RESOLVED That all infrastructure providers be invited to provide any updated information on the status of existing projects on the IIP and whether there were any potential new projects that providers may like to be considered for assessment and prioritisation.
Word for word from the decision Arun published for this meeting.Source: democracy.arun.gov.uk
1.1This report seeks to update the Committee on the Infrastructure Investment Plan 2022-2024 (IIP) and work scheduled for 2023 before the IIP is updated fully in 2024. Under the Council’s Governance procedures (Background Paper 1 Governance) there will be a ‘light touch’ update in 2023 to existing projects on the IIP including any potential new projects that might added and how they will be assessed.
Recommendations
2.1Planning Policy Committee resolves that:-
i. All infrastructure providers be invited to provide any updated information on the status of existing projects on the IIP and whether there are any potential new projects that providers may like to be considered for assessment and prioritisation.
Executive summary
3.1Arun District Council became a Community Infrastructure Levy (CIL) Charging Authority in April 2020. A CIL Governance process was approved at Full Council on 25th January 2021 which set out how CIL infrastructure proposals will be prioritised. This lead to the preparation of a 3-year Infrastructure Investment Plan (for the period 2022-2024) which was approved by the Council on 9 March 2022.
3.2The IIP process includes Arun District Council undertaking consultations with infrastructure providers and Town/Parish Councils, inviting project bids and supporting evidence, to help identify infrastructure projects eligible for funding and prioritisation assessment.
3.3The approved IIP 2022-2024 includes a ‘shortlist’ of 5 priority projects that were identified for funding, following the IIP consultation process carried out in 2021, over the three years (Background Paper 2) and the proposed spend apportionment for those projects. In addition, a ‘baseline list’ or long list (Background Paper 3) has been produced to sit alongside the priority list and this has been assessed (and prioritised according criteria with a Red, Amber, Green coding i.e. RAG assessment).
3.4In accordance with the Governance procedures, the short list and baseline list will be kept under review following a ‘light touch approach’ in the intervening year, as the status and priority of projects changes over time (e.g. where there is updated or new evidence informing funding, delivery and priortisation).
3.5In accordance with the Governance procedures, master contracts have now been drawn up for West Sussex County Council and Arundel Town Council for their respective projects that are included on the ‘short list’. Once signed, the master contracts will be sealed ready for transfer of funds when requested by the provider and appended with a project profoma evidencing delivery.
3.6A sum of £5,560.00 will shortly be transferred to Arundel Town Council for their project at Priory Pocket Park following the reciept of a signed and sealed master contract and proforma.
3.7A total CIL income of £359k was received in 2021/2022. It is anticiapted that a similar level of CIL receipts may be accrued in 2023 net of any CIL relief granted.
3.8The table shows the total CIL funds transferred to Town and Parish Council’s since CIL charging was introduced in April 2020:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Committee Revenue Budget 2026/27RESOLVED to Agree the 2026/27 Revenue Budget as set out in Appendix A and recommends to the Policy and Resources Comm...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.