HEALTH AND SOCIAL CARE PARTNERSHIP - PERFORMANCE REPORT FQ3 2025/26 (OCTOBER - DECEMBER)
NotedCommittee2 papers
AI summaryMid Argyll, Kintyre and the Islands Area Committee noted health and social care performance for October to December 2025, with 35 of 77 key indicators on target and delayed discharges above the Scottish average.
Written from the decision and the officer reportPDF Pro
OutcomeNoted35 of 77 KPIs on target, 45 percent
MoneyNot stated
What happens nextPerformance reporting continuesAnnual IPMF KPI review for 2026/27
Who it affectsHSCP service users and staffAcross 12 service reporting categories
What was decided
The committee acknowledged FQ3 2025/26 performance against 77 Key Performance Indicators within the Integrated Performance Management Framework. Report P2, P4
Members noted the latest Delayed Discharge Sitrep as of 16 February 2026, showing 73 per 100,000 population, up from 46 at the December 2025 census. Report P12, P35
The committee acknowledged performance against the 26 National Health and Wellbeing Outcomes and Ministerial Steering Group Integration Indicators, with 50 percent on track. Report P16, P36
Why
The HSCP Senior Leadership Team is reviewing the Integrated Performance Management Framework to give a more focused approach to national pressures on Urgent and Unscheduled Care, Planned Care and the NHS Highland Operational Improvement Plan. Report P2, P17, P18
The new suite of metrics is intended to show Argyll and Bute's progress within Board level performance and to present service-led feedback across the framework. Report P18
Monitoring and reporting against KPIs ensures the HSCP delivers against key strategic priorities and aligns with the Strategic Plan. Report P19
What happens next
Additional metrics around CfSD and Planned Care will continue to be developed and threaded through Argyll and Bute performance reporting cycles. Report P10, P18
An annual IPMF KPI review for 2026/27 is planned alongside the current reporting cycle. Report P10, P18
The IPMF Dashboard will continue to support self-service performance information for HSCP professional advisors via SharePoint. Report P23
Options considered
Chosen: Acknowledge FQ3 2025/26 performance against KPIs. Standard performance reporting against the Integrated Performance Management Framework Report P4
Chosen: Note the Delayed Discharge Sitrep as of 16 February 2026. To keep the committee informed of the latest delayed discharge position Report P4, P12
Chosen: Acknowledge National Health and Wellbeing Outcomes and MSG Indicators. These form the basis of the annual reporting requirement for Health and Social Care Partnerships across Scotland Report P4, P14
Implications
Governance: Clinical and Care Governance Committee remains central to performance improvement, with a move away from traditional reporting to a fully collaborative approach with Head of Service commentary. Report 6.3
Risk: Performance reports are used by operational management to identify service delivery risk and inform mitigation action. Report P25
Equalities: The IPMF captures relevant indicators to inform HSCP equalities work, including Child (UNCRC), Islands, Fairer Scotland and Socio-economic Duty. Report P24
Staffing: KPIs ensure staff governance requirements continue to be progressed, covering health and safety, wellbeing and new service redesign. Report P20
Other: Data use and sharing is covered within the Argyll and Bute Council and NHS Highland Data Sharing Agreement. Report P25
Who and where
People using health and social care services, carers and families in the Mid Argyll, Kintyre and the Islands area Report P14
HSCP staff across 12 service reporting categories Report P8, P20
Argyll and Bute Council and NHS Highland as partner bodies Report P26, P29
Timeline
October to December 2025: FQ3 2025/26 performance reporting period Report P1, P5
December 2025: Census point with 46 delayed discharges (weekly average) Report P12, P35
16 February 2026: Delayed Discharge Sitrep shows 73 per 100,000 population Report P12, P35
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
Decision The Mid Argyll, Kintyre and the Islands Area Committee: 1. Acknowledged the performance for FQ3 2025/26 (October – December) against latest Key Performance Indicators within the Integrated Performance Management Framework for 2025/26; 2. noted the latest Delayed Discharge Sitrep as of 16 Feb 2026, as at Appendix 1 of the report; 3. acknowledged the latest performance against the National Health and Wellbeing Outcomes and Ministerial Steering Group Integration Indicators, as at Appendix 2 of the report; and 4. acknowledged the inclusion of additional Argyll and Bute Health and Social Care performance metrics aligned to national reporting across Centre for Sustainable Delivery Unscheduled Care, and the Planned Care performance focus within the Operational Improvement Plan, as at Appendix 3 of the report. (Reference: Report by Performance and Information Team Manager, Argyll and Bute Health and Social Care Partnership, dated June 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Executive summary
This report details performance for the Financial Quarter (FQ) 3 2025/26 (October – December). The key performance outputs are taken from the current Integrated Performance Management Framework (IPMF) Reporting Dashboard.
Overall performance for FQ3 notes 35 of 77 measures reported as on target (45%). National Delayed Discharge Sitrep and the National Health & Wellbeing Indicators performance are also provided. The HSCP Senior Leadership Team is currently reviewing the content and structure of the Integrated Performance Management Framework and has refreshed the performance metrics being presented before the IJB in a new suite of measures (Appendix 3). The new suite of measures is designed to offer a more focused approach to national pressures around Centre for Sustainable Delivery’s (CfSD) Urgent & Unscheduled Care, Planned Care and NHS Highland Operational Improvement Plan (OIP), including scope for service feedback.
2. RECOMENDATIONS The Area Committee is asked to:
1 • Acknowledge performance for FQ3 2025/26 (October –December) against latest Key Performance Indicators within the Integrated Performance Management Framework for 2025/26 • Note latest Delayed Discharge Sitrep as of 16 Feb 2026 (Appendix 1) • Acknowledge latest performance against the National Health & Wellbeing Outcomes and Ministerial Steering Group Integration Indicators (Appendix 2) • Acknowledge the inclusion of additional A&B HSCP performance metrics aligned to national reporting across Centre for Sustainable Delivery (CfSD) Unscheduled Care, and the Planned Care performance focus within the Operational Improvement Plan (OIP) (Appendix 3)
3. DETAIL OF REPORT The report details the HSCP (Health and Social Care Partnership) performance for FQ 3 2025/26 (October - December), highlighting key performance trends across the 77 KPIs (Key Performance Indicators). For 2025/26, the latest national update on Delayed Discharges (Appendix 1), alongside the latest performance on the National Health and Wellbeing Outcomes Indicators (Appendix 2) have been included. Additional performance metrics aligned to Urgent & Unscheduled Care, Planned Care and NHS Highland OIP NHS Highland’s OIP are reported within Appendix 3.
Overall performance for FQ3 notes that 77 KPI’s are scoring against a target, with 36 (47%) reporting as OnTrack. The KPI’s report performance against the target and include the target, actual and variance and is a mix of both quantitative and qualitative indicators. The use of the green, amber and red graphics within the Dashboard is used to give an overview of the HSCP’s total performance for each of the twelve services and 77 KPI’s. The use of only green and red for the KPI’s is used to focus delivery with regards to sustaining performance on or above target. Additional metrics around CfSD and Planned Care are reported within Appendix 3 and will continue to be developed and threaded through A&B performance reporting, in conjunction with the current reporting cycle and the annual IPMF KPI review for 2026/27.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.