
Councillor Dougie PhilandMember, present
AR
Councillor Alastair RedmanMember, present

On this subject at Argyll and Bute

Search all
  1. A83 TARBERT TO WHITEHOUSE ACTIVE TRAVEL PROJECT PROGRESS REPORTThis decision
  2. Consider notice of review request: land north east of arivore farm, whitehouse, tarbert, argyll, pa29 6xr (ref: 14/0002/lrb)Agreed

More from Argyll and Bute Mid Argyll, Kintyre & the Islands Area Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... Noted Open
2 Sep 2026 Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... Agreed Open
2 Sep 2026 Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... Noted Open
2 Sep 2026 Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... Noted Open
2 Sep 2026 Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies