Argyll and Bute Council
Policy and Resources Committee, Thursday 20 August 2026 at 10.30am

LORN ARC TIF PROGRAMME DUNBEG CORRIDOR UPDATE

Noted Committee 1 paper

AI summaryArgyll and Bute Policy and Resources Committee noted the update on the Lorn Arc TIF Dunbeg Corridor project, covering 433 houses, a new trunk road roundabout and a commercial area, with site works expected by early 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee considered the update on progress
Money£640k start up costs approvedPlus projected £179m Net Present Value
What happens nextFull Business Case late 2026Site start on groundworks late 2026 or early 2027
Who it affectsOban area residents and economy433 new houses plus commercial development

What was decided

The Committee noted the content of the update report on the Lorn Arc Tax Incremental Finance Dunbeg Corridor project.

No new funding was approved at this meeting; £640k of TIF start up money previously approved will be used to help LINK Housing Association cover detailed design and costings work. Report 1.3, 4.8

Why

LINK Housing Association gained planning consent in March 2026 for 433 houses, a new A85 trunk road roundabout, a commercial area and associated road infrastructure, and acquired the site the same month. Report P12, P13, P14

The Scottish Government extended the TIF agreement by ten years in January 2025, so it now runs until 2050, giving the Council more time to recoup investment from non domestic rates. Report 4.1

What happens next

LINK will progress detailed design and costings, with the Council assisting using the £640k TIF start up money; a Full Business Case is expected towards the end of 2026. Report 4.8, 4.9

Officers will work with Scottish Government More Homes, HIE and other funders to develop a full funding package, with no formal agreements yet in place. Report 4.11

Site start on groundworks is anticipated late 2026 or early 2027, with the affordable housing phase due for completion in 2032. Report 4.7

The money

  • £640k TIF start up costs previously approved for detailed design Report 1.3, 4.8
  • £179m Projected Net Present Value added to the local area Report 1.2, 5.1
  • circa £7m Scottish Government More Homes Division grant that funded land purchase

Options considered

  • Chosen: Note the contents of the report. Officers recommended that Members consider the progress update Report 3.1

Implications

  • Financial: No direct financial implications arise from this report; the Full Business Case will set out detailed development costs and the financial position for Committee approval, expected towards the end of 2026. Report 4.9, 6.0
  • Risk: The report flags risks of depopulation and economic damage if the housing emergency is not tackled, plus unforeseen rises in development costs and uncertainty over non domestic rate income to repay TIF debt. Report 6.0
  • Climate: New housing in suitable locations, built with renewable energy and other measures, can help reduce carbon emissions. Report 6.0
  • Equalities: The development is consistent with LDP2 and the Local Housing Strategy, which are subject to Equality Impact Assessment, and supports economic and social opportunities under the Fairer Scotland Duty. Report 6.0

Who and where

  • Residents of the Oban area needing new housing Report 1.2, 5.1
  • Future tenants and buyers across social rent, mid market rent, shared equity, elderly living, student accommodation and private sale Report P13
  • Local economy and businesses in Argyll and Bute Report 1.2, 5.1
  • Members of the Dunbeg Corridor Working Group including the Council, local Members, public agencies and the public Report 4.12

Timeline

  • January 2025: Scottish Government extended the TIF agreement by ten years to 2050 Report 4.1
  • March 2026: Planning consent granted for the Dunbeg Corridor development
  • March 2026: LINK acquired the land, funded by a circa £7m Scottish Government grant
  • 10th April 2026: Last meeting of the Dunbeg Corridor Working Group Report 4.12
  • 20th August 2026: Policy and Resources Committee noted the update report Report P5
  • End 2026 or early 2027: Indicative site start on groundworks Report 4.7
  • Towards the end of 2026: Full Business Case anticipated for Committee approval Report 4.9, 5.1
  • 2032: Indicative completion of the affordable housing phase Report 4.7

Plain English for the jargon

  • TIF: Tax Incremental Finance, a mechanism that lets a council borrow against future increases in non domestic rates from a development area
  • NDR: Non Domestic Rates, the business rates collected by councils
  • NPV: Net Present Value, the total value of future benefits and costs expressed in today's money
  • MMR: Mid Market Rent, rents set below market rate but above social rent
  • NSSE: New Supply Shared Equity, a Scottish Government shared ownership scheme
  • RSL: Registered Social Landlord, a housing association or similar not for profit landlord
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

Decision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated July 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy and Resources Committee

Executive summary

1.1The last update to Members on progress with the Lorn Arc Tax Incremental Finance (TIF) project at Dunbeg, was the 9th October 2025 OCTOBER 2025 Lorn Arc TIF Update P&R Report.pdf . This report provides an update on progress at Dunbeg since that time, and an indication of likely short and medium term activity. The report does not cover the Oban Airport Business Park TIF project which has been reported on separately.

1.2Significant progress is being made to bring forward the next stage of Dunbeg development which includes 433 houses, a new Trunk Road Roundabout, a commercial area development platform, and associated road infrastructure to serve all of this. Not only will it deliver much needed housing supply in the Oban area, but it has the potential to create a significant economic boost and add £179m in Net Present Value to the area. Having gained planning consent in March 2026, and purchased the site also in March 2026, LINK RSL is now progressing detailed design and costing work. When this is complete it will enable a full business case to be presented to the Council in order to secure a funding package for the infrastructure development. This is anticipated towards the end of 2026.

1.3The Council previously approved £640k of startup costs for the Dunbeg TIF project. These will be used to assist LINK in covering the detailed design and costings work which will now be required.

Recommendation

Members of the Policy and Resources Committee are asked to consider the content of the report. ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE DEVELOPMENT AND ECONOMIC GROWTH 20th AUGUST 2026

LORN ARC TIF PROGRAMME DUNBEG CORRIDOR UPDATE

2.0INTRODUCTION

2.1The last update to Members on progress with the Lorn Arc Tax Incremental Finance project at Dunbeg was the 9th October 2025 OCTOBER 2025 Lorn Arc TIF Update P&R Report.pdf . This report provides an update on progress at Dunbeg since that time, and an indication of likely short and medium term activity. The report does not cover the Oban Airport Business Park TIF project which has been reported on separately.

Recommendations

3.1Members of the Policy and Resources Committee are asked to consider the content of the report.

4.0DETAIL

4.1Members may recall that in January 2025 Scottish Government agreed a formal extension to the TIF agreement extending it by ten years such that it now runs until 2050. This is significant in that it gives a further ten years for the Council to retain Non Domestic Rate (NDR) revenue that has been created since the creation of the TIF scheme and reduces the risk involved in repaying the investment needed to allow the TIF projects to be delivered. Notwithstanding this, the earlier the developments can be delivered, the lower the likely construction costs that will be incurred, and the longer the time period that any new NDR paying development created can contribute to repaying that investment.

4.2The first 3 phases of development at Dunbeg have already been developed and are shown below. 4.3 In March 2026, LINK Housing Association was granted planning consent for four planning applications within the Dunbeg Corridor. These are for: - • the commercial area development which includes an hotel, drive through restaurants and small supermarket.

• phase 4 of the housing development (c433 houses) including social rent, mid-market rent, student housing, shared equity, private sale and plots.

• Social Rent = 150 No • Mid-Market Rent (MMR) – 48 No • New Supply Shared Equity (NSSE) – 40 No • Elderly Living – 31 No (16 NSSE & 15 Rent) • Student Accommodation – 31 No • Private Housing – 133 No. • A new Trunk Road roundabout.

• The associated road network leading to the commercial area and housing site. 4.4 The layout of the consented Phase 4 housing proposal is shown below:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LORN ARC TIF PROGRAMME DUNBEG CORRIDOR UPDATEReport 634 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 18 attended
KM
Katie McKenzieSecretary, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairMember, present
MC
Councillor Math Campbell-SturgessMember, apologies
KG
Councillor Kieron GreenMember, present
AH
Councillor Amanda HampseyMember, present
AK
Councillor Andrew KainMember, absent
RK
Councillor Reeni Kennedy-BoyleMember, present
JL
Councillor Jim LynchChair, present
LM
Councillor Luna MartinMember, present

All 18 on the meeting page

On this subject at Argyll and Bute

Search all
  1. LORN ARC TIF PROGRAMME DUNBEG CORRIDOR UPDATEThis decision
  2. Lorn arc tax incremental finance (tif) updateNoted
  3. Lorn arc tax incremental finance programme - oban airport business park - updateNoted
  4. Lorn arc tax incremental finance programme - update reportNoted
  5. Lorn arc programme updateNoted
  6. Lorn arc tax incremental finance programme - update reportNoted

More from Argyll and Bute Policy and Resources Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... Agreed Open
20 Aug 2026 Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... Noted Open
20 Aug 2026 Potential impact of iran conflict - updateDecision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section ... Noted Open
20 Aug 2026 Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... Agreed Open
20 Aug 2026 Scottish languages act 2025 - areas of linguistic significanceDecision The Policy and Resources Committee – 1. noted the progress being made to ensure that the Council meets its s... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies