CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Policy and Resources Committee, Thursday 20 August 2026 at 10.30am

COMMUNITY REGENERATION PARTNERSHIP FUND - PROGRAMME UPDATE

Noted Committee 2 papers

AI summaryArgyll and Bute Council's Policy and Resources Committee noted progress on the £20.34m Community Regeneration Partnership Programme and delegated authority to the Executive Director to approve change requests in line with the agreed Memorandum of Understanding.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFurther report to come to next committee
Money£20.34mFull CRP funding received from UK Government
What happens nextFurther report to next meetingPolicy and Resources Committee to receive update
Who it affectsCommunities across Argyll and ButeMultiple housing, regeneration and infrastructure projects

What was decided

The Committee noted progress on delivery of the £20.34m Community Regeneration Partnership Programme, including governance, monitoring and risk arrangements, and the status of individual projects. Report 3.0, 5.0

Authority was delegated to the Executive Director for Development and Infrastructure Services, in consultation with the Council Leader and Depute Leaders, to approve change requests to the programme in line with the agreed Memorandum of Understanding. Report 3.0, P9

Members noted that a further report on the programme would be brought to the next Policy and Resources Committee meeting. Report 3.0, P9

Why

The UK Government approved a £20.34m package of CRP funding in November 2025, comprising £20m capital, £250,000 revenue and £90,000 capacity funding, to address spatial inequalities and support place-based economic growth in Argyll and Bute. Report 1.2

A portfolio of housing, regeneration, economic development and community infrastructure projects was approved by UK Ministers, with a Memorandum of Understanding signed in November 2025 establishing governance and monitoring arrangements. Report 4.1, 4.5

The principal programme risk is the requirement to defray the full £20m capital funding in 2026-27; the Project Manager has requested urgent clarification of spend deadlines from the UK Government and is awaiting a formal response. Report 1.5

What happens next

A change request submitted to the UK Government in May 2026 seeks approval to transfer £300,000 from the European Marine Science Site (Camas House) to the Oban Airport Aviation Business Park; formal approval is still awaited.

The next quarterly Monitoring Report is due to be submitted to the Ministry of Housing, Communities and Local Government in August 2026. Report 4.6

Officers will continue to work with delivery partners and MHCLG to manage identified risks, including defrayment deadlines, and a further report will come to the next Policy and Resources Committee. Report 3.0

The money

  • £20.34m Total CRP funding package approved by UK Government for Argyll and Bute Report 1.2
  • £20m Capital funding received by the Council Report 1.2, 4.9
  • £250,000 Revenue funding received by the Council Report 1.2, 4.9
  • £90,000 Capacity funding (revenue) received by the Council Report 1.2, 4.9
  • £300,000 Proposed transfer from European Marine Science Site to Oban Airport Aviation Business Park (change request)
  • £1.3m Latest cost projection for ground-floor fit-out of Camas House (original £1.6m)

Options considered

  • Chosen: Transfer £300,000 from European Marine Science Site (Camas House) to Oban Airport Aviation Business Park. Shortfall in budget for Oban Airport Business Park; ground-floor fit-out cost projection reduced from £1.6m to £1.3m
  • Chosen: Submit further change requests for the CRP programme. Authority delegated to the Executive Director in consultation with the Council Leader and Depute Leaders to approve change requests in line with the MoU Report 3.0

Implications

  • Financial: Full £20.34m allocation received; defrayment of £20m capital in 2026-27 remains a key programme consideration pending UK Government clarification. Report 1.5
  • Legal: Significant legal support is required to provide advice on all CRP projects and to draft funding agreements for external projects; external legal support has been procured. Report 4.5
  • Risk: A programme risk register is maintained and reviewed regularly; principal risk is the defrayment deadline for capital funding. Report 1.5, 4.8
  • Staffing: A Project Manager and an Administration and Finance Assistant have been appointed within the Transformational Projects and Regeneration Team to lead delivery. Report 4.3
  • Equalities: Equality Impact Assessments are undertaken where required; multiple projects directly benefit island communities.
  • Climate: Each CRP project is required to have regard to climate change implications.

Who and where

  • Communities across Argyll and Bute, including island communities
  • Housing sector and Registered Social Landlords in Argyll and Bute Report P25
  • Delivery partners including SAMS, the European Marine Science Site, Highlands and Islands Enterprise and community organisations Report 4.4, P25

Timeline

  • November 2025: UK Government approved £20.34m CRP funding package and Memorandum of Understanding was signed Report 1.2
  • 26 November 2025: Council received an update report on Oban Airport Business Park which first referenced the proposed funding transfer
  • May 2026: First quarterly Monitoring Report submitted to and approved by MHCLG; first change request submitted to UK Government to transfer £300,000 between projects Report 4.6
  • 02/07/2026: Report by Executive Director dated for committee consideration Report P33
  • August 2026: Next quarterly Monitoring Report due to be submitted to MHCLG Report 4.6
  • 20 August 2026: Policy and Resources Committee noted the programme update and delegated change request authority Report P2
  • December 2026: First building at Oban Airport Aviation Business Park due for completion Report P25
  • 31st March 2027: UK Government deadline by which capital funding is to be defrayed; Council understanding is that spend beyond this date is possible if funding is fully committed in advance Report 1.5
  • April 2027: Projected site start date for the Former Royal Hotel, Rothesay development Report P25

Plain English for the jargon

  • CRP: Community Regeneration Partnership, a UK Government programme to address spatial inequalities and support place-based economic growth
  • MHCLG: Ministry of Housing, Communities and Local Government
  • MoU: Memorandum of Understanding, signed in November 2025 to establish CRP programme governance and monitoring
  • Defray: To spend or pay out funds; here refers to the requirement to use capital funding within the financial year
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

Decision The Policy and Resources Committee – 1. noted progress with delivery of the Community Regeneration Partnership Programme (CRP), the current status of projects as set out in Table 1 of the submitted report, and the associated governance, monitoring and risk arrangements for the CRP programme; 2. delegated authority to the Executive Director for Development and Infrastructure Services in consultation with the Council Leader and Depute Leaders to approve change requests relating to the programme in line with the agreed Memorandum of Understanding; and 3. note that a further report would be brought to the next Policy and Resources Committee meeting. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 2 July 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy and Resources Committee

ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE

DEVELOPMENT AND ECONOMIC 20 AUGUST 2026 GROWTH

COMMUNITY REGENERATION PARTNERSHIP FUND – PROGRAMME UPDATE

1.0EXECUTIVE SUMMARY 1.1 The purpose of this report is to update members on the progress of the UK Government’s Community Regeneration Partnership (CRP) Programme and associated projects.

1.2In November 2025 the UK Government (UKG) approved a package of £20.34m CRP funding, comprising £20m capital funding, £250,000 revenue funding and £90,000 of associated capacity funding for Argyll and Bute. The Council has received the full funding allocation.

1.3Programme governance arrangements are in place, and quarterly monitoring reports are being submitted to the Ministry of Housing, Communities and Local Government (MHCLG).

1.4The agreed funding package was developed in partnership with Argyll and Bute Council to boost economic development opportunities and drive positive change across our communities.

1.5The principal programme risk relates to the requirement that the full £20m capital funding is defrayed in 2026-27. The CRP Project Manager has requested urgent clarification of spend deadlines with the UKG and is awaiting a formal response. It remains the Council’s understanding that spend is possible beyond the 31st March 2027 providing that funding is fully committed in advance.

RECOMMENDATIONS The Policy and Resources Committee are asked to:- a) Note progress with delivery of the Community Regeneration Partnership Programme (CRP), the current status of projects as set out in Table 1 of the report, and the associated governance, monitoring and risk arrangements for the CRP programme. b) Delegate authority to the Executive Director for Development and Infrastructure Services in consultation with the Council Leader and Depute Leaders to approve change requests relating to the programme in line with the agreed Memorandum of Understanding. c) Note that a further report will be brought to the next Policy and Resources Committee meeting. ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE

DEVELOPMENT AND ECONOMIC 20 AUGUST 2026 GROWTH

COMMUNITY REGENERATION PARTNERSHIP FUND – PROGRAMME UPDATE

2.0INTRODUCTION 2.1 The purpose of this report is to update members on the progress of the Community Regeneration Partnership (CRP) Programme and associated projects. 2.2 The Community Regeneration Partnership (CRP) Fund is a UK Government programme established to address spatial inequalities and support place-based economic growth. 2.3 In November 2025 the UK Government (UKG) approved a package of £20.34m CRP funding, comprising £20m capital funding, £250,000 revenue funding and £90,000 of associated capacity funding for Argyll and Bute. The Council has received the full funding allocation.

3.0RECOMMENDATIONS 3.1 The Policy and Resources Committee are asked to:- a) Note progress with delivery of the Community Regeneration Partnership Programme (CRP), the current status of projects as set out in Table 1 of the report, and the associated governance, monitoring and risk arrangements for the CRP programme. b) Delegate authority to the Executive Director for Development and Infrastructure Services in consultation with the Council Leader and Depute Leaders to approve change requests relating to the programme in line with the agreed Memorandum of Understanding. c) Note that a further report will be brought to the next Policy and Resources Committee meeting.

4.0DETAIL

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk-Register-CRP-0.1Appendix 1 202 KB Download
PDF
COMMUNITY REGENERATION PARTNERSHIP FUND: PROGRAMME UPDATEReport 223 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 18 attended
KM
Katie McKenzieSecretary, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairMember, present
MC
Councillor Math Campbell-SturgessMember, apologies
KG
Councillor Kieron GreenMember, present
AH
Councillor Amanda HampseyMember, present
AK
Councillor Andrew KainMember, absent
RK
Councillor Reeni Kennedy-BoyleMember, present
JL
Councillor Jim LynchChair, present
LM
Councillor Luna MartinMember, present

All 18 on the meeting page

On this subject at Argyll and Bute

Search all
  1. COMMUNITY REGENERATION PARTNERSHIP FUND - PROGRAMME UPDATEThis decision
  2. Community regeneration partnership fundingApproved
  3. Tackling Poverty and Community Regeneration FundingAgreed
  4. Update on the community learning and regeneration strategy 2008 - 2011Noted
  5. Report by Head of Community Regeneration and Senior Estates Surveyor in regard to land at DalrighAgreed
  6. Community learning and regeneration strategy 2008-2011Agreed

More from Argyll and Bute Policy and Resources Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... Agreed Open
20 Aug 2026 Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... Noted Open
20 Aug 2026 Potential impact of iran conflict - updateDecision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section ... Noted Open
20 Aug 2026 Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... Agreed Open
20 Aug 2026 Scottish languages act 2025 - areas of linguistic significanceDecision The Policy and Resources Committee – 1. noted the progress being made to ensure that the Council meets its s... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies